Hardaway v. National Surety Co.

150 F. 465, 80 C.C.A. 283, 1907 U.S. App. LEXIS 4107
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 19, 1907
DocketNo. 1,584
StatusPublished
Cited by23 cases

This text of 150 F. 465 (Hardaway v. National Surety Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hardaway v. National Surety Co., 150 F. 465, 80 C.C.A. 283, 1907 U.S. App. LEXIS 4107 (6th Cir. 1907).

Opinion

LURTON, Circuit Judge.

This appeal involves only the liability of the National Surety Company, as surety upon a government contractor’s bond made in pursuance of the act of Congress of August 13, 1894 (28 Stat. 278, c. 280, § 1 [U. S. Comp. St. 1901, p. 2523]), to the appellants, Hardaway & Prowell, who claim to have supplied the contractors and principal obligors in the bond with labor and material. The only facts necessary to be stated are these: The firm of Willard & Cornwell, composed of James E. Willard, Charles R. Cornwell, and Joseph Cojme, contracted on October 5, 1899, with the government for the construction of lock and dam No. 4, Black Warrior river, Ala. This contract involved the supplying of a large amount of materials and labor, and the contractors were required to execute a bond in the penal sum of $50,000, conditioned, first, that the contractors would perform their contract according to its true intent and meaning; and, second, that “they would make full -payments to all persons supplying them labor or materials in the prosecution of the work provided for in said contract.” They executed this bond with the National Surety Company as surety. The contractors prosecuted the work as a firm for a year or more, and then, for reasons not necessary to be stated, Willard and Cornwell assigned their interests in the contract to their associate, Joseph Coyne, who agreed to assume all debts of the firm and prosecute the work at his own risk and for his own benefit. As between the partners, we see no valid objection to this agreement. It could not affect the United States, and was never intended to substitute Coyne for. Willard, Cornwell and Coyne, and was effective only as an assumption by one of the firm of the debts of the firm in consideration of the receipt of the benefits to be derived from the execution of the agreement. Burck v. Taylor, 152 U. S. 634, 14 Sup. Ct. 696, 38 L. Ed. 578, and Prairie Bank v. U. S., 164 U. S. 227, 17 Sup. Ct. 142, 41 L. Ed. 412. Coyne went on with the contract, but at last found himself unable to complete the work. In this situation he entered into a contract for the completion of the work with the appellants, Hardaway & Prowell. As the legal- right of Harda-way & Prowell to look to the bond originally given by Willard & Cornwell with the appellee, the National Surety Company, as surety, for their protection, depends upon' the true intent and meaning of this contract. It is here set out in full: '

“State of Alabama, Tuscaloosa County:
"Tlxis contract made this the 2nd day of June, 1903, by and between B. H. Hardaway and It. P. Prowell, hereinafter called Hardaway & Prowell, as parties of the first part, and Joseph Coyne, as party of the second part, witness-oth:
“That, whereas, Willard & Cornwell, a firm composed of J. E. Willard, C. R. Cornwell and the said Joseph Coyne, did, heretofore, on to wit, the - day of-, 1899, enter into a contract with the United States for the construction of Lock No. 4 in the Black Warrior River above Tuscaloosa, Alabama, and whereas, shortly after the beginning of the work upon said lock the said Joseph Coyne, by an arrangement between him and his copartners, undertook to complete and finish said lock according to the specifications of the contract of said firm with the United States, and in consideration of such an undertaking acquired the beneficial interest of said firm in said contract and was to receive all amounts paid by the United States in consideration of such contract, and, whereas, said lock is still uncompleted, and the said Joseph Coyne cannot, on account of his inability to procure the necessary financial [467]*467ilia and on account of the disorganization of his labor forces and for various and sundry other reasons, complete and finish the said work in accordance with the said contract, and whereas said contract is a valued asset to the said Joseph Coyne if the said work can be prosecuted to its completion under t he terms of said contract, there being held in reserve liy the government under the terms of said contract about $8,3C0.(X), which has already been earned by said Coyne, and whereas by reason of his said inability to finish said work the said contract is about to be forfeited, and the said Coyne is in imminent da ger of losing, not. only what profits may be made upon the completion of the work, but the entire reserve fund also retained by the government, and whereas the said Joseph Coyne for the purpose of preventing the forfeiture of said contract, has made overtures to the said Hardaway & Prowell to take up sahl work and complete it, and the said Hardaway & I’roweli have agreed to do so upon the terms and stipulations hereinafter set forth. Now, therefore:
“(1) The said Hardaway & Prowell do hereby undertake and agree with the said Joseph Coyne to superintend the completion of the said lock and dam No. 4 and to furnish the necessary finances for the completion thereof and to put in charge of said work a competent superintendent and to properly organize the work for an energetic prosecution thereof to completion for which services they are io receive an agreed compensation of 15 per cent, upon the fotal cost of completing said contract, which total cost shall be construed to include all amounts necessarily expended and expenses incurred by Hardaway & Prowell in the completion of said work and all amounts necessarily paid and expenses incurred by them to effect a settlement with and an acceptance o. said lock and dam by the United States.
“(21 Tile said Joseph Coyne agrees to the above compensation for Hardaway & Prowell and further agrees to turn over to them entire charge of the completion of said work, and not to interfere with them in any way in the prosecution of said work to completion, and further agrees to turn over to the said Hardaway' <& Prowell the entire outfit of machinery, tools, etc., which he now has at said lock and dam and' the quarries where he is getting stone, and to give the use of the same to them for the completion of said work free of any charge.
“(3) The said Joseph Coyne further agrees to have all checks for each estimate upon said work forwarded by the government to the said Hardaway & Prowell and to properly' endorse such checks so that they may be collected by Hardayvoy & Prowell.
“(-P It is further agreed by all parties hereto that out of the proceeds of the cheeks referred to in the next foregoing paragraph the obligations shall be paid preferentially in the following order:
“(I) The compensation of the said Hardaway' & Prowell as herein agreed for their services.
“(2) All moneys advanced by Hardaway & Prowell and used in the prosecution of said work.
“(3) All debts necessarily incurred by the said Hardaway & Prowell for the prosecution of said work other than debts for labor and material.
“(4) All debts incurred by said Hardaway & Prowell for labor and material or moneys advanced by' them in payment for labor or materia1 debts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. CTI Ltd. v. Mellon Stuart Co.
860 F. Supp. 556 (N.D. Illinois, 1994)
Watson v. Murphey
285 P. 1037 (Arizona Supreme Court, 1930)
Exchange State Bank v. Federal Surety Co.
28 F.2d 485 (Eighth Circuit, 1928)
Gary Hay Grain Co., Inc. v. Carlson
255 P. 722 (Montana Supreme Court, 1927)
Franzen v. Southern Surety Co.
246 P. 30 (Wyoming Supreme Court, 1926)
Fidelity & Casualty Co. v. Livingston
208 N.W. 446 (Michigan Supreme Court, 1926)
Lanstrum v. Zumwalt
237 P. 205 (Montana Supreme Court, 1925)
New Amsterdam Casualty Co. v. State Ex Rel. Green
128 A. 641 (Court of Appeals of Maryland, 1925)
Pratt Lumber Co. v. T. H. Gill Co.
278 F. 783 (E.D. North Carolina, 1922)
Wasco Co. v. New England Equitable Ins.
172 P. 126 (Oregon Supreme Court, 1918)
Cox v. New England Equitable Ins.
247 F. 955 (Eighth Circuit, 1917)
People's National Bank v. Corse
133 Tenn. 720 (Tennessee Supreme Court, 1915)
Title Guaranty & Surety Co. v. State ex rel. Leavenworth State Bank
109 N.E. 237 (Indiana Court of Appeals, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
150 F. 465, 80 C.C.A. 283, 1907 U.S. App. LEXIS 4107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hardaway-v-national-surety-co-ca6-1907.