United States ex rel. Clark-Fontana Paint Co. v. Glassman Construction Co.

266 F. Supp. 110, 1967 U.S. Dist. LEXIS 8978
CourtDistrict Court, D. Maryland
DecidedMarch 31, 1967
DocketCiv. A. No. 16929
StatusPublished

This text of 266 F. Supp. 110 (United States ex rel. Clark-Fontana Paint Co. v. Glassman Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Clark-Fontana Paint Co. v. Glassman Construction Co., 266 F. Supp. 110, 1967 U.S. Dist. LEXIS 8978 (D. Md. 1967).

Opinion

HARVEY, District Judge:

This suit under the Miller Act was brought by a supplier of materials (Clark-Fontana) against a subcontractor (Elmore), the general contractor (Glass-man), and the latter’s surety.1 Glass-man entered into a written contract with the United States on June 26, 1964 for. the construction of 150 housing units at Andrews Air Force Base, Maryland. Glassman, as principal, and Home Indemnity Company, as surety, executed a payment bond in the form required by the Miller Act,2 conditioned upon the prompt payment of all persons supplying labor and materials for the job.

Glassman entered into a written subcontract on August 24, 1964 with Elmore,3 whereby Elmore undertook to perform the painting work required under the principal contract for $56,500. Clark-Fontana in turn agreed with Elmore to supply the paint needed for the project. To assure itself of payment by the subcontractor, Clark-Fontana requested that Glassman agree to make payments on the Elmore subcontract by means of checks payable jointly to Elmore and Clark-Fontana. A written agreement called a “Joint Check Assignment” dated January 14, 1965 was signed by Glassman and Elmore whereby Glassman agreed to “make all payments for above listed job by joint check drawn Elmore Decorating Co. Inc. and Clark Fontana Paint Company” (sic).

Thereafter, Elmore’s men started their work at the job site, and Clark-Fontana delivered paint, billing Elmore for the cost thereof. Pursuant to the terms of the Joint Check Assignment, Glassman drew and delivered to Elmore nine checks payable to “Elmore Decorators and Clark-Fontana Paint Company”. These nine checks totalled $30,300 and bore dates from March 15, 1965 to July 15, 1965. On the reverse side of each check, the following legend was stamped in capital letters:

“THE UNDERSIGNED ENDORSER^), IN CONSIDERATION OF THE ISSUANCE OF THIS CHECK, DO HEREBY WAIVE AND RELEASE TO THE EXTENT OF THE FULL FACE VALUE HEREOF ANY RIGHT ANY OF THEM MAY HAVE TO CLAIM A MECHANIC’S OR MATERIALMEN’S LIEN OR TO ASSERT ANY CLAIM UNDER ANY BOND GIVEN BY THE PAYER HEREOF AS PRINCIPAL, FOR ANY WORK DONE FOR OR MATERIALS FURNISHED TO THE PAYER HEREOF OR ANY OTHER PAYEE OR PAYEES NAMED HEREIN IN OR ABOUT THE CONSTRUCTION, REPAIR OR IMPROVEMENT OF THE JOB DESIGNATED ON THE REVERSE SIDE HEREOF.”

On the reverse side of all but one of the checks there was also stamped “NOTE: TWO ENDORSEMENTS REQUIRED.”

[112]*112John L. Eubank, President of Elmore, would receive these checks from Glass-man, indorse them and take them personally to Clark-Fontana’s President for indorsement. Seven of the checks, after indorsement by both payees, were deposited in Elmore’s account at Citizen’s National Bank. Two of the checks were deposited, after indorsement, in ClarkFontana’s account at Riggs National Bank. From time to time during the period that these checks were being received, Eubank would deliver Elmore’s own check to Clark-Fontana, to be applied against the paint account. On the two occasions that Clark-Fontana deposited checks in its bank account, ClarkFontana gave Elmore its checks to be used for Elmore’s payroll account.

As the work progressed, Elmore experienced increasing difficulty in meeting its payroll. When Glassman declined to make further advances beyond the requirements of the subcontract, Elmore, which was without capital or borrowing power, signed at Glassman’s request a letter dated July 22, 1965 giving notice of default. Glassman thereupon undertook to complete the painting work by employing Elmore’s painters, and from July 22 until August 8, 1965, such painters were paid directly by Glassman. Meanwhile, Clark-Fontana, unaware of Elmore’s default, continued to deliver paint to the job site. On August 9, 1965, a voluntary petition in bankruptcy was filed in this Court by Elmore, notice of which was received by Clark-Fontana the same day.

By the time of the bankruptcy, ClarkFontana had furnished a total of $20,-707.74 in paint materials for the project and had been paid therefor $7,817.16. Clark-Fontana sues here for the difference amounting to $12,890.58, plus interest, and in addition claims $1,485.20, plus interest, for materials delivered directly to Glassman after August 9, 1965.

Although defendants originally contested the entire $14,375.78 claimed in this suit, they have now conceded, after trial, that $5,124.23 is due under the contract, being $3,639.03 in materials delivered between July 15, 1965 and August 9, 1965 and $1,485.20 delivered after August 9, 1965. Relying on ClarkFontana’s indorsements of the nine Glassman checks, defendants deny liability for the remaining $9,251.55 on grounds of (1) waiver, (2) estoppel, and (3) payment. Clark-Fontana in turn emphasizes the remedial nature of the Miller Act and denies that its indorsements beneath the printed language on each check amount to a waiver of any rights under the Act.

It is well established that the Miller Act is remedial in character and should be liberally construed in support of its purpose to protect subcontractors and materialmen furnishing labor or materials for government projects. MacEvoy Co. v. United States, 322 U.S. 102, 104, 64 S.Ct. 890, 88 L.Ed. 1163 (1944) ; Noland Company v. Allied Contractors, Incorporated, 273 F.2d 917, 921 (4th Cir. 1960); United States v. Endebrock-White Company, Inc., 275 F.2d 57, 70 (4th Cir. 1960). On the other hand, the Act poses problems for the general contractor which has in fact paid a subcontractor for materials and labor furnished for a building project but which may have to pay twice if because of insolvency or other reasons the subcontractor has failed to pay the supplier of materials its proper share. To avoid having to pay twice for materials incorporated into a project, general contractors often resort to the practice (apparently common in the industry) of making checks jointly payable to the subcontractor and materialman involved. The question raised by this case is whether a supplier of materials who has not in fact been fully paid can recover under the Miller Act the balance due, when it has received and indorsed checks from the general contractor which were more than sufficient to cover such balance.

The evidence in the case at hand indicates that Clark-Fontana itself requested the joint check agreement so that it could be assured of payment. Reginald R. Clark, the President of Clark-Fontana, testified that he knew that Elmore was [113]*113under-financed and was having difficulty in meeting its payroll as the job progressed. He also testified that he knew that arrangements for payment by joint checks were made in many cases “especially in Maryland” to protect the general contractor from having to pay twice because of the requirements of the mechanics lien law or the Miller Act. When asked whether he had read the stamped legend on the reverse side of each check adding the indorsement, Clark testified that he had read the first part but thinking that it merely stated that two indorsements were required, he did not read the language in its entirety.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Endebrock-White Company
275 F.2d 57 (Fourth Circuit, 1960)
United States v. Five Boro Construction Corporation
310 F.2d 701 (Fourth Circuit, 1962)
Ray v. Eurice
93 A.2d 272 (Court of Appeals of Maryland, 1952)
Marden v. Jones
169 A. 309 (Court of Appeals of Maryland, 1933)
Williams v. Paxson Coal Co.
31 A.2d 69 (Supreme Court of Pennsylvania, 1942)
The Henry S. Grove
22 F.2d 444 (D. Maryland, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
266 F. Supp. 110, 1967 U.S. Dist. LEXIS 8978, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-clark-fontana-paint-co-v-glassman-construction-co-mdd-1967.