United States ex rel. Pileco, Inc. v. Slurry Systems, Inc.

804 F.3d 889, 2015 WL 6500193
CourtCourt of Appeals for the Seventh Circuit
DecidedOctober 28, 2015
DocketNos. 14-1267, 14-1283, 14-1342
StatusPublished
Cited by13 cases

This text of 804 F.3d 889 (United States ex rel. Pileco, Inc. v. Slurry Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Pileco, Inc. v. Slurry Systems, Inc., 804 F.3d 889, 2015 WL 6500193 (7th Cir. 2015).

Opinion

POSNER, Circuit Judge.

We begin by introducing the parties, and their dealings out of which this case arises. Pileco, the plaintiff and appellee— a wholly owned subsidiary of the other appellee, Bauer — sells and leases machinery for use in construction projects. One of the machines Pileco sells and leases is a trench cutter manufactured by Bauer. It is a huge steel machine — roughly 40 feet high and weighing 40 tons — designed to cut into bedrock. It is moved about by a crane manufactured by a different company. (It has motorized wheels, but they’re just used to dig into the ground.)

In 2005 the Army Corps of Engineers invited bids on a federal reservoir project in Illinois. One of the successful bidders was Slurry Systems, Inc. Slurry (as we’ll call the company for short) leased from Pileco one of the trench cutters made by Bauer. (For simplicity we’ll usually use “Pileco” to denote both the parent and the subsidiary.)

Slurry was a prime contractor on the Corps of Engineers’ project and, pursuant [891]*891to the Miller Act, 40 U.S.C. § 3131 et seq., which requires prime contractors on some government construction projects to post bonds guaranteeing both the performance of the prime contractor’s contractual undertakings and the payment by the prime contractor of its subcontractors and material suppliers, had posted the required payment bond using Fidelity & Deposit Co. of Maryland as surety. The bond insured against a failure by Slurry to pay subcontractors, such as Pileco. Contending that the cutter was defective, Slurry refused to pay the agreed rental price for the cutter’s use, and Pileco sued both it and Fidelity for the payment shortfall. Filed in the federal district court in Chicago, Pileco’s suit accused Slurry of breach of its contract for the lease of the cutter (and of miscellaneous associated parts, which we can ignore because they don’t present distinct issues) in violation of Illinois common law. And it accused Fidelity of violating the Miller Act by failing to reimburse Pileco for costs imposed on it by Slurry’s reneging on its obligation to pay Pileco the agreed-upon rental price for the cutter.

The complaint based federal jurisdiction on the section of the Miller Act that authorizes a civil suit to recover money owing under a payment bond for a federal project. 40 U.S.C. § 3133(b). The Miller Act claim also conferred jurisdiction over Pileco’s state-law claim against Slurry under the grant of supplemental jurisdiction in 28 U.S.C. § 1367, thus providing a federal jurisdictional basis for the state law claims. The court also had jurisdiction to hear those claims pursuant to 28 U.S.C. § 1332 (diversity).

Slurry counterclaimed, claiming that Pi-leco had violated the lease and engaged in fraud by supplying a defective cutter. The parties agreed to a jury trial to be presided over by Magistrate Judge Keys. The trial took eight days and resulted in a verdict that awarded Pileco $2 million on its breach of contract claim against Slurry and $1 million on its payment-bond claim against Fidelity, but that also awarded Slurry $600,000 on its breach of contract counterclaim against Pileco. The verdict form had directed the jury, in the event that it awarded Pileco damages, to calculate the damages to which Slurry might be entitled by a provision of the contract that granted Slurry an “equitable adjustment” — an offset against the rental price — for periods when the cutter had been unusable because of a defect attributable to Pileco. Despite the instruction to determine the equitable adjustment if it awarded damages to Pileco, the jury left the space for the answer to that question in the verdict form blank.

Slurry had also filed a third-party breach of contract claim against Bauer, and the jury awarded $3.4 million on that claim and another $1 million on express and implied warranty claims by Slurry against Pileco and Bauer. Awarding Slurry $600,000 against Pileco for breach of contract but $3.4 million against Bauer for breach of the leasing agreement is perplexing because there was only one contract (the lease of the cutter), for which Pileco served as Bauer’s agent, and Bauer’s and Pileco’s interests and trial strategy were generally aligned. Finally and most dramatically (or absurdly), the jury awarded Slurry $20 million in punitive damages (and nothing in compensatory damages) on a claim by Slurry that Bauer had violated the Illinois Consumer Fraud and Deceptive Business Practices Act, 815 ILCS 505/2.

So when the dust settled, Slurry had netted $3 million in compensatory damages against Pileco and Bauer ($3.4 million + $1 million + $600,000 — $2 million) and $20 million in punitive damages. The jury had [892]*892ignored the claim for equitable adjustment despite Pileco’s having acknowledged that it had some merit and despite the instruction to the jury to determine an adjustment amount.

The likeliest reason for the bollixed verdict is the jury instructions, the preparation of which the judge had largely left to the rival lawyers. Even after the judge made some alterations, the instructions (including the verdict form) were far too long (57 pages) and technical for a jury to be expected to understand. The judge and even the parties acknowledged the defects in the instructions after they saw the jury’s verdict.

Obviously the verdict couldn’t stand. Apart from the jury’s having overlooked the issue of equitable adjustment even though it was stated on the verdict form, punitive damages can’t lawfully be awarded when no compensatory damages are awarded. Illinois law allows suit only by someone who “suffers actual damage as a result of a violation of’ the Consumer Fraud Act, 815 ILCS 505/10a(a); Avery v. State Farm Mutual Automobile Ins. Co., 216 Ill.2d 100, 296 Ill.Dec. 448, 885 N.E.2d 801, 858-61 (2005). The award of zero compensatory damages to Slurry on its fraud claim implied that Slurry had incurred no harm from Bauer—and without proof of “actual damage” punitive damages can’t be awarded. Hayman v. Autohaus on Edens, Inc., 315 Ill.App.3d 1075, 248 Ill.Dec. 721, 734 N.E.2d 1012, 1015 (2000). Also there are constitutional limits on the ratio of punitive to compensatory damages. See BMW of North America, Inc. v. Gore, 517 U.S. 559, 580-83, 116 S.Ct. 1589, 134 L.Ed.2d 809 (1996); Keeling v. Esurance Ins. Co., 660 F.3d 273, 275 (7th Cir.2011). The ratio of $20 million to zero is not two to one or a hundred to one or 20 million or any other number to one; it is undefined, like any other division by zero.

Judge Keys ordered a retrial, as authorized by Fed.R.Civ.P. 59

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
804 F.3d 889, 2015 WL 6500193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-pileco-inc-v-slurry-systems-inc-ca7-2015.