U. S. Propellers, Inc. v. Zenith Plastics Co.

187 Cal. App. 2d 780, 10 Cal. Rptr. 137
CourtCalifornia Court of Appeal
DecidedDecember 29, 1960
DocketCiv. No. 24500
StatusPublished
Cited by1 cases

This text of 187 Cal. App. 2d 780 (U. S. Propellers, Inc. v. Zenith Plastics Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U. S. Propellers, Inc. v. Zenith Plastics Co., 187 Cal. App. 2d 780, 10 Cal. Rptr. 137 (Cal. Ct. App. 1960).

Opinion

FOURT, J.

This appeal is from a judgment in an action for breach of contract.

A résumé of the facts is as follows:

Western Electric Company contracted with an agency of the United States Government to produce a radar set for the nation’s air defense system. Western Electric, in turn, let a two and one-quarter million dollar subcontract to Zenith Plasties Company (hereinafter referred to as “Zenith”) in the first half of 1957 to produce a component of that radar set. One of the essential features of this subcontract was the absolute necessity of meeting the delivery date of an acceptable first article by Zenith. Pursuant to this contract, Zenith determined which parts of this component could be manufactured by Zenith itself, and which parts by subcontractors of Zenith. One of the parts within the latter category was the metal honeycomb fabrication for a parabolic reflector antenna assembly.

In the latter part of May 1957, Zenith distributed requests for quotations on this component to various possible subcontractors. One of these subcontractors, U. S. Propellers, Inc. (hereinafter referred to as “U.S.P.”), submitted a quotation on June 10th to supply 140 such parabolic reflectors and one lot of tooling. U.S.P. was the only bidder.

Subsequently, on June 12th, a prearranged conference was held between personnel of U.S.P. and of Zenith at the latter’s plant. At this conference a general discussion of the technical and other requirements of the proposed contract took place. The technical requirements were reviewed in detail and the absolute necessity of U.S.P. ’s meeting a September 13th deadline for delivery of an acceptable first article was repeatedly stressed. U.S.P. represented that it could and would meet this schedule.

Zenith further required that U.S.P. furnish as rapidly [782]*782as possible a satisfactory tool plan, which, in general, consists of a detailed description of each tool to be used to fabricate the required article, the construction of each tool, its use, and the reference tool required. The plan of U.S.P. was to show the starting date, the flow (including the application of the reference tool to the basic tool and all subsequent tools which are tied back to this common reference), and the completion date for each tool, as well as the time schedule for the entire program. A tool plan includes, among other things, sketches clarifying the approach to be taken and illustrating the flow of the manufacturing operations, the application of reference tools, and basic construction details. The requisites of a tool plan were explained to U.S.P., and the Zenith tool plan for the Western Electric contract was shown to them as a model for U.S.P.’s tool plan.

The record discloses a number of reasons why a tool plan is essential once performance is begun, namely: to furnish Zenith with the information required to prepare specific tool work orders and purchase orders; to enable Zenith to establish its accountability to the government for all tools since all tooling which was produced belonged to the government; to enable Zenith to coordinate the performance of this particular subcontractor with that of the other subcontractors working on the same project; to inform Zenith when it would have to supply gages and other check tools to U.S.P., and to coordinate this with the requirements of other subcontractors ; and to give Zenith an accurate indication of U.S.P.’s ability to perform (i.e., whether the engineering capability to produce was present). Such tool plans are generally submitted as a matter of course very shortly after a “go-ahead” is given on a subcontract. Although U.S.P. promised to furnish such a plan, none was ever received by Zenith.

At the June 12th conference, Zenith also requested that U.S.P. furnish a financial statement to the end that Zenith could ascertain whether U.S.P. had the financial ability to expend large sums of money (i.e., at least $100,000) for production of this component prior to the receipt of any moneys from Zenith. This was never received by Zenith, although another request was made therefor after June 12th. At the conclusion of the conference, Zenith gave U.S.P. an oral go-ahead on the contract. This is a standard method of initiating such contracts in the particular industry. The record discloses that the go-ahead was given with the under[783]*783standing that Zenith’s written purchase order would be issued when, and only when, a satisfactory tool plan was furnished by U.S.P.1

Zenith did give U.S.P. the “purchase order numbers” which were to be assigned to the written purchase orders when they were issued.

Because of the necessity of meeting a firm delivery date of the subcontract, Zenith commenced close liaison with U.S.P. to insure on-schedule production. One of Zenith’s buyers and a tool engineer visited U.S.P. ’s plant approximately one week later and it was their opinion that U.S.P. was not making satisfactory progress on the job. U.S.P. admitted that it was so told.

U.S.P.’s facilities were inadequate and the personnel did not demonstrate the necessary skill to fulfill the contract. The subcontractors of U.S.P. also indicated lack of any progress.

On June 28th, the same Zenith employees again visited U.S.P.’s plant. As a result of this visit, it was their opinion that U.S.P. was not and would not be able to undertake the production of the items successfully. Among other things, U.S.P. appeared unable or unwilling to progress beyond the rough drawing and planning stage, or to submit the necessary tool plan or financial statement. Although U.S.P. admittedly was not equipped to perform all of the work itself, its management had not decided what phases of the work would be done by U.S.P. and what phases would be subcontracted, and had prepared no flow chart or other indication of how they intended to fabricate the items. U.S.P. had failed to let any subcontract although it admitted that the majority of the tools to make the component U.S.P. was to deliver to Zenith would have to be produced elsewhere.

To protect itself in the face of the situation with which it was confronted Zenith called for quotations from other concerns. On July 8, 1957, in response to Zenith’s second series of requests for quotations, North American Aviation Company submitted an acceptable quotation accompanied by a satisfactory tool plan.

On July 9, 1957, Zenith cancelled its contract with U.S.P. The following day, U.S.P. received five written purchase orders together with five change notices, the latter of which read: [784]*784‘1 Cancel entire order — Convenience of Zenith Plasties. Advise cancellation charges. Confirming wire July 9, 1957.”

U.S.P. filed its second amended complaint for breach of contract on January 17, 1958. The pretrial conference order filed February 20, 1959, states in pertinent part as follows:

“[T]he parties stipulate that the issues are as set forth under items 1, 2, 5 and 6 including the subdivisions of 2.2 With respect to the third issue,3 plaintiff will concede that there was such a custom but contends that there are excep: tions thereto. With respect to the fourth issue,4 plaintiff will stipulate that there is no issue of the right to terminate under the purchase order issued on or about July 9, 1957 if such purchase orders were applicable to the procurement in issue.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Santa Clara Properties Co. v. R. L. C., Inc.
217 Cal. App. 2d 840 (California Court of Appeal, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
187 Cal. App. 2d 780, 10 Cal. Rptr. 137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/u-s-propellers-inc-v-zenith-plastics-co-calctapp-1960.