United States Ex Rel. Dorfman v. Standard Surety & Casualty Co.

37 F. Supp. 323, 1941 U.S. Dist. LEXIS 3697
CourtDistrict Court, S.D. New York
DecidedMarch 5, 1941
DocketCiv. 6-467
StatusPublished
Cited by6 cases

This text of 37 F. Supp. 323 (United States Ex Rel. Dorfman v. Standard Surety & Casualty Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Dorfman v. Standard Surety & Casualty Co., 37 F. Supp. 323, 1941 U.S. Dist. LEXIS 3697 (S.D.N.Y. 1941).

Opinion

BYERS, District Judge.

This is an action upon a bond required by 40 U.S.C.A. § 270a(2), namely, a payment bond “for the protection of all persons supplying labor and material in the prosecution of the work * * * ”, namely, that specified in a contract entered into by Reuben Malkin, Inc., with the United States Government, concerning work done at 201 Varick Street (U. S. Appraiser’s Stores) New York City.

It sufficiently appears that there was such a contract and that the contractor did not pay in full for the labor involved, and that some resultant liability attached to the defendant Surety Company.

It is necessary to determine the amount remaining unpaid by the contractor, and the persons who are entitled to judgment under the bond, and the amounts due.

The evidence, as a whole, is confused, fragmentary and in some respects quite difficult of acceptance.

The use-plaintiffs are Irving Dorfman and Barney Shapoff, who assert that they were subcontractors as to all the exterior painting, and that they are entitled to recover an alleged unpaid balance owing to them under the said subcontract.

For reasons to be stated, it will be found that they were not subcontractors but co-foremen employed by the contractor, and their recovery must be limited to the amount remaining unpaid of their wages.

By order of January 15, 1941, Hyman Kenoff was permitted to intervene as a use-plaintiff, and he asserts that he was employed, by Dorfman and Shapoff as a painter on the job, and that $131.25 of his wages remains unpaid.

It was stipulated on the trial that that is the correct amount of his claim.

The original complaint, filed December 8, 1939, named the Surety Company and Herman Katz as defendants and, in addition to the matters above stated and for a second cause of action, alleged that during the prosecution of the contract the defendant Katz loaned to the contractor Malkin the sum of $545, which was delivered to Dorfman and Shapoff, and by them applied toward the pay rolls of their laborers, and that the said $545 was included in the sum of $1,033 alleged in the first cause to have been paid by the contractor; that Katz had instituted an action to recover the $545 from Dorfman and Shapoff, and that they deny having done the borrowing, and that they were in doubt as to whether they were liable to Katz for any part of the moneys advanced by him.

*325 On December 26, 1939, Katz filed a cross-complaint and answer, in which it was asserted that the said $'545 was loaned by him to Dorfman and Shapoff to be used for the payment of labor; and for his cross-complaint against the Surety Company, the Malkin contract was alleged, and that during the months of April, May and July, 1939, Katz, at the joint request of Malkin and Dorfman and Shapoff, “caused to be performed certain labor and services consisting of painting in connection with” the said contract, of the reasonable price and value of $545, and judgment was sought against the defendant Surety Company for that sum.

There was subsequent procedural activity in great volume, and to little apparent purpose, none of which seems to require present recital.

It also appears that certain laborers, who were not paid, have filed labor claims with the Federal Works Agency for wages owing to -them, namely:

Eric Holm ...................... $27.50
Karl Jensen ..................... 23.50
Charles Jensen................... 23.50
Eddie Schnitzer.................. 85.00

as the result of which, the total sum of $159.50 was withheld from the final payment on the Malkin contract, and apparently those sums are now in the custody of the Comptroller General for the benefit of the claimants. While those sums were not paid by the contractor, they have been earmarked for the workmen, and are available to them.

It seems that the exterior painting embraced within the Malkin contract was done during a period of seven weeks, commencing about April 17, 1939, and terminating on or about June 10, 1939.

Dorfman and Shapoff have failed to satisfy this court that their status was that of subcontractors, for the following reasons :

(a) The alleged subcontract (their Exhibit 1) is dated April 17, 1939, and purports to constitute an agreement between Malkin and Dorfman and Shapoff for all the said exterior painting; Dorfman and Shapoff agreed to furnish all labor and Malkin agreed to furnish all “equipment, material and compensation” therefor, and Malkin agreed to pay $3,200 as the contract price, thirty per cent, upon the “Inspector’s approval” and the balance upon receipt of his check from the Government m final payment.

In other words, Malkin was to pay for all labor and material and employees’ compensation, and Dorfman and Shapoff were to assume no financial responsibility. To call this a subcontract would not make it such.

A statement of the judicial understanding of a true subcontract will be found in the opinion of Mr. Justice Day in United States to Use of Hill v. American Surety Company, 200 U.S. 197, at 205, 26 S.Ct. 168, at 171, 50 L.Ed. 437: “If the contractor sees fit to let the work to a subcontractor, who employs labor and buys materials which are used to carry out and fulfil the engagement of the original contract * * * he is thereby supplied with the materials and labor for the fulfilment of his engagement as effectually as he would have been had he directly hired the labor or bought the materials.”

The only labor that Malkin contracted for with Dorfman and Shapoff was their own; Malkin was to furnish everything else, and Dorfman testified that he and Shapoff did not put any money into the job and that Malkin was to pay for the labor, materials and equipment. This obviously left nothing for Dorfman and Shapoff to furnish but their own services.

In the plaintiffs’ original bill of particulars, they listed the laborers employed on the job and the rate of compensation per day. Included therein were the four men above-named, who presented their claims to the Government; their letters request that action be taken against Malkin, and no mention is made that any one of them was ever employed by Dorfman and Shapoff. ‘

(b) Dorfman made a claim for compensation, claiming that he had suffered an injury on the job about May 3d, and he stated on the blank provided by the Department of Labor of the State of New York, in connection with case No. 39203763, that he was injured moving a scaffold; that his employer was Reuben Malkin, and that he was a painter earning $10.50 a day, and that he was a time worker, and that he had sprained the muscles of his neck and back in moving the ropes of the scaffold on the roof of the building 201 Varick Street, New York.

Of course that was incompatible with any subcontractual status on his part at that time.

*326 (c) Malkin testified that the so-called contract was not executed on the date that it bears, although it purports to have been verified before a notary public on April 17, 1939.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
37 F. Supp. 323, 1941 U.S. Dist. LEXIS 3697, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-dorfman-v-standard-surety-casualty-co-nysd-1941.