This text of 618 F.2d 588 (Umpqua River Navigation Co. v. Crescent City Harbor District) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Umpqua River Navigation Co. v. Crescent City Harbor District, 618 F.2d 588 (9th Cir. 1980).

Opinion

GOODWIN, Circuit Judge:

Umpqua River Navigation Company (Umpqua), a general contractor, appeals a judgment denying recovery of cost overruns incurred by its subcontractor, Western Pacific Dredging Corporation (Western), while dredging a boat basin for Crescent City harbor district. Umpqua alleged, under various contract and tort theories, that specifications provided by the harbor district and prepared by Swine Engineering, Inc. inaccurately represented soil conditions in the dredging area, that Umpqua and Western relied on these specifications in submitting contract bids, and that, during the dredging, Western encountered conditions materially differing from those shown in the specifications, resulting in unforeseen costs. The harbor district filed a third-party complaint against Swine, alleging that if the specifications were negligently prepared, Swine must indemnify the harbor district. The district court found that Umpqua could not recover under any theory and entered judgment for the harbor district and Swine against Umpqua, and for Swine on the harbor district’s indemnity action. We affirm.

[591]*591The series of events underlying this litigation began in the early 1970’s, when the harbor district decided to investigate the possibility of expanding its boat facilities. In June 1971, as part of its preliminary research, the harbor district commissioned an independent firm, AAA Drilling, to drill eight test holes on the beach near the site of the proposed new boat basin to find bedrock levels. AAA subsequently prepared drawings, showing the location of its borings, the depth of bedrock, and the materials found between the surface and bedrock. AAA made no underwater borings in the proposed dredging channel.

Shortly after these drillings, still in June 1971, the harbor district informed Swine that it had been chosen to design the new boat basin. The harbor district turned the AAA results over to Swine, and, after prolonged negotiations, the harbor district and Swine signed a formal agreement in May 1972.

In August 1972, Swine arranged for Harding, Miller, a soils engineering firm, to make two more test borings. These holes were drilled in the area where the breakwater surrounding the boat basin was to be constructed, not in the dredging channel.

The results of the AAA and Harding, Miller borings were included in sheet 002 of the boat basin plans. Sheet 002 showed the presence of sandy clay, sand, clay, and gravel at the test hold sites. The term “gravel” was not defined in the plans, and nothing in the contract materials furnished to bidders interpreted or elaborated on this soil information.

In March 1973, the harbor district invited sealed bids on the boat basin construction. The bidding materials included plans, specifications, and special and general conditions. Particularly relevant to this case are special conditions 3 (“Examination of Site”) and 4 (“Soil Information and Pile Tests”), and general condition 21 (“Subsurface Conditions Found Different”).1 Contractors were given thirty days to submit their bids.

Before bidding, Umpqua examined the results of the AAA borings reported on sheet 002 and concluded that they were unreliable except as showing the depth of bedrock. Umpqua’s project engineer found the test results defective because the soil logs were inconsistent and because the logs did not include a legend defining various soil terms. Umpqua did, in compliance with special condition 4, request the reports underlying the Harding, Miller soil logs. Those borings, however, were taken at the location of the proposed breakwater, and not in the dredging channel.

[592]*592Western Pacific also conducted a pre-bid investigation. Robert Kaltsukis, a Western Pacific dredge captain, visited the project site. Kaltsukis, who had encountered rocks while dredging a nearby portion of Crescent City harbor in the mid 1960’s saw submerged rocks in an area adjacent to the dredging site. As part of his on-site inspection, Kaltsukis used a backhoe to dig test holes near two of the AAA boring locations. The results of these tests, which did not get down to project level, were inconsistent with the information shown on sheet 002, yielding sand and pea gravel, rather than only gravel, as indicated in the AAA results. Despite these discrepancies, Western Pacific did not comply with special condition 4 and attempt to obtain the source data for sheet 002.

Umpqua was awarded the boat basin construction contract in May 1973, and shortly thereafter selected Western Pacific as its dredging subcontractor. Western’s subcontract bid, which Umpqua accepted, was based on an estimated dredging output of 10,000 cubic yards per day, using hydraulic dredging methods.

Western began dredging on May 29,1973. Almost immediately, the dredge “Polhemus” encountered cobbles, boulders, and cemented sand. The dredge sustained damage requiring extensive repairs. These difficulties arose during the dredging of the boat basin’s access channel and turning area, areas in which no soil borings were taken. On July 26, Western notified Umpqua that it had encountered conditions materially different from those indicated in the plans and that it was withdrawing the “Polhemus” from the project. Umpqua forwarded this notice to Swine which, in turn, informed the harbor district.

Western brought in a second, larger dredge, the “Herb Anderson”, which encountered difficulties similar to those encountered by “Polhemus.” The parties offer conflicting explanations of these problems. Umpqua contends that the damage to the dredges was unprecedented, resulting from extreme and unforeseeable concentrations of cobbles and boulders. The harbor district and Swine assert that Western’s dredging troubles were due to inefficient crews and improper maintenance of the dredges.

Whatever the source of its dredging problems, Western Pacific, on August 25, again notified Swine that it had encountered conditions different from those shown in the plans. Swine and the harbor, district did not formally investigate Western’s claims until November 28. On that day, with representatives of Western, Umpqua, Swine, and the harbor district present, Umpqua’s floating crane, “Mink”, dug test holes at three locations designated by Western. On the basis of these borings, which yielded a large quantity of sand and silt, some cobbles, and one boulder, Umpqua and Swine engineers decided the basin was dredgable and directed Western Pacific to continue.

Western Pacific completed dredging on December 21. Over six months of intermittent dredging, Western rarely met its projected output of 10,000 cubic yards per day. The material dredged during the entire project was 80 percent sand, 15 percent gravel less than three inches in diameter, and 5 percent material exceeding three inches in diameter. Neither Umpqua nor Western Pacific obtained a change order, as required by general condition 21, or submitted a bill for extra costs at any time before June 6,1974, when Umpqua reported that the boat basin project was completed.

On June 11, 1974, Western informed Umpqua that it had incurred additional dredging expenses of $523,402. This claim was ultimately forwarded to the harbor district, which formally denied the claim on July 30, 1974. The harbor district then paid Umpqua 75 cents per cubic yard dredged, and Umpqua paid Western 65 cents per cubic yard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
618 F.2d 588, Counsel Stack Legal Research, https://law.counselstack.com/opinion/umpqua-river-navigation-co-v-crescent-city-harbor-district-ca9-1980.