United Masonry, Inc. v. K. W. F., Inc.

241 N.E.2d 912, 16 Ohio App. 2d 77, 45 Ohio Op. 2d 225, 1968 Ohio App. LEXIS 320
CourtOhio Court of Appeals
DecidedNovember 14, 1968
Docket28719
StatusPublished
Cited by1 cases

This text of 241 N.E.2d 912 (United Masonry, Inc. v. K. W. F., Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Masonry, Inc. v. K. W. F., Inc., 241 N.E.2d 912, 16 Ohio App. 2d 77, 45 Ohio Op. 2d 225, 1968 Ohio App. LEXIS 320 (Ohio Ct. App. 1968).

Opinion

Corrigan, P. J.

Appellant, Westerly Towers Company, appeals on questions of law and fact from a decision of the Court of Common Pleas of Cuyahoga County which granted appellee, United Masonry, Inc., a mechanic’s lien in the amount of $38,000 on an apartment house owned by Westerly Towers Company.

Being an appeal on questions of law and fact, the cause is before us for hearing de novo.

Pertinent facts, as reflected by the evidence, disclose that over a period of time ending on October 7, 1964, appellee furnished materials and did masonry work on the apartment house which was then owned by K. W. F., Inc. *78 In November 1964, when K. W. F., Inc., determined that it was nnable to continue with the project because of a stopping of funds for disbursements on the job by the bank, the principals of K. W. F., Inc., began negotiations to sell their interests in the project. At this point, many material men and other creditors filed mechanics’ liens on the property. United Masonry did not file a mechanic’s lien immediately, but waited until April 1, 1965. It had learned, on or about December 1, 1964, of defendant K. W. F.’s suspension of work on the building. It contends that it was lulled into the belief that the job had not terminated and that it would be invited back to finish its portion of the project as soon as the financial difficulties were overcome. It maintains further that it received no notice from the new owners of the apartment building until March 18,1965, that it would not be allowed to finish its part of the job, after which date it filed a mechanic’s lien.

The first assignment of error reads as follows:

“A court may not extend the time for filing a mechanic’s lien beyond the sixty-day statutory period.”

Many cases in Ohio have held that the statutes governing the perfection of a mechanic’s lien must be strictly construed. Manpower, Inc., v. Phillips (1962), 173 Ohio St. 45; Robert V. Clapp Co. v. Fox (1931), 124 Ohio St. 331; C. C. Constance & Sons v. Lay (1930), 122 Ohio St. 468; Love Lumber Co., Inc., v. Reaser (1964), 4 Ohio App. 2d 354; D. & H. Coal Co. v. Lay (1930), 37 Ohio App. 433.

Section 1311.06, Revised Code, provides that the mechanic’s lien affidavit must be filed within 60 days from the date the last material was furnished at the building, or from the date the last labor was performed. This requirement is mandatory. King v. Ship Building Co. (1893), 50 Ohio St. 320. Demann’s Ohio Mechanic’s Lien Law (2d Ed.) 220, Section 9.10; DeWitt’s Ohio Mechanic’s Liens 270, Section 157.

An exception to this strict rule is explained in Groff v. Harris (1934), 18 Ohio Law Abs. 101. There, the court held that a subcontractor who waited two years to file a mechanic’s lien after he learned that the principal contractor had abandoned the project had waited too long. In so deciding, however, the court stated:

*79 “Where the construction of a building has been abandoned by the act of the owner, through no fault of the principal contractor or subcontractors, the date of the fair notice or knowledge of such abandonment, or a reasonable time thereafter within which a lien claimant may determine what he will do is the date from which to calculate the time within which a lien may be filed, rather than from the actual time of the completion of the building, or furnishing of the last material, or doing of the last work as the particular statute may provide.”

Under this assignment of error, appellant urges that the above-quoted statement from Groff is mere obiter dictum and not the law of Ohio. The facts of the instant case, however, do not require a decision on this point. Whether the 60-day statutory period is measured from the date the last material was furnished or labor performed, as expressed in Section 1311.06, Revised Code, or whether it is measured from the date appellee discovered that K. W. F., Inc., had abandoned the project under the theory of the Groff case, United Masonry still filed its lien too late. Assignment of error number one is overruled. Appellant’s assignment of error number two reads: “If Groff is the law of Ohio, the law and the facts of this case show there was an abandonment more than 60 days prior to plaintiff filing its mechanic’s lien.”

Appellant contends that the project was abandoned when work ceased in December 1964, whereas appellee maintains that even though work on the project ceased in December 1964, the project was not abandoned until March 1965, or, in any event, it did not learn of the abandonment until then. An analogous case relied upon by appellee is F. Pedretti é Sons v. Stichtenoth (1892), 6 C. C. 516. There, the court refused to deny a mechanic a lien on the premises despite the fact that the mechanic failed to file his lien until after the statutory time limit had expired. The facts revealed, however, that the owner of the premises asked the plaintiffs to suspend their work while the floor was put down. At various times plaintiffs returned to complete the work but were told by the owner to return at a later date. Eventually the owner told them that they would never be allowed to complete the contract. The court mea *80 sured the lien period from the date they were informed by the owner that their contract had terminated rather than from the date of their last labor. In Pedretti, the owner of the premises clearly was attempting to take advantage of the statutory time period by refusing to allow plaintiffs to complete their contract. In the case at bar, however, the owner of the property, K. W. F., Inc., gave every indication of abandoning operations long before appellee sought its lien.

Two schools of thought prevail as to when an abandonment occurs. The first view, expressed by the Kansas Supreme Court, holds that actual cessation of work is the time of abandonment. Chicago Lumber Co. v. Merrimack River Savings Bank (1893), 52 Kan. 410, 34 P. 1045. The court stated, at page 415:

“We think the contention of the plaintiff in error, that abandonment of work on this mill is a mental act of the owners, is unsound; that it is a physical, visible condition, to be determined from an inspection of the premises. When Douglas & Bixby ceased to do anything toward the completion of their building, they abandoned the work, no matter how much they may have hoped, expected or intended to be able to resume, if subsequent events show that they never' did in fact resume work. If the owner temporarily suspend work on the building, and thereafter resume, no doubt liens might be taken within the statutory period after completion of the work; and if it were a fact in this case that the owners had resumed work for the purpose of completing the building as originally planned, a different question would be presented. It is immaterial what the cause of the abandonment may have been.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Settle Builders Supply Co. v. Frankel-Shore Partnership
326 N.E.2d 271 (Court of Common Pleas of Ohio, Hamilton County, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
241 N.E.2d 912, 16 Ohio App. 2d 77, 45 Ohio Op. 2d 225, 1968 Ohio App. LEXIS 320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-masonry-inc-v-k-w-f-inc-ohioctapp-1968.