United States ex rel. International Business Machines Corp. v. Hartford Fire Insurance

112 F. Supp. 2d 1023, 2000 U.S. Dist. LEXIS 13367
CourtDistrict Court, D. Hawaii
DecidedJuly 19, 2000
DocketNo. 99-00437 DAE
StatusPublished
Cited by1 cases

This text of 112 F. Supp. 2d 1023 (United States ex rel. International Business Machines Corp. v. Hartford Fire Insurance) is published on Counsel Stack Legal Research, covering District Court, D. Hawaii primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. International Business Machines Corp. v. Hartford Fire Insurance, 112 F. Supp. 2d 1023, 2000 U.S. Dist. LEXIS 13367 (D. Haw. 2000).

Opinion

ORDER DISMISSING DEFENDANT HARTFORD FIRE INSURANCE COMPANY’S COUNTER MOTION FOR SUMMARY JUDGMENT; GRANTING IN PART AND DENYING IN PART PLAINTIFF UNITED STATES OF AMERICA FOR THE USE AND BENEFIT OF INTERNATIONAL BUSINESS MACHINES CORPORATION’S MOTION FOR SUMMARY JUDGMENT; AND GRANTING PLAN-TIFF UNITED STATES OF AMERICA FOR THE USE AND BENEFIT OF INTERNATIONA BUSINESS MACHINES CORPORATION’S MOTION TO STRIKE DEFENDANT HARTFORD FIRE INSURANCE COMPANY’S DISCLOSURE OF EXPERT WITNESSES AND PRECLUDE EXPERT TESTIMONY AS MOOT

DAVID ALAN EZRA, Chief Judge.

The court heard arguments on July 18, 2000. Kenneth R. Kupchak, Esq., appeared at the hearing on behalf of Plaintiff; Harvey J. Lung, Esq., and Darren S. Matsuda, Esq., appeared at the hearing on behalf of Defendant Hartford Fire Insurance Company. After reviewing the cross-motions and the supporting and opposing memoranda, the court GRANTS in part' and DENIES in part Plaintiffs Cross-Motion for Summary Judgment, DISMISSES Defendant’s Counter Motion for Summary Judgment and GRANTS Plaintiffs Motion to Strike Defendant Hartford Fire Insurance Company’s Disclosure of Expert Witnesses and Preclude Expert Testimony as moot.

BACKGROUND

In this civil case, International Business Machines Corporation (“IBM”) seeks enforcement of a payment bond under the Miller Act, 40 U.S.C. § 270a et seq., under which Defendant Hartford Fire Insurance Company (“Defendant”) is the surety.

On March 26, 1996, R.P. Richards Construction Company (“Richards”) entered into a valid contract with the United States of America to construct the Industrial Waste Treatment Complex for Navy, Public Work Center, Phase III, at Pearl Harbor, Hawaii (“Project”). Then, on April 3, 1996, pursuant to the Miller Act, Defendant issued a payment bond naming Richards as the principal, and delivered it to the Government. In the agreement, Defendant contracted to pay any “first-tier” subcontractors, including IBM, for all supplies and labor necessary for the construction of the Project that were not paid for by Richards, up to $2,500,00o.1 Impor[1026]*1026tantly, however, the bond was issued before Richards entered into any subcontract or purchase order agreements with other parties, including the IBM subcontract. Therefore, Defendant did not rely on any subcontracts or purchase orders when it issued the Miller Act bond; rather, it simply agreed to protect any suppliers of labor and materials to the Project.

Then, on July 11, 1996, Richards entered into a subcontract with IBM, wherein IBM agreed to “furnish and install, among other things, a process instrumentation and control system, ..., for the construction of the [Project]” in exchange for a total subcontract price of $1,340,000. During the performance of the subcontract, Richards and the Navy authorized necessary changes to IBM’s work, which increased the cost of IBM’s performance. As a result, IBM claims that “IBM and Richards agreed that IBM was entitled to an equitable adjustment for those increased costs under the Subcontract.” IBM asserts that its added costs equaled $350,000 and the parties negotiated the “extra work claims” in May of 1998.

According to IBM, Richards requested a modification to the subcontract’s payment clause during the negotiations2 and the parties “reached an agreement in which [they] compromised IBM’s extra work claims to the amount of $175,000.” Defendant was never informed about this equitable adjustment claim. Then, on September 1, 1998, the above “agreement” was reduced to writing, titled “Payment,” as a revision to the payment clause of the original subcontract.3 In this new payment agreement, Richards and IBM agreed that Richards owed IBM $1,203,726.22, which is the value of IBM’s labor and materials under the subcontract and approved change orders less the $239,691.78 that Richards had already paid IBM. Further, Richards agreed to pay the sum in twelve monthly installments of $98,144.67.

In addition to the payment for labor and supplies, however, Richards contracted to pay IBM an extra “$175,000 in consideration of the [] extended payment agreement and release of any claim heretofore asserted by Subcontractor against Contractor related to this agreement,” to be paid in twelve monthly installments of $14,583.34. IBM claims that this latter provision’s addition of $175,000 to the subcontract price reflected the “equitable adjustment” for services rendered. However, Defendant contends that it was simply for the “extension of time to pay off the debt and for the settlement of IBM’s equitable claims.” Moreover, Defendant was never informed of these negotiations during or after they occurred, nor has it ever consented to or authorized the payment clause revision.

Though the original subcontract stated that the Project was to be completed by July 10, 1998, the payments to IBM were scheduled to commence on September 1, 1998, and continue for twelve months. [1027]*1027Pursuant to the agreement, Richards made the first three payments of $112,738.01. However, it stopped making payments in November of 1998,4 even though it still owed $990,541.97 under the revised payment clause of the subcontract.5 As a result, IBM notified Defendant on December 30, 1998 of Richards’ non-payment of the subcontract and its bond claim. This notification was the first notice that Defendant received from IBM concerning Richards’ non-payment of the subcontract.

It is important to note that IBM’s performance on the subcontract continued until at least October 2, 1998, when Richards authorized it via letter to “proceed with the additional work approved in the Prime Contract Modification [00025].” Further, IBM filed the instant Complaint on June 17, 1999. Also, pursuant to a Rule 16 Scheduling Conference, Magistrate Judge Yamashita set May 11, 2000 as the deadline for dispositive motions.

Plaintiff filed its Motion for Summary Judgment on April 28, 2000 and then filed its Motion to Strike Disclosure of Expert Witnesses and Preclude Expert Testimony on June 14, 2000. Then, on June 30, 2000, Defendant filed its Oppositions to both Motions, and filed a Cross-Motion for Summary Judgment. Finally, on July 7, 2000, IBM filed its Reply Briefs and its Opposition to Defendant’s Cross-Motion.

STANDARD OF REVIEW

Rule 56(c) provides that summary judgment shall be entered when:

[T]he pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue of material fact and that the moving party is entitled to judgment as a matter of law.

Fed.R.Civ.P. 56(c). The moving party has the initial burden of demonstrating for the court that there is no genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986) (citing Adickes v. S.H. Kress & Co., 398 U.S. 144, 90 S.Ct. 1598, 26 L.Ed.2d 142 (1970)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
112 F. Supp. 2d 1023, 2000 U.S. Dist. LEXIS 13367, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-international-business-machines-corp-v-hartford-hid-2000.