Ultrafog, Ltd. v. ORR Protection Sys., Inc.

CourtCourt of Appeals for the Sixth Circuit
DecidedAugust 11, 2022
Docket21-5909
StatusUnpublished

This text of Ultrafog, Ltd. v. ORR Protection Sys., Inc. (Ultrafog, Ltd. v. ORR Protection Sys., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ultrafog, Ltd. v. ORR Protection Sys., Inc., (6th Cir. 2022).

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 22a0330n.06

No. 21-5909

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT FILED Aug 11, 2022 DEBORAH S. HUNT, Clerk ) ULTRAFOG, LTD., ) Plaintiff - Appellant, ON APPEAL FROM THE ) UNITED STATES DISTRICT ) v. COURT FOR THE WESTERN ) DISTRICT OF KENTUCKY ) ORR PROTECTION SYSTEMS, INC., ) OPINION Defendant - Appellee. ) ) )

Before: CLAY, GRIFFIN, and WHITE, Circuit Judges.

WHITE, J., announced the judgment and delivered the opinion of the court in which CLAY and GRIFFIN, JJ., joined in different parts. CLAY, J. (pp. 17–23), delivered a separate opinion concurring in Section II.D. and dissenting from the remainder of the lead opinion. GRIFFIN, J. (pp. 24–27), delivered a separate opinion concurring in the lead opinion except as to the introductory paragraph, Section II.D., and Section III.

HELENE N. WHITE, Circuit Judge. In this breach-of-contract action, Plaintiff-Appellant

Ultrafog, Ltd. (“Ultrafog”) appeals the grant of judgment on the pleadings to Defendant-Appellee

Orr Protection Systems, Inc. (“ORR”), arguing that it adequately stated a claim for breach of

contract and that the existence of material issues of fact rendered the district court’s judgment

premature. We AFFIRM in part, REVERSE in part, and REMAND for further proceedings.

I.

This dispute concerns a project to rehabilitate the Hugh L. Carey Tunnel (formerly known

as the Brooklyn-Battery Tunnel) in New York City. Navillus was hired by the New York

Triborough Bridge and Tunnel Authority as the primary contractor for the project, which included No. 21-5909, Ultrafog, Ltd. v. Orr Prot. Sys., Inc.

updating the tunnel’s fire suppression system. Around July 2018, Navillus invited ORR to submit

a proposal to provide design-build services related to the tunnel’s ventilation and fire suppression

systems. The next month, Navillus and ORR engaged in preliminary discussions to the effect that,

if Navillus retained ORR as a subcontractor, ORR would retain Ultrafog as a sub-subcontractor.

On March 22, 2019, Ultrafog submitted a formal proposal to ORR. On April 9, 2019, Navillus

issued a letter of intent to retain ORR as a subcontractor for the project. On April 11, 2019, before

ORR and Navillus formalized their relationship, ORR submitted a purchase order to Ultrafog. In

that purchase order, Ultrafog agreed to provide design drawings, calculations, and tunnel test

engineering support for the project. In June 2019, Navillus and ORR executed a subcontract

agreement (the “Prime Contract”). On July 2, 2019, ORR submitted a second purchase order to

Ultrafog for the “remaining balance” of the fire-suppression system for the project. R.1, PID 4 (¶

16).1

Each purchase order stated that it was subject to ORR’s Terms and Conditions. The Terms

and Conditions apply to “all Work (as defined below) purchased by [ORR] and performed by any

recipient of an ORR Purchase Order (“Subcontractor”).” R.1-7, PID 303 (¶ 1). The Terms and

Conditions define “Work” as follows:

2. Work. Subcontractor shall perform the services as detailed in the Purchase Order and as provided herein, including any fire detection/suppression or related activity (collectively the “Work”), in a good, timely and workmanlike manner. It shall be the responsibility of Subcontractor to examine, review and understand the Purchase Order relating to the Work (including the services and materials to be provided by Subcontractor), and it shall further be the responsibility of Subcontractor to familiarize itself with all conditions which may affect the Work. In performing the Work and as applicable to the Work, Subcontractor agrees to assume and be bound to ORR by the same duties, obligations and responsibilities as ORR is to the general contractor and owner (collectively “Owner”) under the agreement between ORR and the Owner (the “Prime Contract”) of the applicable site where the Work will be performed (the “Work Site”). In the event of a conflict between this Subcontract and the Prime Contract, the provisions imposing the greater duty, obligation and

1 There was a total of four purchase orders between ORR and Ultrafog.

-2- No. 21-5909, Ultrafog, Ltd. v. Orr Prot. Sys., Inc.

responsibility on Subcontractor shall govern in all respects. Accordingly, Subcontractor agrees to be bound to ORR to perform the Work under the terms and conditions of the Prime Contract.

Id., PID 303–04 (¶ 2).

The Terms and Conditions also contain the following provisions regarding default and

early termination, the meaning and applicability of which the parties dispute on appeal:

16. Default of Subcontractor. Should Subcontractor at any time (a) breach this Agreement, a Purchase Order or its obligations pursuant to the Prime Contract; (b) cause stoppage or delay of or interference with the Project, or any portion thereof; or (c) become insolvent, then, in any such event, each of which shall constitute a default hereunder by Subcontractor, ORR shall, after giving Subcontractor written notice of default and forty- eight (48) hours within which to cure such default, have the right to exercise any one or more of the following remedies: a. Require that Subcontractor utilize, at its own expense, overtime labor (including Saturday and Sunday work), in additional shifts as necessary to overcome the consequences of any delay attributable to Subcontractor’s default; and/or b. Attempt to remedy the default by whatever means ORR may deem necessary or appropriate, including, without limitation, correcting, furnishing, performing or otherwise completing the Work, or any portion thereof, by itself or through others (utilizing where appropriate any materials and equipment previously purchased for that purpose by Subcontractor) and deducting the cost thereof (plus an allowance for administrative costs equal to twenty percent (20%) of such costs) from any monies due or that become due to Subcontractor hereunder.

17. Early Termination. Either party may immediately terminate this Agreement if the other party fails to cure any material breach of this Agreement within thirty (30) days after receipt of written notice of such breach from the other party. B. If Owner terminates the Prime Contract, or stops the Work for a reason other than the sole default of ORR, ORR may immediately terminate this Agreement or stop the Work for the same reason, and Subcontractor’s rights and remedies, including payment of any unpaid and earned portion of the Price, shall be limited to the corresponding rights and remedies available to ORR under the Prime Contract.

Id., PID 307–08 (¶¶ 16–17).

Ultrafog ordered equipment and performed services to satisfy the requirements of the

purchase orders. During this time, employees from Navillus, ORR, and Ultrafog participated in

weekly meetings via telephone. ORR did not object to Ultrafog’s work and made a partial payment

of $459,600 for the services Ultrafog performed toward the purchase orders.

-3- No. 21-5909, Ultrafog, Ltd. v. Orr Prot. Sys., Inc.

On February 20, 2020, Navillus sent a letter to ORR “request[ing] ORR to terminate

Ultrafog from the Project with immediate effect.” R.1-10, PID 346. In its letter, Navillus asserted

that Ultrafog had “caused the design process on the Project to become inefficient & inadequate”

for a number of reasons, including inadequate staffing, failure to follow schedules, and fire testing

and certification issues. Id., PID 345–46. It further stated that “should Navillus incur any

additional cost as a result of this termination and/or Ultrafog’s failure to perform on the Project as

required,” ORR would be responsible to Navillus for such costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Kevin W. Ziegler v. Ibp Hog Market, Inc.
249 F.3d 509 (Sixth Circuit, 2001)
Kathryn Keys v. Humana, Inc.
684 F.3d 605 (Sixth Circuit, 2012)
Fritz v. Charter Township of Com-Stock
592 F.3d 718 (Sixth Circuit, 2010)
JPMorgan Chase Bank, N.A. v. Winget
510 F.3d 577 (Sixth Circuit, 2007)
Barany-Snyder v. Weiner
539 F.3d 327 (Sixth Circuit, 2008)
Abney v. Nationwide Mutual Insurance Co.
215 S.W.3d 699 (Kentucky Supreme Court, 2007)
City of Louisa v. Newland
705 S.W.2d 916 (Kentucky Supreme Court, 1986)
Cantrell Supply, Inc. v. Liberty Mutual Insurance Co.
94 S.W.3d 381 (Court of Appeals of Kentucky, 2002)
Hazard Coal Corp. v. Knight
325 S.W.3d 290 (Kentucky Supreme Court, 2010)
First Commonwealth Bank of Prestonsburg v. West
55 S.W.3d 829 (Court of Appeals of Kentucky, 2000)
Plaza Condominium Ass'n v. Wellington Corp.
920 S.W.2d 51 (Kentucky Supreme Court, 1996)
OP Link Handle Company v. Wright
429 S.W.2d 842 (Court of Appeals of Kentucky (pre-1976), 1968)
The Kentucky Shakespeare Festival, Inc. v. Brantley Dunaway
490 S.W.3d 691 (Kentucky Supreme Court, 2016)
Henderson v. Continental Casualty Company
39 S.W.2d 209 (Court of Appeals of Kentucky (pre-1976), 1931)

Cite This Page — Counsel Stack

Bluebook (online)
Ultrafog, Ltd. v. ORR Protection Sys., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ultrafog-ltd-v-orr-protection-sys-inc-ca6-2022.