Ulloa v. SASCO CA2/3

CourtCalifornia Court of Appeal
DecidedAugust 29, 2025
DocketB331169
StatusUnpublished

This text of Ulloa v. SASCO CA2/3 (Ulloa v. SASCO CA2/3) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ulloa v. SASCO CA2/3, (Cal. Ct. App. 2025).

Opinion

Filed 8/29/25 Ulloa v. SASCO CA2/3

NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS

California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION THREE

ANTONIO ULLOA, B331169

Plaintiff and Appellant, (Los Angeles County Super. Ct. No. 20STCV14710) v.

SASCO,

Defendant and Respondent.

APPEAL from a judgment of the Superior Court of Los Angeles County, Robert B. Broadbelt, Judge. Affirmed. Employee Justice Legal Group, Kaveh S. Elihu, and Matias N. Castro for Plaintiff and Appellant. Jackson Lewis and Dylan B. Carp for Defendant and Respondent.

‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗ Plaintiff Antonio Ulloa appeals from a judgment entered after the trial court granted summary adjudication for his former employer, defendant SASCO, on a variety of discrimination, retaliation, and wage-and-hour claims. On appeal, Ulloa does not challenge the trial court’s order with regard to Ulloa’s wage-and- hour claims (eleventh through fifteenth causes of action), but he contends there were triable issues of material fact with regard to causes of action alleging age and disability discrimination, retaliation, failure to accommodate, failure to engage in the interactive process, and wrongful termination (first through tenth causes of action). We conclude that Ulloa has not demonstrated triable issues as to any cause of action, and thus we affirm the judgment. FACTUAL AND PROCEDURAL BACKGROUND I. Background. A. SASCO. SASCO is an electrical contractor based in Fullerton, California. SASCO’s construction-related work is divided into office and field work. On the office side, SASCO is organized by groups, each of which is headed by a project manager and project engineer who determine staffing needs. On the field side, each job is managed by a foreman, who reports to a general foreman. The general foreman reports to a superintendent, who reports to the director of field operations. As relevant to the present litigation, Mark Smith was the project manager, April Benson was the project engineer, Jack Ivy was the superintendent, and Smokey Stanton was the director of field operations. SASCO hired electricians through the local electrician’s union, the International Brotherhood of Electrical Workers,

2 Local 11 (electrician’s union). The electrician’s union maintained a “book”—i.e., a list of union members seeking work—and sent union members out to jobs based on the length of time they had been out of work. If SASCO had more electricians than it needed, it would terminate them and send them back to the union to sign up for new work. B. Ulloa’s employment by SASCO. Plaintiff Ulloa is a journeyman transportation system electrician (journeyman electrician) and a member of the electrician’s union. SASCO hired Ulloa through his union in August 2013, when Ulloa was 51 years old. The terms of Ulloa’s employment were controlled by the Electrician Union’s Collective Bargaining Agreement in effect from July 1, 2014 to June 30, 2019 (CBA). As a journeyman electrician, Ulloa was qualified to work on outside wiring jobs only. In 2013, Ulloa worked on replacing city streetlights. That job involved digging about five feet down, pouring cement, setting up anchor bolts, assembling the light poles, and then connecting the light poles to the electric grid. In 2016 and 2017, Ulloa worked primarily on two projects: the Ameron project and the Mobilitie project. The Ameron project involved installing and replacing streetlights, and it was managed by acting foreman Frank Niels and general foreman Angel Marquez. The Mobilitie project involved installing small cell towers (antennas) on streetlights, and it was managed by foreman Andres (Andy) Contreras and general foreman Angel Marquez. Both projects were renewed on a yearly basis, and were some of the few jobs SASCO did that involved outside wiring.

3 C. Ulloa’s heart attack, return to work, and termination. Ulloa had a heart attack in October 2018. He had surgery to implant a heart stent and was out of work on a medical leave of absence for about two months, returning to work on December 9, 2018. Prior to Ulloa’s return to work, project engineer April Benson told Ulloa that SASCO was “slow right now, so you won’t have full weeks until after the new year.” Benson inquired: “Do you want to stay on disability until after the new year? So you get full pay? [¶] It [d]oesn’t matter to us. It’s up to you.” Ulloa responded that he had already submitted his disability paperwork and preferred to return to work December 9. Benson said: “OK.[] Next week, we have an equipment install Monday, Tuesday, and Wednesday. Right now Thursday and Friday no work.” Effective December 9, 2018, Ulloa’s doctor released Ulloa back to work without limitations. Ulloa testified that he did not request any accommodations when he returned to work because he was able to perform all the work his job required and he “knew the company doesn’t do any light duty work.” Project manager Mark Smith similarly testified that SASCO did not offer light duty work to field employees. Smith explained: “[U]nless the field employee is a-hundred percent capable of performing their job, we don’t really have any work for them. . . . [I]t’s – it’s a safety concern, you know, that the guys need to be able to do their task. We don’t want to have anybody get hurt or hurt anyone else . . . by not being a-hundred percent capable.” Ulloa was placed back on the Mobilitie project upon his return to work, working on a two-person crew with electrician

4 apprentice Edgar Alvarez. One other crew was assigned to the Mobilitie project, staffed by an unidentified journeyman electrician and electrician apprentice Alberto Paz. In late February 2019, Smith decided to lay off one of the two crews assigned to the Mobilitie project because the project was nearly finished. It was left to superintendent Jack Ivy and general foreman Angel Marquez to determine which crew would be laid off. Marquez chose Ulloa and Alvarez for termination, in consultation with their direct supervisor, foreman Andres Contreras. Ivy testified that Ulloa and Alvarez were terminated because there were just a few Mobilitie sites left to finish and “the crew that [Ulloa] and [Alvarez] were on, their crew, the poles that they were doing in their area were finished and there was no more work for them. The other crew was going to finish the other sites and the [Mobilitie] project was then ended.” Contreras similarly testified that he recommended Ulloa and Alvarez for termination because the Mobilitie project was ending and because Ulloa had been insubordinate by seeking work from other divisions of the company without Contreras’s permission. Ulloa and Alvarez were notified of their termination on February 28, 2019, approximately two and a half months after Ulloa’s return from medical leave. At the time of their termination, Ulloa was 56 years old and Alvarez was 35 years old. Ulloa’s termination notice said Ulloa was terminated due to a reduction in force and was “[e]ligible for rehire.” After Ulloa was terminated, the other Mobilitie crew spent a few weeks completing the remaining installations. Those crew members then were transferred to other projects. Ulloa’s last day of work was February 28, 2019. He left his union in about October 2019.

5 II. The present action. In April 2020, Ulloa filed a sixteen-count complaint against SASCO, alleging: (1) discrimination based on age and disability in violation of the Fair Employment and Housing Act (FEHA; Gov.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. City of Santa Monica
294 P.3d 49 (California Supreme Court, 2013)
Coleman v. Gulf Insurance Group
718 P.2d 77 (California Supreme Court, 1986)
D'AMICO v. Board of Medical Examiners
520 P.2d 10 (California Supreme Court, 1974)
Scotch v. Art Institute of California-Orange County, Inc.
173 Cal. App. 4th 986 (California Court of Appeal, 2009)
Nadaf-Rahrov v. the Neiman Marcus Group, Inc.
166 Cal. App. 4th 952 (California Court of Appeal, 2008)
DeJung v. Superior Court
169 Cal. App. 4th 533 (California Court of Appeal, 2008)
Trop v. Sony Pictures Entertainment, Inc.
29 Cal. Rptr. 3d 144 (California Court of Appeal, 2005)
Martin v. Lockheed Missiles & Space Co.
29 Cal. App. 4th 1718 (California Court of Appeal, 1994)
King v. United Parcel Service, Inc.
60 Cal. Rptr. 3d 359 (California Court of Appeal, 2007)
Beale v. GTE CALIFORNIA
999 F. Supp. 1312 (C.D. California, 1996)
Horn v. Cushman & Wakefield Western, Inc.
85 Cal. Rptr. 2d 459 (California Court of Appeal, 1999)
Aguilar v. Atlantic Richfield Co.
24 P.3d 493 (California Supreme Court, 2001)
Guz v. Bechtel National, Inc.
8 P.3d 1089 (California Supreme Court, 2000)
Saelzler v. Advanced Group 400
23 P.3d 1143 (California Supreme Court, 2001)
Reid v. Google, Inc.
235 P.3d 988 (California Supreme Court, 2010)
Jumaane v. City of Los Angeles
241 Cal. App. 4th 1390 (California Court of Appeal, 2015)
Jameson v. Desta
420 P.3d 746 (California Supreme Court, 2018)
Jordache Enterprises Inc. v. Brobeck
18 Cal. 4th 739 (California Supreme Court, 1998)
Rogers v. County of Los Angeles
198 Cal. App. 4th 480 (California Court of Appeal, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Ulloa v. SASCO CA2/3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ulloa-v-sasco-ca23-calctapp-2025.