United Gas Pipe Line Co. v. Federal Power Commission. Michigan Consolidated Gas Co. v. Federal Power Commission

181 F.2d 796, 86 U.S. App. D.C. 314, 1950 U.S. App. LEXIS 3842
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 5, 1950
Docket10125, 10126
StatusPublished
Cited by57 cases

This text of 181 F.2d 796 (United Gas Pipe Line Co. v. Federal Power Commission. Michigan Consolidated Gas Co. v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Gas Pipe Line Co. v. Federal Power Commission. Michigan Consolidated Gas Co. v. Federal Power Commission, 181 F.2d 796, 86 U.S. App. D.C. 314, 1950 U.S. App. LEXIS 3842 (D.C. Cir. 1950).

Opinion

*797 BAZELON, Circuit Judge.

Petitioners seek direct review in this court of a rule issued by the Federal Power Commission pursuant to Sections 4(c) and 16 of the Natural Gas Act, 15 U.S.C.A. §§ 717c (c), 717o. Section 4(c) authorizes the Commission to prescribe rules and regulations for filing “ * * * in such form as the Commission may designate * * * schedules showing all rates and charges for any transportation or sale subject to the jurisdiction of the Commission, and the classifications, practices, and regulations affecting such rates and charges, together with all contracts which in any manner affect or relate to such rates, charges, classifications, and services.” 15 U.S.C. A. § 717c (c).

Section 16 gives the Commission, inter alia, the general authority to issue “ * * * such orders, rules, and regulations as it may find necessary or appropriate to carry out the provisions of this act. ” IS U.S.C. A. § 717<?

Since both petitions involve closely-related problems of fact and law, it was agreed by counsel that they might be argued and decided together. We will first discuss the contentions of petitioner, United Gas Pipe Line Company.

The regulation issued by the Commission, Order No. 144, requires the United Gas Pipe Line Company and all other companies similarly situated to file their rates in tariff-schedule form instead of as percentage contracts or as amendments to existing contracts, as has heretofore been done. 1 Since the Commission considered Order No. 144 a valid exercise of its rule-making power and hence legislative in nature, it did not hold a quasi-judicial hearing. It did, however, satisfy the requirements for rule-making established by Section 4 of the Administrative Procedure Act, 5 ‘U.S.C.A. § 1004. Thus, the, proposed regulations were published in the Federal Register before they were promulgated, interested persons were given an opportunity to submit written comments, a public hearing was held and oral argument heard, but no evidence was taken.

As petitioner views the case, although the regulations are procedural in form and superficially prospective in nature, they will in reality work a change in rates, cause certain provisions to be eliminated from its contracts, and will be retroactive in effect. 2

*798 Thus, the argument proceeds, a quasi-judicial hearing has been denied where it should have been granted for, under Section 5(a) of the Natural Gas Act, 15 U.S. C.A. § 717d(a), rates may be changed by the Commission only after a hearing is held and they have.been found to be unjust and unreasonable. Since-. Commission acceptance of this view would have resulted in an order reviewable- under Section 19(b), 15 U.S.C.A. § 717r(b), it is contended that, even absent such acceptance, review may be obtained here under-that section. Petitioner also appears to make an alternative argument — that since Order No. 144 operates upon it particularly and causes it irreparable injury, review may be obtained in this court under the authority of Columbia Broadcasting System v. United States, 1942, 316 U.S. 407, 62 S.Ct. 1194, 86 L.Ed. 1563.

Petitioner has mistaken its remedy. Although the distinction between rule and order is not always clearly definable, our authority to review orders of the Federal Power Commission under the Natural Gas Act does not suffer the same weakness. Not all orders were made reviewable under Section 19(b). As in the analogous provision of the Federal Power Act, Congress set out “a distinctive formulation of the conditions under which resort to the courts, may be made.” 3 On its face, the Act contemplates review of a decision.: based on evidence presented in a quasi-judicial proceeding before the Commission. 4 It spe- *799 ciñes that the Commission shall file with the proper circuit court of appeals “a transcript of the record upon which the order complained of was entered * * “The finding of the Commission as to the facts, if supported by substantial evidence, shall be conclusive”, etc. Unless the case comes to us after such a proceeding, we are given no authority to directly review the Commission’s action.

Review provisions such as 19(b) evidence Congressional recognition that an appellate court has no intelligible basis for decision unless a subordinate tribunal has made a record fully encompassing the issues. The wisdom of thus circumscribing the authority to review is readily apparent in this particular case. For we are asked to pierce form and find substance, to make an important decision concerning the scope of the Commission’s regulatory authority, merely on the basis of allegations in a Petition for Review. The central question here is the effect of Order No. 144 on certain contracts of petitioner. Yet we do not even have such contracts before us as part of the record. Nor do we have the aid of testimony, affidavits, etc. It is clear to us that decisions of this kind cannot be made in vacuo; and that Congress realized it when it made our review dependent upon the sort of conditions contained in Section 19(b).

This is not a case where the Commission has asserted authority under one of the many sections of the Act which specifically require a hearing. If a hearing had been denied under such circumstances, we would have no difficulty in ordering one to be held. Nor would we hesitate to ignore labels and take jurisdiction if this were a case where it was clear that the administrative order (denying treatment of certain documents as confidential) operated “particularly rather than generally * * * [and was] a judgment entered on a state of facts and affecting only one person.” 5 The present case is quite different. We have before us a rule directed to all companies similarly situated, and we have the Commission’s binding assurance that the regulations will operate only prospectively. 6 Under such circumstances, there is at the very least a strong presumption that the Commission has merely promulgated regulations of general applicability and not orders reviewable under Section 19(b).

We do not hold, however, that petitioner is left entirely without a remedy if, as it alleges, the regulations are merely a veiled way of striking at it without granting a hearing. Several remedies remain available. First, the regulations themselves make provision for an application for exception. 7 If this furnishes only a partial remedy, or no remedy at all, as petitioner *800 asserts, then the proper forum is the district court. The very- case upon which petitioner relies most strongly, Columbia Broadcasting System v. United States, 1942, 316 U.S. 407, 62 S.Ct. 1194, 86 L.Ed. 1563, points to that court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoffman v. IRS
Fourth Circuit, 1997
Gott v. Walters
756 F.2d 902 (D.C. Circuit, 1985)
Suburban O'Hare Commission v. Dole
603 F. Supp. 1013 (N.D. Illinois, 1985)
Cadc 79-71 City Of Rochester v. Bond
603 F.2d 927 (D.C. Circuit, 1979)
City of Rochester v. Bond
603 F.2d 927 (D.C. Circuit, 1979)
Sima Products Corp. v. McLucas
460 F. Supp. 128 (N.D. Illinois, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
181 F.2d 796, 86 U.S. App. D.C. 314, 1950 U.S. App. LEXIS 3842, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-gas-pipe-line-co-v-federal-power-commission-michigan-consolidated-cadc-1950.