Unis v. JTS Constructors/Managers, Inc.

541 So. 2d 278, 1989 WL 22852
CourtLouisiana Court of Appeal
DecidedMarch 15, 1989
Docket87-1292
StatusPublished
Cited by7 cases

This text of 541 So. 2d 278 (Unis v. JTS Constructors/Managers, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Unis v. JTS Constructors/Managers, Inc., 541 So. 2d 278, 1989 WL 22852 (La. Ct. App. 1989).

Opinion

541 So.2d 278 (1989)

Jack R. UNIS, d/b/a R.J. Insulation, Plaintiff-Appellee,
v.
JTS CONSTRUCTORS/MANAGERS, INC., JTS Realty XVII, Joseph T. Spinosa, and David B. Ammons, Defendants-Appellants.

No. 87-1292.

Court of Appeal of Louisiana, Third Circuit.

March 15, 1989.

*279 David W. Burton, Deridder, for plaintiff-appellee.

Rubin, Curry, Colvin & Joseph, Stephen P. Strohschein, Baton Rouge, for defendants-appellants.

Before DOMENGEAUX, FORET and YELVERTON, JJ.

DOMENGEAUX, Judge.

This opinion will address the issues presented for review in the consolidated cases entitled: Jack R. Unis, d/b/a R.J. Insulation v. JTS Constructors/Managers, Inc., JTS Realty XVII, Joseph T. Spinosa, and David B. Ammons; Jack R. Unis, II v. JTS Constructors/Managers, Inc., Et al.; and Jack R. Unis, II v. JTS Constructors/Managers, Inc., Et al., respectively numbered by our Clerk of Court 87-1292, 87-1293 and 87-1294. These suits, which were tried in the Parish of Beauregard, were originally filed in the Parishes of Beauregard, Lafayette and Iberia and were respectively numbered by the Clerks of the District Courts C-85-612, 85-8259-C and 59484-D. We will, for the reasons hereinafter set forth, decide all issues in this opinion but, will render separate decrees in the two suits entitled: Jack R. Unis, II v. JTS Constructors/Managers, Inc., Et al., respectively filed in the Parishes of Lafayette and Iberia and numbered by our Clerk 87-1293 and 87-1294.

These actions arose as the result of five construction contracts entered into between *280 Jack R. Unis, II (Unis), a painting and insulation subcontractor doing business as R.J. Insulation and JTS Constructors/Managers, Inc. (JTS Constructors), a general contractor. The contracts concerned the painting and insulation of three apartment complexes of approximately 50,000 square feet each of which the overall construction was undertaken by JTS Constructors. The construction projects were referred to as the Palmetto Creek Project in Beauregard Parish, the Ridgeview Project in Lafayette Parish and the Evangeline Trace Project in Iberia Parish. Unis entered into three separate subcontracts with JTS Constructors to perform the insulation work on the projects. Unis also entered into two additional subcontracts with JTS Constructors which called for the painting of the Ridgeview and Evangeline Trace Projects. The subcontractor did not contract to paint the Palmetto Creek Project.

Unis commenced these proceedings against JTS Constructors seeking sums allegedly outstanding for the work performed according to the construction subcontracts.[1] The plaintiff also sought recovery as provided by La.R.S. 9:2784 (1984) for JTS Constructors' alleged failure to pay Unis "without reasonable cause" within twenty-one consecutive days after receiving payment from the owner of the projects. R.S. 9:2784(C) provides, in part, for a penalty:

in the amount of one-half of one percent of the amount due, per day, from the expiration of the period allowed herein for payment after the receipt of payment from the owner.

The statute places a ceiling on the penalty of fifteen percent of the outstanding balance unreasonably withheld.

JTS Constructors answered Unis' petition alleging that the plaintiff had not performed according to the terms and conditions of the subcontracts and that it was justified in removing Unis from the Ridgeview and Evangeline Trace Projects for delays in performance and poor workmanship. The defendant's answers in the Ridgeview and Evangeline Trace suits also included reconventional demands seeking sums in excess of the original contract price allegedly expended to fulfill Unis' painting obligations on the projects. JTS Constructors sought, in the alternative, compensation (set-off) for any sums it might owe Unis against the unanticipated expenses it incurred to cover Unis' alleged breach of its painting subcontracts on the Ridgeview and Evangeline Trace Projects. The defendant's pleadings also sought to have Unis held liable for the liquidated damages it incurred for its own delay in performance as the general contractor. Subsequent to both answering the plaintiff's suits and their consolidation, JTS Constructors filed two "Supplemental and Amending Reconventional Demand[s]" seeking liquidated damages from Unis allegedly in accordance with the terms of the Ridgeview and Evangeline Trace painting subcontracts.

The Trial Judge, in his "Reasons For Judgment" initially addressed the parties' disputes concerning the three insulation subcontracts. The Court accepted the parties' stipulation that Unis was due $17,195.90 for his work on the Palmetto Creek Project and then concluded that the insulation work on both the Ridgeview Project and the Evangeline Trace Project was substantially performed. The Court concluded that the contract price for the insulation of the Ridgeview Project was $17,302.65, that Unis had been paid $15,572.38 and that JTS Constructors was indebted unto Unis for the $1,730.27 balance. The Judge then determined that the contract price for the insulation of the Evangeline Trace Project was $20,142.17, that Unis had received $13,091.54 and that $7,050.63 remained to be paid to Unis.

The Trial Judge next reviewed R.S. 9:2784 to determine if Unis was entitled to any statutory penalties. The Trial Court reasoned that Unis was entitled to no penalties *281 for the sums withheld by JTS Constructors on the Ridegview and Evangeline Trace Projects because it was reasonably withheld pending a resolution of the parties' disputes over the painting subcontracts. The Court was of the opinion, however, that Unis was entitled to recover penalties on the Palmetto Creek Project because the parties stipulated to the amount owed and because there was no painting or other work over which the parties had any dispute. Simply stated, the Trial Judge held that because no disputes existed between the parties over the Palmetto Creek Project, it was unreasonable for JTS Constructors to withhold payment. Unis was awarded a fifteen percent penalty on the $17,195.50 withheld which amounted to $2,579.38.

Subsequent to resolving the disputes concerning the insulation subcontracts, the Trial Court addressed the Ridgeview and Evangeline Trace painting subcontract disputes. The Court was of the opinion that the painting work at the Ridgeview Project had been substantially performed by Unis before he was ordered off the job on January 25, 1985, despite also concluding that there was some unfinished work and that some of the completed work was substandard. The Judge reasoned that because the contract had been substantially performed Unis was entitled to the full contract price, $44,800.00, less reasonable costs incurred by JTS Constructors in obtaining full performance, including the recompletion of unsatisfactory work. Unis argued that the project was ninety-seven percent complete when he was ordered off the job, that he had been paid $34,272.00 by that time and that he was due $9,184.00 which would compensate him in an amount equal to ninety-seven percent of the contract price. JTS Constructors presented evidence that it cost the company $17,000.00 to have J.D. Gaudet Painters, another painting subcontractor, complete the Ridgeview painting work, $6,572.00 more than the Unis contract price, and that it was entitled to recover the amount in excess of the original contract price from Unis.

The Trial Court held that JTS Constructors was justified in terminating Unis, but declined to render judgment on this issue in favor of either party.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cal's A/C & Elec v. Famous Const Corp
220 F.3d 326 (Fifth Circuit, 2000)
Pipe Liners, Inc. v. Edenwald Contracting Co.
610 So. 2d 1109 (Louisiana Court of Appeal, 1992)
Unis v. JTS Constructors/Managers, Inc.
541 So. 2d 284 (Louisiana Court of Appeal, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
541 So. 2d 278, 1989 WL 22852, Counsel Stack Legal Research, https://law.counselstack.com/opinion/unis-v-jts-constructorsmanagers-inc-lactapp-1989.