United States Ex Rel. Durcholz v. FKW Inc.

997 F. Supp. 1159, 42 Cont. Cas. Fed. 77,345, 1998 U.S. Dist. LEXIS 6247, 1998 WL 214605
District Court, S.D. Indiana·Decided April 27, 1998·No. EV 95-121 C B/H·Published·Cited by 13 cases

Opinion

ENTRY GRANTING IN PART AND DENYING IN PART DEFENDANTS’ MOTION FOR PARTIAL SUMMARY JUDGMENT

BARKER, Chief Judge.

This motion comes before the Court on Defendants’ Motion for Summary Judgment on Plaintiffs’ False Claim Act (“FCA”) claims, alleging that (1) Plaintiffs’ claims are jurisdictionally barred, and (2) even if jurisdiction exists, neither Defendant violated the FCA 1 For the following reasons, Defendants’ Motion for Partial Summary Judgment is GRANTED IN PART AND DENTED IN PART.

I. PROCEDURAL HISTORY

Plaintiffs complaint sets forth claims against Defendants Jeffrey J. Strange (“Strange”) and FKW Incorporated (“FKW”) for violating the FCA and tortiously interfering with Plaintiffs business relationship with the United States Government. In a February 25, 1998 Entry, this Court denied Plaintiffs Motion for Summary Judgment on the FCA claims and dismissed Plaintiffs tortious interference claim against Strange. See United States ex rel. Durcholz v. FKW Incorporated, 1998 WL 89659, No. 95-121-C-B/S (Feb. 25, 1998 S.D.Ind.). That Entry outlined the facts of this action in considerable detail. Therefore, we now discuss only those facts which are relevant to the instant motion.

II. BACKGROUND

This case arises out of a government contract awarded to FKW to clear two sedimentation ponds at the Crane Navel Surface Warfare Center (“Crane”) in Crane, Indiana. As an employee of the Navy’s office of the Officer in Charge of Construction (“OICC”), Strange was assigned to serve as the government’s contracting officer on the ponds project. Strange Depo., vol. 1, at 77. Strange’s immediate supervisors were Lieutenant DeWayne Roby (“Roby”) and Commander Larry Laws (“Laws”). Id., vol. 2, at 170. Gerald Hill (“Hill”), the Deputy Director of the Public Works Directorate, and David Smith (“Smith”), Support Division Director for the Engineering Field Activity (supervisor of the OICC), also were Strange’s superiors with important roles in the project. Hill Aff. ¶ 1; Smith Aff. ¶¶ 3-4.

Recognizing the need for an expedited effort to clear the ponds, a consensus developed among Crane officials that dredging should be used to complete the project because it was quicker than conventional excavation, which was the traditional alternative. Laws Aff. ¶ 4; Hill Aff. ¶¶5-7. Although dredging was the method that the government preferred, using non-prepriced items to support the delivery order would invariably slow the process. 2 Laws Aff. ¶21. Therefore, Strange requested and received authorization from Smith to use conventional excavation (“conventional”) line items listed in the UPB to price the project so long as the delivery order was issued as a “performance specification.” 3 D.Smith Aff. ¶8, 11. Indeed, if the delivery order was issued as a performance specification, Smith instructed Strange that he could use line items from the UPB which support any method of completing the project. Id. ¶¶ 8,11.

In November 1994, Strange informally requested FKW to submit a proposal on the *1163 project. Strange Depo. at 134; Frederick Depo. at 27; Plaintiff’s Exhibit. FEW determined that it would use a subcontractor to perform the project and therefore began soliciting bids from various government-approved subcontractors. Plaintiffs Exhibit 3; Frederick Depo. at 39. Knowing that the government wanted the project performed by dredging, FKW indicated to potential subcontractors that it preferred dredging bids. Frederick Depo. at 40; Bex Depo. at 115. Pursuant to FKW’s request for bids, Durcholz Excavating and Construction submitted the lowest dredging bid ($271,700) and Midwest Dredging and Excavation (“Midwest”) submitted the second-lowest dredging bid ($369,800). 4 Frederick Depo. at 59-61.

Brian K. Frederick (“Frederick”), FKWs supervisor of operations at Crane in 1994 and 1995, knew that Dureholz submitted the lowest dredging bid. 5 Frederick Depo. at 190-91. Strange’s superiors knew the prices of the various subcontractor bids, but believed that Durcholz’s bid was only for conventional excavating and not dredging. Roby Depo. at 83. 6 Strange and Dale Bex (“Bex”) 7 told FKW that it preferred Midwest and, consistent with that preference, FKW selected Midwest and not Dureholz. 8 Frederick Depo. at 61. It is undisputed that FKW was not required to select the lowest dredging bid. D.Smith Depo. at 77.

FKW submitted its formal written proposal for the project in the amount of $457,810 on December 22, 1994. Strange’s Exhibit 8. FKW priced its proposal by reference to attached conventional line items, but the figure was really based primarily upon Midwest’s bid. Frederick Depo. at 69; Strange Depo., vol. 2, at 208. Roby, Strange, and Bex knew and approved of FKW’s use of conventional line items, knowing that the proposed price was actually based on Midwest’s bid. Roby Depo. at 99, 112. FKW’s proposed price was higher than both the government’s and FKW’s original estimates. Frederick Depo. at 64; Strange Depo. at 182-83. Following Strange and Bex’s direction, FKW supported the increase in price by adding a conventional line item for gravel for a road from the ponds up to the containment site. Frederick Depo. at 64. However, since Midwest planned to use dredging, neither the road construction nor the other conventional line items would actually be performed. Id. at 64.

Thereafter, Bex concluded that FKW’s proposal was reasonable. Bex Depo. at 65. Strange and Bex then held a negotiation session with FKW, at which they accepted FKW’s proposed price without modification. 9 Strange’s Exhibit 9; Bex Depo. at 67; Frederick Depo. at 81. Following the session, Strange wrote a post-negotiation memorandum which stated that non-prepriced items for the project amounted to $2,817. Strange’s Exhibit 7; Strange Depo. at 186.

On December 27, 1994, Strange completed the delivery order for the project in the *1164 amount of $457,810. 10 Hill Aff. ¶ 10. Acting on behalf of Laws, Hill instructed Strange not to issue the order until Stan Armstrong (“Armstrong”), a representative from the Crane Army Ammunition Activity (“CAAA”), approved the price. 11 Id. After Hill advised Armstrong that the relevant government officials on the project recommended approval of the delivery order’s price, Armstrong gave his approval and the order was issued. Id. at tlO.

Midwest proceeded to perform the project by dredging. The government, however, rejected FEW’S first submitted invoice because it was supported with attached conventional line items which for obvious reasons had not been performed. Frederick Depo. at 121.

Free access — add to your briefcase to read the full text and ask questions with AI

United States Ex Rel. Durcholz v. FKW Inc., 997 F. Supp. 1159, 42 Cont. Cas. Fed. 77,345, 1998 U.S. Dist. LEXIS 6247, 1998 WL 214605 (S.D. Ind. 1998).

997 F. Supp. 1159 (United States Ex Rel. Durcholz v. FKW Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related