Union Paving Co. v. United States ex rel. Soule Steel Co.

150 F.2d 390, 1945 U.S. App. LEXIS 3299
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 29, 1945
DocketNo. 10571
StatusPublished
Cited by3 cases

This text of 150 F.2d 390 (Union Paving Co. v. United States ex rel. Soule Steel Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Union Paving Co. v. United States ex rel. Soule Steel Co., 150 F.2d 390, 1945 U.S. App. LEXIS 3299 (9th Cir. 1945).

Opinion

MATHEWS, Circuit Judge.

On November 4, 1939, a contract was awarded to Union Paving Company, hereafter called Union, for the construction of public work of the United States, namely, abutments and piers for a bridge over the Pit River in California. The work was more particularly described in specifications which were part of the contract. The contract was to be performed and executed in the Northern District of California. The total amount payable by the terms of the contract was $1,138,288. Before the contract was awarded, Union furnished to the United States, for the protection of persons supplying labor and material in the prosecution of the work, a payment bond in the sum of $455,315.20 (40% of $1,138,288), as required by § 1 of the Act of August 24, 1935, c. 642, 49 Stat. 793, 40 U.S.C.A. § 270a. Sureties on the bond were Pacific Indemnity Company and Maryland Casualty Company. On January 6, 1940, Union made a subcontract with Soule Steel Company, hereafter called Soule, whereby Soule agreed to do a part of the work — ■ the part described in the subcontract. The subcontract provided:

“The subcontractor [Soule] at its own cost agrees to provide all labor, materials, tools and equipment or other means and promptly unload all reinforcement bars1 from cars delivered at Redding, California2 check and haul the same to the job site and provide suitable warehouse or other means of protection for any material requiring storage or protection * * *

“The subcontractor at its own cost agrees to provide all labor, wire, wire ties, rods or other materials and appliances used for securing reinforcement bars, metal or other temporary supports, if used, to hold reinforcement bars during the placing of concrete, including backing-up strip required for welding * * *

“The subcontractor at its own cost agrees to provide all labor, materials and equipment and cut the ends of the bars for welding and provide all clamps, tie rods, cables, blocking, anchors and other accessories that may be required, including the placement of backing-up strips, and shall firmly and securely hold the reinforcing bars in position while the joints are being welded * * *

“The subcontractor at its own cost agrees to provide all labor, materials, tools, accessories and equipment and perform and observe all the provisions contained in paragraph 66 of [the specifications of Union’s contract with the United States].3

[392]*392“Time is of the essence of this agreement and the subcontractor agrees that it will proceed with the placing of reinforcement bars in sections of the piers and abutments made ready for such placement immediately after being notified by the contractor [Union] of the readiness of each section and prosecute the same diligently to completion, unless prevented by strikes, lockouts or other contingencies beyond its control. * * *

“The contractor at its own cost agrees to provide an accessible roadway from Highway 99 to the base of all piers and abutments ; construct a wooden trestle over and about the base of all pier excavations and construct wooden cores as shown on the plans which may be used by the subcontractor as a supplementary support for reinforcement bars; * * *

“The contractor agrees to pay said subcontractor for placing reinforcement bars at the rate of $22.50 per ton for reinforcement bars actually placed in accordance with the plans and specifications, which shall be considered as full compensation for unloading, warehousing, hauling, bending and placing reinforcement bars and clamps, and doing all work necessary or incidental thereto and for furnishing all tie wire, clamps and supporting devices. * * *

“Payments are to be made to subcontractor on or about the 10th of the following month for 85% of the value of the work performed during the preceding month, and the remaining l5% to be paid thirty days after completion of said subcontractor’s portion of the work.”

Between January 6, 1940, and May 31, 1941, Soule placed 5,533.125 tons of reinforcement bars, as required by the subcontract, and, at Union’s request, supplied labor and materials which were not required by the subcontract, but were required by Union’s contract with the United States, and were of the reasonable value of $671.84. The work provided for in the subcontract was completed on or about May 31, 1941. Soule was charged by Union $102.18 for reinforcement bars delivered to Soule and not accounted for and was paid by Union $47,712.35 on or before July 18, 1941, and $16,000 on December 31, 1941. There was no further payment.

A suit against Union and its sureties was brought in the name of the United States for the use of Soule.4 The complaint alleged that from July 18, 1941, to December 31, 1941, Union owed Soule the principal sum of $77,352.62, and that from and after December 31, 1941, Union owed Soule the principal sum of $61,352.62.5 The complaint prayed judgment for $61,-352.62, for interest on $77,352.62 from July 18, 1941, to December 31, 1941, for interest on $61,352.62 from December 31, 1941, until paid, and for costs. Union and its sureties answered the complaint, jury trial was waived, the case was tried by the court, findings of fact and conclusions of law were stated, and judgment was entered as prayed in the complaint. Union and its sureties have appealed.

Questions presented are (1) whether, by the terms of the subcontract, Soule was obligated to pay the cost of the falsework hereinafter mentioned; (2) whether, upon learning that it was being charged with the cost of the falsework, it was Soule’s duty to rescind the subcontract; and (3) whether the court erred in admitting evidence of negotiations leading up to the subcontract.

[393]*393I. The evidence showed that in one of the abutments and seven of the piers (abutment 1 and piers 1-7) provided for in Union’s contract with the United States, Union erected falsework;6 that Union used the falsework in pouring concrete; and that Soule used it to support and hold reinforcement bars while concrete was being poured. After October 18, 1940, Union charged Soule for erecting falsework $61,-112.35 (claimed to be its cost), contending that, by the terms of the subcontract, Souie was obligated to erect the falsework or to pay the cost thereof. Soule contended that, by the terms of the subcontract, Union was obligated to construct the false-work at its own cost.

The subcontract did not provide that Soule should pour any concrete or erect any falsework to be used in pouring concrete. It did not, in terms, provide for the erection of falsework for any purpose. It did, however, provide that Soule should, at its own cost, “provide all * * * metal or other temporary supports, if used, to hold reinforcement bars during the placing of concrete.” Union contended that the falsework erected in abutment 1 and piers 1-7 constituted such a “temporary support.” The subcontract also provided that Soule should “proceed with the placing of reinforcement bars in sections of the piers and abutments made ready for such placement immediately after being notified by [Union] of the readiness of each section.” Obviously, the duty of making the sections “ready” rested on Union, not on Soule. Soule contended that the erection of falsework in abutment 1 and piers 1-7 was a part of that duty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
150 F.2d 390, 1945 U.S. App. LEXIS 3299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/union-paving-co-v-united-states-ex-rel-soule-steel-co-ca9-1945.