Ty-Excavating, Inc. v. Boccia, Unpublished Decision (11-26-2004)

2004 Ohio 6338
CourtOhio Court of Appeals
DecidedNovember 26, 2004
DocketCase No. 2003-T-0099.
StatusUnpublished
Cited by1 cases

This text of 2004 Ohio 6338 (Ty-Excavating, Inc. v. Boccia, Unpublished Decision (11-26-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ty-Excavating, Inc. v. Boccia, Unpublished Decision (11-26-2004), 2004 Ohio 6338 (Ohio Ct. App. 2004).

Opinion

OPINION
{¶ 1} Appellant, Richard Boccia ("appellant") entered into a contract with the City of Niles to perform certain street, storm water, and sidewalk removal and replacement of the same on Holford Street in Niles, Ohio. While the city estimated the cost of the project around $227,608, appellant was awarded the contract on the basis of his $158,967.25 bid. Two relevant provisions within the Holford Street project contract were: (1) the contractor with the city must pay all employees the required "Federal prevailing wage" and (2) the contractor could only subcontract out fifty percent of the work.

{¶ 2} At trial, Mark Hess, Construction Contract Supervisor for the City of Niles, testified that appellant had reported the road black top, concrete sidewalk, and gutter installation would be subcontracted. This work represented nearly fifty percent of the work on the Holford Street project. In order to comply with the subcontracting limitation, any other work had to be accomplished by appellant's employees. With this in mind, appellant approached Steve Protiva ("appellee") and hired him to dig trenches and install pipe. Although the parties did not discuss other activities, appellee additionally removed sidewalk and road gutter while on the job.

{¶ 3} Although no written agreement was drafted, appellee testified that appellant would pay him the "Federal prevailing wage" and lease any equipment necessary for the job. According to appellee, in August, 2000, appellant requested that appellee bring his equipment to the worksite and begin work immediately. Although appellee tried to set forth a specific amount for his equipment rental, appellant stated: "`Just get your equipment out there and let's get started' * * * `we'll work the numbers out later on.'"

{¶ 4} From August 21, 2000 through September 28, 2000, appellee worked for appellant on the project. Although paid for his labor, appellee was never paid for the use of his equipment. When the project reached a standstill due to a conflict between the city and the gas company, appellee presented appellant with an invoice for the lease of the equipment. According to appellee, appellant disagreed with the figures and asked him to "re-work" them. After reconsideration, appellee notified appellant that he could not reduce the figures. According to appellee, appellant again stated he "needed better numbers." Appellant never paid appellee.

{¶ 5} At trial, appellant stated that appellee agreed to a "flat rate" compensation whereby he would be paid $6,000 for his work. According to appellant, the $6,000 figure was based upon negotiations during which appellee allegedly accepted appellant's offer to pay him $6 per linear foot of piping that he installed on a job which required the installation of approximately 1000 linear feet of pipe. If he did not do $6,000 worth of work, any remainder would be used as money for the lease. Appellee denied appellant's construction of the agreement and denied ever assenting to a "flat rate" of $6 per linear foot of pipe.

{¶ 6} This matter was tried to the bench on May 7, 2003. On June 30, 2003, the trial court issued its judgment in appellee's favor. Appellant now appeals and raises the following assignments of error:

{¶ 7} "[1.] The findings of fact relative to awarding plaintiff-appellee a judgment against defendant-appellant are against the manifest weight of the evidence, thus resulting in a grossly improper interpretation of the agreement between the parties.

{¶ 8} "[2.] The construction given the oral agreement between the parties is overbroad as a matter of law.

{¶ 9} "[3.] The damages awarded were erroneously calculated and are not supported in the record."

{¶ 10} As appellant's first two assignments of error attack the trial court's construction of the conflicting evidence presented at trial, we shall address them together.

{¶ 11} In determining whether the judgment of the trial court is against the manifest weight of the evidence, an appellate court is guided by the presumption that the findings of the trial court are correct as the trial judge is in the best position to view the witnesses and observe the demeanor, gestures, and voice inflections, and use these observations in weighing the credibility of the testimony. Ratliff v. Dept. ofRehabilitations and Corrections (1999), 133 Ohio App.3d 304,309.

{¶ 12} "Judgments supported by some competent, credible evidence going to all essential elements of the case will not be reversed by a reviewing court as being against the manifest weight of the evidence." C.E. Morris Co. v. Foley ConstructionCo. (1978), 54 Ohio St.2d 279, syllabus.

{¶ 13} Appellant presented evidence that, although he had an oral agreement with appellee, the agreement unequivocally limited appellee's compensation to $6,000 for his services. According to appellant, the $6,000 figure was based upon negotiations during which appellee allegedly accepted appellant's offer to pay him $6 per linear foot of piping that he installed on a job which required the installation of approximately 1000 linear feet of pipe. Appellant contends that the $6,000 ceiling enveloped not only the labor appellee provided but also the use of his equipment. Appellant argues that the trial court's construction of the oral agreement, allowing appellee to recover $7,400 for use of his equipment, was overbroad and against the manifest weight of the evidence.

{¶ 14} Appellee's complaint against appellant sounded in breach of contract. In general, to establish a breach of contract a party must demonstrate: (1) the existence of a binding contract; (2) the non-breaching party performed its contractual duties; (3) the other party failed to fulfill its contractual duties without legal excuse; and (4) the nonbreaching party suffered damages as a result of the breach. Laurent v. FloodData Services, Inc. (2001), 146 Ohio App.3d 392, 398, citing,Garofalo v. Chicago Title Ins. Co. (1995), 104 Ohio App. 3d 95,108.

{¶ 15} Pursuant to his contract with the City of Niles, appellant could subcontract up to fifty percent of the work; however, as he had already approached that limit,1 he was required to hire appellee as an employee. Both appellant and appellee testified that appellant agreed to hire appellee as an employee, rather than a subcontractor, for the Holford Street project. Hence, neither party disputes that a binding oral contract existed between the parties wherein appellee would work on the construction site as appellant's employee.

{¶ 16} At some point in August, 2000, the parties met and discussed the nature of their prospective relationship. During this meeting, appellee testified that appellant offered to hire him as his employee and lease appellee's equipment for use on the project. Nothing final regarding appellee's compensation was established at this meeting. However, appellee testified that he rejected appellant's offers to pay him $6 per linear foot of piping and $10 per linear foot of piping.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee v. Sanders, Unpublished Decision (4-29-2005)
2005 Ohio 2091 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 6338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ty-excavating-inc-v-boccia-unpublished-decision-11-26-2004-ohioctapp-2004.