Union Railroad v. Dull

124 U.S. 173, 8 S. Ct. 433, 31 L. Ed. 417, 1888 U.S. LEXIS 1850
CourtSupreme Court of the United States
DecidedJanuary 16, 1888
StatusPublished
Cited by19 cases

This text of 124 U.S. 173 (Union Railroad v. Dull) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Union Railroad v. Dull, 124 U.S. 173, 8 S. Ct. 433, 31 L. Ed. 417, 1888 U.S. LEXIS 1850 (1888).

Opinion

Me. Justice HablaN

delivered the opinion of the court.

This suit was brought by the appellant in the Circuit Court of Baltimore City, and was subsequently removed into the Circuit Court of the United States for the District of Maryland. Its principal object was to obtain a decree setting aside, as void against the appellant, certain construction contracts between the Union Kailroad ■ Company of Baltimore, James J. Dull, 'William M. Wiley, and,K. Snowden Andrews; a contract of arbitration between that company and James J. Dull, surviving partner of "William M. Wiley, together with the award of the arbitrators, and the judgment entered pursuant thereto; and, also, a written agreement between the *175 Canton Company of Baltimore and James J. Dull, surviving1 partner of William M. Wiley, together with certain promissory notes' given in ’execution of the last named agreement.. A part of the relief asked was a decree compelling James J.. Dull, as surviving partner, Samuel M. Shoemaker, (now deceased, and whose administrators with the will annexed are -before the court,) and John Ellicotfc, to refund certain sums, which they had received on account of the judgment based upon said award, and on said promissory notes.

The defendants, Dull, Shoemaker, and Ellicott, were required to answer, and did answer, under oath, not only the-material allegations of the bill, but various special interrogatories propounded to them. Upon final hearing, the injunction granted at the commencement of the suit was dissolved, and the bill dismissed. Of that decree the appellant complains.

Stating only such facts as are clearly established by the-answers made under oath, Vigel v. Hopp, 104 U. S. 441, 2 Story Eq. § 1528, by the exhibits, and by the depositions, the case before us is, in substance, as follows:

On "the first day of May, 1871, the railroad company made a written agreement with Dull, Wiley, and Andrews, for the construction by those parties, for the prices and upon the .terms therein stated, and to the satisfaction and acceptance of its chief engineer, of the graduation and masonry of, section ‘1 of said railroad, including a tunnel under the bed of Hoffman Street, in the city of Baltimore, and such other work as might be necessary tó finish that section in accordance with the specifications and agreeably to such directions as might be given by the company’s chief engineer, or by his assistant in charge of the work for the time being. The contractors agreed to complete the work on or before January, 1873, the parties expressly stipulating that the time so named should be of the essence of the contract.

On the 1st of May, 1871, the parties entered into a supplementary agreement, providing for the indemnification of the company against all claims or damages arising from the tunnel or excavation work under the bed of Hoffman Street.

*176 Shortly thereafter, Andrews, with the consent of the company, assigned and released to Dull and Wiley all his interest' in the original and supplemental agreements.

On the 20th of December 1875, Wiley having died, and Dull, as surviving partner, having instituted suit against the railroad company in the Baltimore City Court, a written agreement was entered into between the company and Dull, as such surviving partner, which is at the foundation of the present litigation. That agreement recites the completion of the work covered by the original'and supplemental agreements of May and July, 1871; the claim by Dull of a large balance due him as surviving partner; a dispute between the parties as to what was due from the railroad company under said contracts of construction, as well as for work done and materials furnished by the contractors; the claim of Dull, as surviving partner, to be paid for certain stone used by the contractors, in addition to what was required by said agreements; the claim of th¿ company that the contractors had not finished the work within the time stipulated, and in a substantial manner, to the satisfaction, and' acceptance of the chief engineer or his assistant in charge of the work for. the time being,; its claim that it' had been compelled to pay damages aghinst which the contractors could, with due care, have guarded them; and the claim of the company, that, ■after deducting its said demands, it was entitled to recover á balance. By this agreement, all matters of difference between the parties, and- their respective claims against each other, were referred to the arbitration of indifferent persons to be chosen as follows: one by each party, the two thus chosen to select a third arbitrator, and no one of the arbitrators to be. a lawyer. The arbitrators were authorized to determine such matters of difference, and award what sum should be paid by the railroad company to Dull, or by the latter to- the ¡former, and the award to be “ final and conclusive in the premises.”

The agreement further provided that the action of Dull, then docketed in- the Baltimore City Court, should, by rule of nou-rt, “ be submitted and referred to the award and arbitra *177 ment of the said three arbitrators, whose award, or the award of a majority of them in the premises, shall be returned to said court, to the end that judgment may be given therein in accordance with the provisions of Article VII. of the Maryland Code of Public General Laws; ” further, that the true construction, meaning, and extent of. certain covenants in the supplemental agreement should be finally and conclusively determined by Alexander Sterling, jr., esquire.

Pursuant to this agreement, Henry Tyson and Eobert K. Martin were selected by the parties, respectively, as arbitrators. They concurred in selecting H. D. "Whitcomb as the third arbitrator. By consent an order was passed in the Baltimore City Court,.referring the case pending there to said arbitrators. Upon full examination of all matters and claims in dispute, they unanimously awarded $54,159.50 to be paid by the company to Dull, and judgment for that amount was, accordingly, entered, in the Baltimore City Court, on the 11th ■ of- January, 1877, in favor of Dull, surviving partner of Wiley.

On the 25th of February, 1877, a written agreement was entered into between Dub and the Canton Company of Baltimore, whereby the former agreed, among other things, to delay action upon his judgment, and to accept payment of the balance then due upon it —$47,562.15 — as follows: $5000, July 2,1877; $10,000, February 7,1878; $14,000, February 7, 1879; $18,562.15, February 7, 1880; for which amounts the Union Eailroad Company executed to Dull its promissory notes, as well as interest notes for $1276.86, $1298.14, $976.86, $993.14, $556.86, and $556.14. These notes, principal and interest, were guaranteed by the Canton Company. The latter agreed that it would pay each note within one week after default by the railroad company. Dull reserved the right, in addition to his recourse on the Canton Company, to sue out execution on his judgment against the railroad company for any balance due thereon at the time of default in paying any of said notes at maturity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Special March 1981 Grand Jury
753 F.2d 575 (Seventh Circuit, 1985)
Jicarilla Apache Tribe v. Andrus
687 F.2d 1324 (Tenth Circuit, 1982)
Eaton v. Sontag
387 A.2d 33 (Supreme Judicial Court of Maine, 1978)
United States v. Ehrlichman
376 F. Supp. 29 (District of Columbia, 1974)
Pacific Royalty Co. v. Williams
227 F.2d 49 (Tenth Circuit, 1955)
Nixon v. Temple Terrace Estates, Inc.
121 So. 475 (Supreme Court of Florida, 1929)
Johnson v. Curley
257 P. 163 (California Court of Appeal, 1927)
Demarest v. Winchester Repeating Arms Co.
257 F. 162 (D. Connecticut, 1919)
Getchell v. Kirkby
92 A. 1007 (Supreme Judicial Court of Maine, 1915)
Schinzer v. Wyman
146 N.W. 898 (North Dakota Supreme Court, 1914)
Campbell v. Northwest Eckington Improvement Co.
229 U.S. 561 (Supreme Court, 1913)
Kennedy v. Custer
174 F. 972 (Eighth Circuit, 1909)
Fairchild v. Dement
164 F. 200 (U.S. Circuit Court for the Northern District of Illnois, 1908)
Western Maryland Railway Co. v. Kehoe
1 Balt. C. Rep. 753 (Baltimore City Circuit Court, 1898)
Cincinnati, H. & D. R. v. McKeen
64 F. 36 (Seventh Circuit, 1894)
Peeler v. Lathrop
48 F. 780 (Fifth Circuit, 1891)
Watkins v. Bryant
27 P. 775 (California Supreme Court, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
124 U.S. 173, 8 S. Ct. 433, 31 L. Ed. 417, 1888 U.S. LEXIS 1850, Counsel Stack Legal Research, https://law.counselstack.com/opinion/union-railroad-v-dull-scotus-1888.