Underground Construction v. City of Oakland CA1/4

CourtCalifornia Court of Appeal
DecidedMay 15, 2013
DocketA130752
StatusUnpublished

This text of Underground Construction v. City of Oakland CA1/4 (Underground Construction v. City of Oakland CA1/4) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Underground Construction v. City of Oakland CA1/4, (Cal. Ct. App. 2013).

Opinion

Filed 5/15/13 Underground Construction v. City of Oakland CA1/4 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION FOUR

UNDERGROUND CONSTRUCTION CO., INC., Plaintiff and Appellant, A130752

v. (Alameda County CITY OF OAKLAND, Super. Ct. No. RG07363440) Defendant and Appellant.

I. INTRODUCTION Underground Construction Co., Inc. (Underground) worked on a construction project in Oakland (the Project) that included relocating existing overhead electrical, telephone, and cable television lines into conduit laid in underground trenches; removing and replacing sidewalks and adding ramps; and installing utility boxes and street light foundations. During the course of the Project, disputes arose between Underground, the City of Oakland (the City), and the owners of the affected utility lines1 regarding how much Underground was owed for certain aspects of the work. Ultimately, Underground

1 The utility lines being moved belonged to Comcast of California/Colorado, LLC (Comcast); Pacific Gas and Electric (PG&E); and Pacific Telephone and Telegraph (AT&T). AT&T was variously known during some of the relevant time periods as Pacific Telephone and Telegraph, Pacific Bell, or SBC, but for simplicity, we will refer to it simply as AT&T. We will refer to Comcast, PG&E, and AT&T collectively as the Utilities.

1 sued the City and the Utilities (collectively the Owner Parties) for additional sums it alleged were due under the contract for the Project. Underground and the Owner Parties participated in a mediation, which resulted in a settlement as between Underground and the Utilities. Underground took the position that the City had also agreed to a settlement. However, the trial court denied Underground’s motion to enforce the settlement agreement against the City, and the case between Underground and the City went to jury trial. The jury rendered a verdict in favor of Underground on most of its claims, but ruled in the City’s favor on Underground’s statutory claim for prompt payment. The trial court declined to reduce the amount of the verdict against the City by the amounts Underground had received from the Utilities under the settlement agreement. In postjudgment orders, the trial court denied Underground’s motion for attorney fees, and granted Underground’s motion to strike the City’s cost bill. The City timely appealed from the judgment. The City did not file a separate notice of appeal from the trial court’s postjudgment orders, but argues that the trial court should have awarded it attorney fees. Underground appealed from the denial of its motion for attorney fees. Underground also filed a protective cross-appeal from the trial court’s denial of its motion to enforce the settlement agreement against the City. We affirm the judgment, affirm the denial of Underground’s postjudgment motion for attorney fees, deny the City’s purported claim for attorney fees, and dismiss Underground’s protective cross-appeal as moot.

2 II. FACTS AND PROCEDURAL BACKGROUND A. The Project and the Contract Although each of the Utilities participated in the design and planning of the Project, the City took the lead in obtaining competitive bids for the work.2 Because the parties expected that the exact scope of the Project would require adjustment during the course of the work, the City used a unit price system to facilitate comparing bids. Under that system, the City divided the work into various categories (such as trenches and sidewalk concrete paving), and provided an estimate of the number of units of work to be done within each category (such as linear feet for trenches, or square feet for sidewalk concrete paving). The contractors bidding on the contract were required to provide a price per unit for each category of work. This enabled the City to compare bids by multiplying the price per unit times the estimated number of units, even though the City did not know the exact number of units of work that ultimately would be required (and, by the same token, the bidders did not know exactly how much they ultimately would receive). Underground was initially the second lowest bidder, but the lowest bidder withdrew its bid, so the Project was awarded to Underground. Work on the Project was delayed for over a year after that, due to disagreements between the Utilities and the City regarding the terms of the contract for the Project. Ultimately, Underground and the City (but not the Utilities, except for Comcast) signed a contract (the Contract), which incorporated by reference a voluminous package of contract documents, including a set of standard specifications referred to as the “Green Book” or “greenbook” (the Green Book). The Utilities that did not actually sign the

2 “As is required on review after a jury trial, in reciting the facts, we ‘resolv[e] . . . all conflicts in the evidence and all legitimate and reasonable inferences that may arise therefrom in favor of the jury’s findings and the verdict. [Citations.]’ [Citation.]” (Bankhead v. ArvinMeritor, Inc. (2012) 205 Cal.App.4th 68, 73.) In this section, we provide only a brief overview of basic background facts that are largely uncontroverted. Additional factual details are included in our discussion of the parties’ contentions on appeal.

3 Contract nonetheless paid for portions of the work based on a billing formula established under the Contract. During the course of the work on the Project and after its completion, disputes arose among the Parties regarding the amount Underground was entitled to be paid for various aspects of the work. Some of these disputes were resolved before the trial underlying this appeal. We briefly outline the remaining disputes in the next two sections. B. Underground’s Claims for Additional Payment 1. Additional Sidewalk Concrete Removal Portions of the trenches included in the Project ran underneath sidewalks, which had to be removed for construction of the trench, and then replaced. The Contract’s express terms required that when a portion of sidewalk was removed and later replaced, this had to be done along the “score lines” dividing the sidewalk into “flags” (rectangles of concrete bounded by visible lines). Thus, Underground’s bid contemplated that whenever the trench construction required removal of any part of a sidewalk flag, the entire flag, approximately two and one-half feet wide, would have to be removed and replaced. As the Project progressed, the amount of sidewalk that Underground had to remove and replace on either side of the trenches turned out, in many areas, to be considerably wider than the contemplated two and one-half feet. This occurred for at least two, and possibly three reasons. First, the existing sidewalks in the area of the Project proved to be in poor condition. As a result, the City required Underground to remove and replace not only the flags situated immediately above the trenches, but also additional adjacent portions of the sidewalks. Second, the City had a rule (the six-foot rule) requiring that when the sidewalk above a section of trench was less than six feet wide, the entire sidewalk had to be removed and replaced. The six-foot rule was not referenced in the Contract, and apparently was not disclosed to Underground prior to its bid. Third, according to the City, Underground damaged portions of the existing sidewalks during the course of the work, which it was obligated under the Contract to

4 remove and replace, and removed other portions for its own convenience, which it also had to replace.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Williams
940 P.2d 710 (California Supreme Court, 1997)
People v. Harrison
768 P.2d 1078 (California Supreme Court, 1989)
Soule v. General Motors Corp.
882 P.2d 298 (California Supreme Court, 1994)
Shamblin v. Brattain
749 P.2d 339 (California Supreme Court, 1988)
People v. Overstreet
726 P.2d 1288 (California Supreme Court, 1986)
In Re Marriage of Flaherty
646 P.2d 179 (California Supreme Court, 1982)
City of Los Angeles v. Retlaw Enterprises, Inc.
546 P.2d 1380 (California Supreme Court, 1976)
Western Land Office, Inc. v. Cervantes
175 Cal. App. 3d 724 (California Court of Appeal, 1985)
County of Nevada v. Kinicki
106 Cal. App. 3d 357 (California Court of Appeal, 1980)
Norman I. Krug Real Estate Investments, Inc. v. Praszker
220 Cal. App. 3d 35 (California Court of Appeal, 1990)
Fibreboard Paper Products Corp. v. East Bay Union of MacHinists, Local 1304
227 Cal. App. 2d 675 (California Court of Appeal, 1964)
Denver D. Darling, Inc. v. Controlled Environments Construction, Inc.
108 Cal. Rptr. 2d 213 (California Court of Appeal, 2001)
Taylor v. Van-Catlin Construction
30 Cal. Rptr. 3d 690 (California Court of Appeal, 2005)
Rael v. Davis
166 Cal. App. 4th 1608 (California Court of Appeal, 2008)
Arntz Builders v. City of Berkeley
166 Cal. App. 4th 276 (California Court of Appeal, 2008)
Major v. Western Home Insurance
169 Cal. App. 4th 1197 (California Court of Appeal, 2009)
Colony Hill v. Ghamaty
50 Cal. Rptr. 3d 247 (California Court of Appeal, 2006)
Red Mountain, LLC v. Fallbrook Public Utility District
48 Cal. Rptr. 3d 875 (California Court of Appeal, 2006)
R. P. Richards, Inc. v. Chartered Construction Corp.
99 Cal. Rptr. 2d 425 (California Court of Appeal, 2000)
DeZerega v. Meggs
99 Cal. Rptr. 2d 366 (California Court of Appeal, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Underground Construction v. City of Oakland CA1/4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/underground-construction-v-city-of-oakland-ca14-calctapp-2013.