UGI Utilities, Inc.—Gas Division v. Public Utility Commission

878 A.2d 186, 2005 Pa. Commw. LEXIS 341
CourtCommonwealth Court of Pennsylvania
DecidedJuly 7, 2005
StatusPublished
Cited by6 cases

This text of 878 A.2d 186 (UGI Utilities, Inc.—Gas Division v. Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
UGI Utilities, Inc.—Gas Division v. Public Utility Commission, 878 A.2d 186, 2005 Pa. Commw. LEXIS 341 (Pa. Ct. App. 2005).

Opinion

OPINION BY

Judge PELLEGRINI.

UGI Utilities, Inc. — Gas Division (UGI) appeals from an order of the Pennsylvania Public Utility Commission (PUC) adopting that portion of the recommended decision of the Administrative Law Judge (ALJ) modifying the financial security requirement it imposed on Shipley Energy Company (Shipley).

UGI is a natural gas distribution company (NGDC). 1 Shipley is a natural gas supplier (NGS) 2 which purchases natural gas from UGI and then sells the gas to its *188 customers which is delivered through UGI’s distribution lines. On July 2, 2003, Shipley filed with the PUC a petition for modification of financial security requirements imposed by UGI for security as an NGS serving on UGI’s system. UGI required Shipley to maintain a level of security equal to $10.2 million to operate on its system. Shipley requested an order reducing its required level of financial security on the UGI system; prohibiting UGI from using potential penalties as a basis for any security requirement; and requiring UGI to modify its supplier tariff to the extent necessary to make it consistent with the PUC’s regulations. UGI filed an answer denying that its tariff was inconsistent with the PUC’s regulations or inappropriate for Shipley’s circumstances.

The PUC assigned the matter to an ALJ and directed that three questions be addressed:

•Whether the financial security criteria in the UGI tariff were consistent with the PUC’s regulations and whether they were applied in a non-discriminatory manner;
•Whether the amount of Shipley’s security was reasonably related to the financial exposure which could be imposed on UGI by the default or bankruptcy of Shipley; and.
• Whether the financial security criteria in the UGI tariff adequately incorporated the PUC’s regulations at 52 Pa. Code § 62.111(c)(l)(i) regarding the criteria for modification and/or adjust.ment of the amount of security.

At the hearing, Paul Szykman (Szyk-man), Director of Rates and Gas Supply for UGI, explained that financial security was determined based on the Daily Delivery Requirement (DDR) to each supplier that represented the anticipated demand of the supplier’s aggregated pool of customers. “The security requirement for an enrolled larger Choice customer [referring to the Natural Gas Choice and Competition Act (Act), Act of June 22, 1999, P.L. 122, 66 Pa.C.S. §§ 2201-2212] is determined by applying the formula specified in Section 8.5 of UGI’s Choice Supplier Tariff (attached as Appendix PJS-2 to my direct testimony) 3 using the DDR at a design temperature of minus 1.2 degrees F for the Choice supplier’s peak Design Day Requirement.” (Reproduced Record at 76a.) He explained that it was necessary to use the rate proposed by UGI because UGI had to rely on the interstate pipeline facilities to which it was connected for incremental supplies. In the event of a default by Shipley or any NGS, UGI would have to purchase supplies from third parties who maintained pipeline capacity in the eastern part of Pennsylvania, and it would be likely that the default would occur during the coldest conditions on a 33-day cycle, with a forecasted gas price of $113.40/Dth, which UGI would have to pay to try to lure supplies away from other destinations to meet the unexpected load or find that supplies were not even available. Szykman further stated that there *189 were no price caps placed on what a supplier could charge UGI for replacement supplies in the event of an NGS’ default.

Szykman also explained that it was necessary that the financial security requirement include a provision for any consumers to impose a penalty that could be imposed on Shipley or UGI because when UGI relied upon NGS Choice suppliers to deliver gas to its system, it did not buy back-up supplies to meet system requirements in the event of a default. An inclusion of a penalty was also necessary to prevent an NGS Choice supplier from diverting and selling supplies needed to meet its supply obligations in UGI’s system to other market areas, i.e., to engage in arbitrage, 4 which would have an impact on other customers on UGI’s system and the reliability of the system. “These penalty amounts reflect the fact that prices in other markets can reach very high levels, and that a strong incentive must be in place to remove the financial temptation to divert supplies to other markets.” (Reproduced Record at 83a.) Szykman admitted on cross-examination, however, that he knew of no NGS Choice supplier or natural gas supplier that had engaged in arbitrage or any NGS Choice supplier on UGI’s system that had engaged in arbitrage with their gas supplier.

Matthew Sommer (Sommer), Business Manager for Shipley, testified that Shipley had been serving customers on the UGI system since March 2002, and was rated as having an extremely low risk of failure or default. However, UGI’s security requirement had a significant negative effect on Shipley’s ability to do business. “Without substantial relief from that unwarranted burden, there is a very strong likelihood that we will not be a continuing presence in the UGI market. If that happens, customers, who currently are able to enjoy savings over POLR service from UGI will be left with no alternative, and UGI will have succeeded in driving the last remaining NGS from its territory.” (Reproduced Record at 55a.)

James Christ (Christ), President of Lumen Group, Inc., a consulting firm that focused on regulatory and market issues, testified that he had calculated the security requirements of UGI as they applied to Shipley and found them to be significantly higher than they needed to be to comply with PUC regulations. Christ explained that UGI’s required level of security was $1,200 per customer based on the $120 * 10 days * Design Day Requirement in Section 8.5, even though he calculated the actual maximum exposure to be $62.37 for the entire 30-day month. He made this calculation using the peak month of January, assuming it would be 20% colder than normal, and that the default by NGS would occur on average in the middle of the billing period or a 15-day exposure. He also stated he examined historical gas prices for the duration of the Choice program, or February 2002 to the present, February 2003, and took an average. Christ also stated that actual facts proved that where an NGS Choice supplier, including Shipley, had not delivered the required amount of gas to the UGI system, it did not require UGI to purchase any gas on the spot market. Therefore, there was no truth that a shortfall of delivered supply demanded high security. Christ recommended that the security requirement be set at $31.18 per customer or one-half *190 of the reasonably calculated maximum exposure amount. Christ also opined that financial exposure should not include penalties because “the non-cost based penalties, which UGI intends to be a discouragement to NGS to not perform, are insulting and not in the spirit of Choice ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crosby Valve, LLC v. Department of Insurance
131 A.3d 1087 (Commonwealth Court of Pennsylvania, 2016)
Polites v. Pennsylvania Public Utility Commission
928 A.2d 388 (Commonwealth Court of Pennsylvania, 2007)
Mercury Trucking, Inc. v. Pennsylvania Public Utility Commission
923 A.2d 1244 (Commonwealth Court of Pennsylvania, 2007)
PPL Electric Utilities Corp. v. Pennsylvania Public Utility Commission
912 A.2d 386 (Commonwealth Court of Pennsylvania, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
878 A.2d 186, 2005 Pa. Commw. LEXIS 341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ugi-utilities-incgas-division-v-public-utility-commission-pacommwct-2005.