Underground Boring v. P Mining

CourtCourt of Appeals of South Carolina
DecidedJuly 21, 2011
Docket2011-UP-372
StatusUnpublished

This text of Underground Boring v. P Mining (Underground Boring v. P Mining) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Underground Boring v. P Mining, (S.C. Ct. App. 2011).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals

Underground Boring, LLC, Respondent,

v.

P Mining, Inc., Appellant.


Appeal From Horry County
Steven H. John, Circuit Court Judge


Unpublished Opinion No. 2011-UP-372
Submitted April 1, 2011 – Filed July 21, 2011   


AFFIRMED


Douglas Charles Baxter, of Myrtle Beach, and Mason A. Summers, of Columbia, for Appellant.

William A. Bryan, of Surfside Beach, for Respondent.

PER CURIAM: In this breach of contract action, P Mining appeals the trial court's judgment in favor of Underground Boring in the amount of $99,041.35 plus $29,369.48 in prejudgment interest.  We affirm.[1] 

FACTS/PROCEDURAL HISTORY

The City of North Myrtle Beach (the City) hired P Mining to replace all overhead utility lines with underground ones.  It provided P Mining with plans and detailed specifications for the project.  P Mining subcontracted with Underground Boring for boring and installation of conduit.  The parties entered into a one-page contract, which listed the prices for the different sizes of conduit.  The contract did not specify the depth that the conduit should be buried.  The parties subsequently agreed to a price adjustment. 

After Underground Boring finished its work, Santee Cooper complained to P Mining that the conduit had not been buried deeply enough in some places.  On July 29, 2005, Charles Permenter with P Mining wrote Donnie Stewart of Underground Boring to inform him P Mining would not pay any funds towards the outstanding balance until Stewart met with the City and Santee Cooper and they signed off on all of the bores completed.  Stewart testified the meeting was never scheduled.  P Mining requested Underground Boring correct the installation of conduit that had not been buried deeply enough in the median of Ocean Boulevard.  Stewart stated he was willing to make the repair if P Mining paid the remaining funds owed Underground Boring.  The payment was never forthcoming.  Other than the Ocean Boulevard location, Stewart never received any written requests identifying particular areas P Mining, the City, or Santee Cooper wanted Underground Boring to make corrections. 

A dispute also arose between the City and P Mining concerning the amount of conduit buried.  Because the City had concerns about the depth of the conduit, as well as the quantity P Mining had billed, it withheld payment from P Mining.  P Mining, in turn, withheld payment from Underground Boring. 

Underground Boring brought this action seeking payment of the balance due of $116,656.35 in addition to interest, attorney's fees, and costs.[2]  In its answer, P Mining asserted Underground Boring had breached the contract. 

After a bench trial, the court found Underground Boring was never made aware of any specifications and specifically was not told a depth for the borings.  The court noted the contract between P Mining and Underground Boring did not require a specific bury depth, nor did the contract incorporate by reference the terms of the City's contract and specifications.  Thus it held P Mining was not entitled to a setoff for the amounts it claimed it incurred to bury the conduit deeper.  The trial court also rejected P Mining's contention Underground Boring had submitted bills for more than the actual linear footages bored.  The court further found P Mining was entitled to a set-off for repairs it made to sewer lines Underground Boring hit on three separate occasions.  Thus, it held Underground Boring was owed an unpaid balance of $116,656.35, less the amount owed for the repairs by P Mining, leaving an amount of $99,041.35.  It denied Underground Boring's request for attorney's fees and prejudgment interest. 

Both parties filed motions to alter or amend.  The court denied P Mining's motion.  It also denied Underground Boring's motion to the extent it requested attorney's fees and interest pursuant to section 27-1-15 of the South Carolina Code (2007), but granted prejudgment interest in the amount of $29,369.48 pursuant to section 34-31-20(A) of the South Carolina Code (Supp. 2010).  It denied the remainder of the motion requesting the court exclude the set-offs for the repairs.  This appeal followed. 

STANDARD OF REVIEW

"An action for breach of contract is an action at law."  Electro Lab of Aiken, Inc. v. Sharp Constr. Co. of Sumter, Inc., 357 S.C. 363, 367, 593 S.E.2d 170, 172 (Ct. App. 2004).  In a law action tried without a jury, this court's review is limited to correcting errors of law, and we are required to uphold the trial court's findings of fact unless there is no evidence to support them.  Townes Assocs., Ltd. v. City of Greenville, 266 S.C. 81, 85-86, 221 S.E.2d 773, 775 (1976).

LAW/ANALYSIS

A.  Required Burial Depth

P Mining argues the trial court erred in finding Underground Boring was not required to install the conduit at a minimum burial depth of three feet.  It first contends the court erred in finding Underground Boring was never made aware of the requirement set forth in the plans and specifications for the project that the conduit be installed at a minimum depth of three feet. 

The City's detailed specifications for the project provided "Conduit depth must have at least 3' of cover over the conduits to meet code.  Conduits in areas where proposed and existing water, sewer, and drainage exist must be installed at a depth approved by a City of North Myrtle Beach inspector on site."  Stewart stated that while he was given the plans, he was never provided with the specifications.  The trial court held, "Based on the testimony presented and the Court's viewing of the credibility of the witnesses, the Court specifically finds that [Underground Boring] was never made aware of any specifications and specifically was not told a depth for the borings."  "Credibility determinations regarding testimony are a matter for the finder of fact, who has the opportunity to observe the witnesses, and those determinations are entitled to great deference on appeal."  Okatie River, L.L.C. v. Southeastern Site Prep, L.L.C., 353 S.C. 327, 338, 577 S.E.2d 468, 474 (Ct. App. 2003).  We hold the trial court's finding is supported by the evidence. 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

South Carolina Department of Natural Resources v. Town of McClellanville
550 S.E.2d 299 (Supreme Court of South Carolina, 2001)
Okatie River, L.L.C. v. Southeastern Site Prep, L.L.C.
577 S.E.2d 468 (Court of Appeals of South Carolina, 2003)
Klutts Resort Realty, Inc. v. Down'Round Development Corp.
232 S.E.2d 20 (Supreme Court of South Carolina, 1977)
Penton v. J.F. Cleckley & Co.
486 S.E.2d 742 (Supreme Court of South Carolina, 1997)
Townes Associates, Ltd. v. City of Greenville
221 S.E.2d 773 (Supreme Court of South Carolina, 1976)
Gamble v. International Paper Realty Corp.
474 S.E.2d 438 (Supreme Court of South Carolina, 1996)
Electro-Lab of Aiken, Inc. v. Sharp Construction Co. of Sumter, Inc.
593 S.E.2d 170 (Court of Appeals of South Carolina, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Underground Boring v. P Mining, Counsel Stack Legal Research, https://law.counselstack.com/opinion/underground-boring-v-p-mining-scctapp-2011.