Unit Drilling Co. v. Enron Oil & Gas Co.

108 F.3d 1186
CourtCourt of Appeals for the Tenth Circuit
DecidedMarch 4, 1997
Docket95-7039, 95-7123 and 95-7125
StatusPublished
Cited by60 cases

This text of 108 F.3d 1186 (Unit Drilling Co. v. Enron Oil & Gas Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Unit Drilling Co. v. Enron Oil & Gas Co., 108 F.3d 1186 (10th Cir. 1997).

Opinion

EBEL, Circuit Judge.

Plaintiff-Appellant Unit Drilling Company sued Enron Oil & Gas Company to recover the contract price of drilling work that it had performed. The case was tried to a jury which returned an ambiguous verdict. The district court refused to ask the jury to clarify the verdict as requested by Unit, and ruled that Unit would recover no damages. We hold that the district court abused its discretion in refusing to clarify the verdict. We therefore reverse and remand for a new trial.

FACTS

This breach of contract case arises out of a well-drilling contract between Unit Drilling Company (Unit), a drilling contractor, and Enron Oil & Gas Company (Enron), an oil and gas producer. While Unit was drilling the well for Enron, drill pipes separated twice. Enron incurred additional costs to have the pipes repaired and then refused to pay the final invoices submitted by Unit, claiming that it was damaged by the pipe separation in an amount greater than the amount due on the final invoices. Unit brought a diversity action pursuant to 28 U.S.C. § 1332 (1994) to recover $157,262.36, the amount of Enron’s unpaid invoices. Enron claimed a set-off in the amount of $158,-444.73.

The case was tried to a jury. At the close of the evidence, the jury was given four general verdict forms. The jurors were instructed that if they found that Enron had breached the contract, they were to indicate that on Form 1, and go on to consider Enron’s claim for set-off. If they found that Enron did not breach the contract, they were to indicate that on Form 2, and not consider Enron’s claim for set-off. If they found that Enron was entitled to a set-off, they were to indicate that on Form 3. If they found against Enron on its claim for a set-off, they were to use Form 4.

The jurors were also instructed that if they found that Enron breached the contract, they could measure Unit’s damages in one of two ways. If they found that Unit fully performed the contract, they could award expectation damages of up to $157,262.36, the amount of the unpaid invoices. However, if they found that Unit only substantially performed the contract, they were to award the amount of the unpaid invoices, less the cost to Enron of correcting any defects that Unit caused. 1

The jury returned a verdict for Unit on its breach of contract claim and awarded it $70,-768.02 oil Form 1. It awarded Enron a set-off of $86,494.30 on Form 3. 2 The district court *1190 interpreted these verdicts to mean that Unit would recover no damages. To reach this conclusion, the court subtracted the amount of the set-off on Form 3 from the amount of damages on Form 1. Because the set-off was greater than the damages, the court awarded Unit no damages. 3 Unit objected to this interpretation of the verdicts, arguing that the jury itself had subtracted the amount of Enron’s set-off, $86,494.30, from the amount of the unpaid invoices, $157,262.36, to arrive at an award of $70,768.02. 4 Unit asserted that the jury intended it to receive a judgment of $70,768.02 after the set-off.

Before the jury was discharged, Unit asked the trial judge to question the jury to clarify the damage awards, but the court refused. The court also refused to grant plaintiffs motion for judgment as a matter of law or its motion for a new trial.

On appeal, Unit claims the district court erred (1) in instructing the jury, (2) in refusing to question the jury to clarify the verdict, and (3) in interpreting the jury’s damage awards. Unit also claims that the district court erred in excluding evidence of Enron’s dealings with another contractor. Both Unit and Enron also raise issues relating to awards of attorney fees and costs.

A. Jury Instructions

Unit contends that the trial court erred in giving confusing jury instructions. However, Unit waived its right to claim error in the instructions by failing to object specifically at trial to the defect in the jury instructions of which it now complains. Under Fed. R.Civ.P. 51 “[n]o party may assign as error the giving or the failure to give an instruction unless that party objects thereto before the jury retires to consider its verdict, stating distinctly the matter objected to and the grounds of the objection.” See also Neu v. Grant, 548 F.2d 281, 287 (10th Cir.1977) (“The need for specific objection applies to ... instructing the jury_”).

During the trial, Unit raised two specific objections to the jury instructions. Neither objection related to the possibility that the jury would reduce Unit’s award by the cost to Enron of fixing the pipes and separately award Enron the same damages on its claim for a set-off. Unit complained generally that the verdict forms were “extremely difficult to understand.” However, when the trial judge asked Unit to suggest a way to make the forms more understandable, Unit did not provide one. The confusion encountered in the verdict forms could have been cured with an instruction telling the jury that if they reduced Unit’s Form 1 award of damages by the amount it cost Enron to fix the pipes, they should not also award that amount to Enron as a set-off on Form 3. 5 However, Unit sought no such instruction.

Where the issue of jury instructions is not preserved for appeal, the court reviews the instructions for plain error. United States v. Zimmerman, 943 F.2d 1204, 1213 (10th Cir.1991). Plain error requires a finding that the instructions were “patently plainly erroneous and prejudicial.” Moe v. Avions Marcel Dassault-Breguet Aviation, 727 F.2d 917, 924 (10th Cir.1984). The instructions given may have led the jury erroneously to award the plaintiff damages under *1191 a formula for substantial performance, thus reducing Unit’s damages by the cost to Enron of fixing the pipes, and separately to award Enron the cost of the repairs as a set-off. Alternatively, the instructions may have confused the jury about how to fill out the verdict forms. On the whole, however, the instructions given were a correct statement of the law and the imperfections in them did not rise to the level of plain error.

B. Questioning of Jurors

Unit next claims that the trial court erred in refusing to ask the jury to clarify its damage awards when an ambiguity developed and Unit specifically requested clarification before the jury was discharged. We agree. In Resolution Trust Corp. v. Stone,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sepi v. Netflix
Tenth Circuit, 2024
Jensen v. West Jordan City
Tenth Circuit, 2020
Fox v. Pittsburg State University
257 F. Supp. 3d 1112 (D. Kansas, 2017)
Retiree, Inc. v. Anspach
95 F. Supp. 3d 1303 (D. Kansas, 2015)
Weitz Co. LLC v. MacKenzie House, LLC
665 F.3d 970 (Eighth Circuit, 2012)
Cook v. Rockwell International Corp.
564 F. Supp. 2d 1189 (D. Colorado, 2008)
Hardman v. Autozone, Inc.
Tenth Circuit, 2007
Johnson Ex Rel. Estate of Cano v. Holmes
455 F.3d 1133 (Tenth Circuit, 2006)
Nichols v. Bell
440 F. Supp. 2d 730 (E.D. Tennessee, 2006)
Markham v. National States Insurance
122 F. App'x 392 (Tenth Circuit, 2004)
Eggert v. Wasatch Energy Corp.
2004 UT 28 (Utah Supreme Court, 2004)
McQuay v. Penn-America Insurance
91 F. App'x 626 (Tenth Circuit, 2003)
Winner Intern. Corp. v. Common Sense, Inc.
863 So. 2d 1088 (Supreme Court of Alabama, 2003)
TC Systems Inc. v. Town of Colonie, New York
213 F. Supp. 2d 171 (N.D. New York, 2002)
Rahn v. Junction City Foundry, Inc.
161 F. Supp. 2d 1219 (D. Kansas, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
108 F.3d 1186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/unit-drilling-co-v-enron-oil-gas-co-ca10-1997.