Uhlhorn v. Owens

211 F. Supp. 798, 11 A.F.T.R.2d (RIA) 369, 1962 U.S. Dist. LEXIS 5223
CourtDistrict Court, S.D. Texas
DecidedNovember 19, 1962
DocketCiv. A. 1466
StatusPublished
Cited by7 cases

This text of 211 F. Supp. 798 (Uhlhorn v. Owens) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Uhlhorn v. Owens, 211 F. Supp. 798, 11 A.F.T.R.2d (RIA) 369, 1962 U.S. Dist. LEXIS 5223 (S.D. Tex. 1962).

Opinion

GARZA, District Judge.

This case was originally filed in State District Court by W. B. Uhlhom d/b/a W. B. Uhlhom Construction Co., as a bill' of interpleader against Paul Owens and Jack Dooley, individually and d/b/a Valley Lathing & Plastering Company, Security State Bank of Pharr, Central Valley Ready-Mix Company, G & G Lumber Company, Damacio Reyna, Rolando Munoz, L. E. Travis & Sons, Inc., and the United States of America as Defendants. The United States of America removed the case to this Court.

After removal, the Government, not satisfied with the mere position of a defendant in the interpleader action, filed an intervention pursuant to Sections 7401 and 7403 of the Internal Revenue Code of 1954.

Uhlhorn Construction Co. had .the primary contract to build the Falcon Housing Project at Falcon Heights, Texas,, with the International Boundary & Water Commission. The work to be performed under said contract was for a housing project to be used in conjunction with Falcon Dam.

Uhlhorn then entered into a written subcontract with the Defendant Paul Owens, d/b/a Paul Owens Lathing Company, on or about April 27, 1960, and the obligation of the subcontract was thereafter assumed by and transferred to the Defendants Owens and Dooley, d/b/a Valley Lathing & Plastering Company, who proceeded to perform it. On-May 14, 1960, the subcontractor assigned all the proceeds due the said subcontractor under and by reason of said contract, to the Defendant Security State Bank of Pharr, Texas, and authorized Uhl-horn to make checks payable jointly to said subcontractor and said bank. The bank, under said assignment, made advances to the subcontractor, and the-amount still owed on said advances, by the subcontractor to the bank, is in excess of the amount still due them under this contract.

The prime contractor and interpleader, Uhlhorn, towards the close of not only *800 the subcontract but the prime contract, even though they had an affidavit signed by Jack Dooley in behalf of Valley Lathing & Plastering Company that all bills had been paid, became aware of several claims, and they have tendered into court the sum of $4,893.45 as the balance retained under the subcontract, and has asked the Court to determine the rightful claimants to said amount.

G & G Lumber Company and L. E. Travis & 'Sons, Inc., have disclaimed. Reyna and Munoz have never appeared to press their claims. The State of Texas has intervened, claiming a lien for delinquent unemployment taxes against the subcontractors in the sum of $1,028.34.

Prior to the issuing of the affidavit mentioned above by Dooley, according to their last estimate submitted to Uhlhorn, Uhlhorn owed them on the contract the sum of $4,977.00, and on the oral representation of the subcontractor that all bills were paid, Uhlhorn had prepared a check, dated May 10, 1961, in said amount. They held the check, however, until May 18th, when the Defendant Dooley came and made the verbal assertion that the subcontract had been fully completed, that all bills for labor and materials had been paid and satisfied, and that he was, therefore, entitled to said check for $4,977.00. The check in that amount, made payable jointly to the subcontractor and to the bank, was then delivered.

Shortly after delivering said check, Uhlhorn was advised by the International Boundary & Water Commission that there was in fact an outstanding unpaid bill for materials due by the subcontractor to G & G Lumber Company, and Uhlhorn proceeded to stop payment on the check for $4,977.00.

The bank, in turn, in this case has filed a cross-action against Uhlhorn, claiming that by relying on the issuance of the check for $4,977.00, it released all the notes that the subcontractor had with them, with the exception of one. They allege in their cross-action that they were misled by Uhlhorn, through its agents, that the check for $4,977.00 was good, and that Uhlhorn is now precluded and estopped to stop payment on said check or refuse to pay said check.

The Court, after a hearing, has ruled adversely on the cross-action of the bank against Uhlhorn, finding that Uhlhorn was within his rights in stopping payment on the check and could not be es-topped or precluded from stopping payment on the same.

Uhlhorn, after stopping payment on said check of $4,977.00, on the advice of the subcontractor and with its consent, paid G & G Lumber Company the sum of $439.30, resulting in the amount which he has tendered into Court.

The mechanics’ liens of Valley Ready-Mix Company, Damacio Reyna and Rolando Munoz, even if treated as mechanics’ liens, have not been perfected and reduced to judgment, and therefore are inchoate and not superior to the claim of the Government; and since the amount involved is less than that claimed by the Government, they are out of the case as far as the funds in court are concerned. The same holds true for the claim of the State of Texas; and as far as the money in court is concerned, the State of Texas does not have any right to the same.

That leaves for disposal the controversy between Security State Bank of Pharr, Texas, and the Government, as to the priority of their liens.

Security State Bank has taken the position that its assignment from the subcontractor was a protected assignment and was a choate interest; that its assignment was prior in time to the filing of the Government’s tax liens which are for a greater amount than the amount tendered into court. The amount due by the subcontractor to the Security State Bank is also in excess of the amount tendered. So a ruling on the priority of the liens as between the Bank and the Government will resolve the question of who is entitled to the money now in. court.

There is no question that in order for the assignment held by the bank *801 to be a valid assignment, it had to be taken under Article 260-1, Vernon’s Texas Civil Statutes. This was the same statute involved in the case of United States v. R. F. Ball Construction Co., Inc. et al., which is to be found in R. F. Ball Const. Co. v. Jacobs, D.C., 140 F.Supp. 60; 5 Cir., 239 F.2d 384, and 355 U.S. 587, 78 S.Ct. 442, 2 L.Ed.2d 510, as it existed before the 1957 amendment to the same.

The pertinent part of said statute is Section 1(1) which reads as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
211 F. Supp. 798, 11 A.F.T.R.2d (RIA) 369, 1962 U.S. Dist. LEXIS 5223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uhlhorn-v-owens-txsd-1962.