Settle Builders Supply Co. v. Frankel-Shore Partnership

326 N.E.2d 271, 42 Ohio Misc. 13, 71 Ohio Op. 2d 96, 1974 Ohio Misc. LEXIS 182
CourtCourt of Common Pleas of Ohio, Hamilton County
DecidedDecember 4, 1974
DocketNo. A-723982
StatusPublished
Cited by3 cases

This text of 326 N.E.2d 271 (Settle Builders Supply Co. v. Frankel-Shore Partnership) is published on Counsel Stack Legal Research, covering Court of Common Pleas of Ohio, Hamilton County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Settle Builders Supply Co. v. Frankel-Shore Partnership, 326 N.E.2d 271, 42 Ohio Misc. 13, 71 Ohio Op. 2d 96, 1974 Ohio Misc. LEXIS 182 (Ohio Super. Ct. 1974).

Opinion

Bettman, J.

This case, in which plaintiff prays for foreclosure of a mechanic’s lien, was tried to the court. The facts, which are substantially undisputed, are that defendant Frankel-Shore, as owner, contracted with D. I. B. Construction Company, Inc., for the construction of apartments known as Regency Square. D. I. B. subcontracted all the concrete work required by the principal contract to U. S. Finishing (U. S.). Plaintiff, Settle Builders Supply, contacted U. S. about supplying materials necessary for the concrete work on the job. They discussed prices and it [14]*14was. agreed that U. S. would call on plaintiff for the materials needed as the job went on. Such deliveries were commenced in July, 1971, and were made on delivery tickets marked “Sold to U. S. Finishing’’ and entered on plaintiff’s ledger card under an account in the name of U. S. Finishing. Deliveries were made from time to time, the last delivery being December 1, 1971. On that date, U. S. abandoned the job and approximately at that time plaintiff-Settle, had a conversation with the general contractor, D. I. B., who advised plaintiff that it was going to finish the concrete work and would like materials from plaintiff. Plaintiff then resumed delivering the same type of materials to the job, from time to time, on delivery tickets marked “Sold to D. I. B. Construction” and entered the charge on a ledger card for D. I. B. The last of such materials was delivered to the job on March 8, 1972. On April 13, 1972, plaintiff filed its affidavit for lien for $1,003.13, which represented the materials delivered from July 2, 1971, through December 1,1971; plaintiff having been paid by D. I. B. for all materials furnished thereafter.

Defendant’s position is that plaintiff failed to perfect its lien because it was filed more than sixty days after the last material was furnished under plaintiff’s contract with U. S. Plaintiff maintains that in order to have a valid lien all it needs do is file within sixty days after it last furnishes material at the building.

The resolution of the matter involves a determination of the meaning of R. C. 1311.02 and 1311.06. R. C. 1311.02 provides, in pertinent part, that:

“Every person who * * # furnishes * * * material * * * for constructing * * * [a] building # * * by virtue of a contract, express or implied, with the owner * * * and every person who as a ® * * materialman * * * furnishes * * ’* material * * * to * * * any subcontractor, in carrying forward, performing, or completing any such contract, has a lien to secure the payment thereof * * *.”

There can be no doubt that the words “any such contract” means the contract with the owner of the premises. A. M. Lewin Lumber Co. v. Guttman (1929), 34 Ohio App. [15]*15458, 171 N. E. 342. This is the all-encompassing blanket under which the labor must be performed or material furnished in order to obtain a lien on the owner’s property. If work is done or material furnished under a contract with a contractor or subcontractor, one would not be entitled to a lien unless the work or material was pursuant to the principal contract with the owner. To put the matter more simply, an owner’s land is only lienable for work done or materials furnished which were called for by his contract.

There being no question here that the materials furnished by Settle were for carrying forward the contract between defendant-owner and D. I. B., plaintiff would be entitled under R. C. 1311.02 to a lien. However, to perfect its lien plaintiff must comply with the provisions of R. C. 1311.06, which provides, in pertinent part:

“Every * * * materialman # * * shall make and file * * * an affidavit showing the amount due * * * the name and address of the person to or for whom such * * * material * * * was furnished * * * the name of the owner * * * and the name and address of the lien claimant * # *. Such * * * affidavit shall be filed within sixty days from the date on which the last of the # * # material * * * was furnished at the building * *

Plaintiff argues that since it last furnished material to the job in March, its lien filed in April is within time, and that it makes no difference that the material was furnished partly to U. S. and partly to D. I. B. since it was all furnished to the job and pursuant to the contract between the owner and the principal contractor. We feel such contention must fail on the basis of the language of R. C. 1311.06, the logic of the situation and the basic scheme of R. 0. Chapter 1311.

Taking up first the general spirit of R. C. Chapter 1311 — its intent is to provide laborers and materialmen liens for work done pursuant to a contract with the owner and also provide protection to the owner by requiring affidavits and certificates from all subcontractors and mate-rialmen, etc., on every payout and, by virtue of the sixty-day lien limit, prompt notice to the owner of any claim that has [16]*16not for one reason or another been brought to his attention. If a materialman, who might be furnishing materials to a number of subcontractors working at different times on a job, could hold back until sixty days after the last material was furnished to the last contractor, an owner who had been taking every precaution the law provided him could suddenly find himself stuck with claims which should have been paid long before.

R. C. 1311.06 requires that the affidavit state the name and address of the person to or for whom such material was furnished. In this case, the affidavit states correctly that the material was furnished in pursuance of a contract with U. S. R. C. 1311.06 further provides that:

“* * * such affidavit shall be filed within sixty days from the date on which the last of the * * * material * * * was furnished at the building * * *.” (Emphasis ours.)

The words “the material” can only refer to the material furnished to the person whose name and address is shown on the affidavit. In this case the lien affidavit shows the material was furnished to U. S., who all parties knew had abandoned the job on December 1,1971, more than four months before the affidavit was filed. The statute might have been clearer had it used the words “such material” rather than the words “the material.” Indeed that is the language used in the suggested affidavit for mechanic’s lien provided for in R. C. 1311.06, which states, in part:

“A. B. # * * — says that he furnished * # * material * * * in and for construction * * * a certain * # * in pursuance of a certain contract, with C. D. * * * subcontractor * * q^e last of such * * * material * * * furnished on the.day of.* * * and there is * * * due * * * therefor from the said O. D. * * * the sum of .dollars, for which amount deponent claims a lien on said land of which.is * * * the owner * * (Emphasis ours.)

Plaintiff cites as authority for its contention that its lien is valid the case of Ropp v. Bd. of County Commissioners (Court of Appeals for Hardin County, 1917), 28 Ohio Ct. App. 74. In that case A had a contract with de[17]*17fendants to improve a road. He entered into a verbal contract with plaintiff to do the required hanling. The hanling went on over some period of time and at some point dnring that period A contracted with H to complete the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S.K. Drywall, Inc. v. Developers Financial Group, Inc.
799 P.2d 1362 (Court of Appeals of Arizona, 1990)
Gene McVety, Inc. v. Don Grady Homes, Inc.
581 P.2d 1132 (Arizona Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
326 N.E.2d 271, 42 Ohio Misc. 13, 71 Ohio Op. 2d 96, 1974 Ohio Misc. LEXIS 182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/settle-builders-supply-co-v-frankel-shore-partnership-ohctcomplhamilt-1974.