United California Bank v. Maltzman

44 Cal. App. 3d 41, 118 Cal. Rptr. 299, 1974 Cal. App. LEXIS 741
CourtCalifornia Court of Appeal
DecidedDecember 23, 1974
DocketCiv. 43648
StatusPublished
Cited by15 cases

This text of 44 Cal. App. 3d 41 (United California Bank v. Maltzman) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United California Bank v. Maltzman, 44 Cal. App. 3d 41, 118 Cal. Rptr. 299, 1974 Cal. App. LEXIS 741 (Cal. Ct. App. 1974).

Opinion

Opinion

LORING, J. *

United California Bank (UCB), plaintiff and cross-defendant commenced this action to recover money alleged to be due under a contract, entered into as part of a loan transaction, entitled “Sponsors’ Loan Purchase Agreement.” The terms of this agreement required Elliott Maltzman, W. E. Robertson, Harold Pollack, Harriette Maltzman, Pearl Robertson and Joyce Pollack (sponsors) to purchase a certain promissory note upon the occurrence of certain conditions precedent.

Saymur Investment Corp., H. D. P. Corp. and E. B. M. Corp., doing business as Santa Clarita Village, a joint venture (joint venture) and sponsors cross-complained alleging that UCB failed to disburse funds promised to be loaned to the joint venture under a “Construction Loan Agreement.” After nonjury trial sponsors were found to be liable in the sum of $686,757.83, including principal, interest, and attorneys fees, together with costs of $447.90. The court also found that joint venture and sponsors were not entitled to recover anything from UCB under their cross-complaint. Sponsors and joint venture appeal from the entire judgment.

Contentions

Joint venture, as cross-complainant, and sponsors, as defendants,

*46 contend that:

I UCB’s refusal to disburse funds for the construction of on-site improvements constituted a material breach of contract and failure of consideration, excusing sponsors from any obligation to perform under Sponsors’ Loan Purchase Agreement, and entitling joint venture and sponsors to recover damages on their cross-complaint.

Sponsors, as defendants, contend on appeal that:

I Joint venture was not in default and the conditions precedent to sponsors’ obligations under Sponsors’ Loan Purchase Agreement did not occur.
II UCB failed to tender an assignment of the promissory, note and deed of trust to sponsors and thus sponsors are not obliged to pay UCB the sum demanded.
III Sponsors were in fact the principal obligors under the promissory note, and Code of Civil Procedure section 726 bars suit against sponsors unless the security for the loan is exhausted.
IV If Sponsors’ Loan Purchase Agreement is to be regarded as a true guarantee creating a separate obligation from the secured debt, sponsors were entitled to require UCB to proceed first against joint venture and the security as a prerequisite to asserting liability on their part and they are exonerated to the extent UCB failed to do so.
V The interest computed by UCB and awarded by the court is plainly excessive and contrary to the terms of the governing instruments.

Facts

In 1966, sponsors Elliott Maltzman and Harold Pollack entered into negotiations with Robert Hamer of UCB for a possible loan for the development of a parcel of land. Sponsors soúght financing for the construction of single family dwellings. The tract of land was then owned by Halell Corporation, which was owned by Maltzman and Pollack. There were 73 residential lots in the tract, including 6 lots that were improved with model homes.

Hamer made an independent credit investigation of Halell Corp., Maltzman and Pollack. Cost estimates were submitted by Maltzman *47 regarding off-site improvements (grading, curbing, gutters, sewers, storm drains and utilities) and on-site improvements (actual dwellings).

On March 16, 1967, UCB approved a loan of $1,273,000. to Halell to be personally guaranteed by Maltzman, Pollack, and their wives. But just prior to the actual consummation of the loan, a joint venture was formed, known as Santa Clarita Village, to carry out the development in lieu of Halell Corp. The joint venture acquired ownership of the tract from Halell Corp. The joint venture consisted of three corporations: Saymur Investment Corp., described as W. E. Robertson’s Corporation, E. B. M. Corp., whose officers were the Maltzmans and H. D. P. Corp., whose officers were the Pollacks. Robertson was brought into the joint venture because of his building experience and substantial personal wealth which might be needed by the joint venture. Hamer testified that, with the exception of Saymur Corp., the financial condition of the corporations was “less than minimal,” and that they were “shell corporations.” UCB entered into the loan agreement in reliance on the individual credit of the defendants and would not have done so but for their individual commitments.

By documents dated May 17, 1967, the negotiations were reduced to writing. The documents were prepared by UCB,. The Construction Loan Agreement was between UCB and joint venture. Under it a loan of $1,273,000 would be made by UCB to joint venture secured by a trust deed on the 67 lots. The improvements were to be completed within 180 days from the date the trust deed was recorded. Joint venture was also required to remit to UCB such funds as were required to assure full payment for all of the improvements. The loan was to be disbursed for certain allocated uses: the payment of an existing encumbrance, off-site improvements, actual loan expenses, and the remainder was to be released as construction on the remaining improvements progressed. This agreement also provided that irrespective of provisions in other documents, interest on the loan disbursed was to be 7 percent per annum from the respective date of advancement until 18 months from the date of agreement, and thereafter at a rate of 10 percent.

The promissory note was in the principal amount of $1,273,000, all of which was payable in one lump sum in 18 months. Interest was stated to be payable monthly, at a rate of 7 percent per annum.

By a separate letter dated May 17, 1967, from joint venture to UCB, attached to the Construction Loan Agreement, it was stated that joint venture would improve 30 lots with single family dwellings. Construction *48 of single family dwellings would not begin on the remaining 37 lots until it was mutually agreed that a satisfactory volume of sales of the first 30 lots had been effected.

Sponsors’ Loan Purchase Agreement provided in essence that upon the occurrence of the condition precedent that the joint venture had not completed construction in time or defaulted in any other obligation, sponsors agreed to purchase the loan, which was evidenced in part by the promissory note and deed of trust and the Construction Loan Agreement, by paying UCB the full amount of principal disbursed and interest which had accrued and attorney’s fees.

The deed of trust was recorded by UCB on October 2, 1967. Joint venture was delayed in initiating construction because of delay in obtaining a subdivision report from the California Real Estate Division. Off-site construction was started in early 1968. The off-site improvements were completed in the spring of 1969.

On February 6, 1968, Hamer inspected the tract. In a memorandum dated February 8, 1968, Hamer stated that Maltzman and Robertson were urged to delay commencement of on-site construction until the houses were tested for marketability. E. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rabo AgriFinance v. Valadao CA2/8
California Court of Appeal, 2023
The Joint Equity Committee v. Genovese CA4/3
California Court of Appeal, 2014
Truong v. Truong CA4/3
California Court of Appeal, 2013
Fort Bragg Unified School District v. Colonial American Casualty & Surety Co.
194 Cal. App. 4th 891 (California Court of Appeal, 2011)
Peregrine Funding, Inc. v. Sheppard Mullin Richter & Hampton LLP
35 Cal. Rptr. 3d 31 (California Court of Appeal, 2005)
San Diego Hospice v. County of San Diego
31 Cal. App. 4th 1048 (California Court of Appeal, 1995)
Golden Eagle Insurance v. First Nationwide Financial Corp.
26 Cal. App. 4th 160 (California Court of Appeal, 1994)
Okun v. Morton
203 Cal. App. 3d 805 (California Court of Appeal, 1988)
McNall v. Tatham
676 F. Supp. 987 (C.D. California, 1987)
Kennecott Corp. v. Union Oil Co.
196 Cal. App. 3d 1179 (California Court of Appeal, 1987)
Metzenbaum v. R.O.S. Associates
188 Cal. App. 3d 202 (California Court of Appeal, 1986)
Krueger v. Bank of America
145 Cal. App. 3d 204 (California Court of Appeal, 1983)
Sukut-Coulson, Inc. v. Allied Canon Co.
85 Cal. App. 3d 648 (California Court of Appeal, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
44 Cal. App. 3d 41, 118 Cal. Rptr. 299, 1974 Cal. App. LEXIS 741, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-california-bank-v-maltzman-calctapp-1974.