Twp. of Mt. Lebanon v. Metropolitan Casualty Ins. Co. of New York.

161 A. 632, 106 Pa. Super. 209, 1932 Pa. Super. LEXIS 225
CourtSuperior Court of Pennsylvania
DecidedApril 21, 1932
DocketAppeal 128
StatusPublished
Cited by6 cases

This text of 161 A. 632 (Twp. of Mt. Lebanon v. Metropolitan Casualty Ins. Co. of New York.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Twp. of Mt. Lebanon v. Metropolitan Casualty Ins. Co. of New York., 161 A. 632, 106 Pa. Super. 209, 1932 Pa. Super. LEXIS 225 (Pa. Ct. App. 1932).

Opinion

Opinion by

Cunningham, J.,

In this> action on an additional bond, given by a contractor, as principal, and the defendant, as surety, to protect laborers and materialmen, the main question is whether the bond was intended to cover materials furnished by the use-plaintiff prior to the date on which it was executed. The court below decided the questions of law raised by the defendant’s statutory demurrer in its favor on the ground that the bond was intended to operate prospectively only; from the judgment thus entered for defendant the use-plaintiff has appealed.

The facts as set forth in the statement of claim are *. The Township of Mount Lebanon, the legal plaintiff, entered into a contract on October 8, 1928, with the Southern Construction and Supply Corporation for the grading, paving and curbing of a road in that township. Defendant, as surety, executed the usual performance bond. The use-plaintiff, a cement company, sold the contractor, between October 14 and October 17, 1929, cement which entered into the construction. Under the use-plaintiff’s credit terms, the contractor was entitled to a period of thirty days within which to make payment. The contractor never paid for the cement, but subsequently went into bankruptcy, and the use-plaintiff has received only a three per cent dividend from the bankrupt estate.

On November 12, 1929, the contractor, as principal, and defendant, as surety, entered into an additional bond in the amount of $35,488, naming the Township of Mount Lebanon as obligee and conditioned that the contractor, “shall and will promptly pay, or cause to *212 be paid, to any person or persons, co-partnership or co-partnerships, corporation or corporations all sums of money which may be due for labor performed or materials supplied and furnished in and about the performance of the work covered by the said contract.”

The construction work was accepted by the township on December 30, 1929. In form, this bond is similar to the one considered by us in City of Pittsburgh to the use of The Bessemer Cement Corporation v. Commercial Casualty Insurance Co., 106 Pa. Superior Ct. 254, in that the township is the sole obligee, and no right of action thereon is expressly given to laborers and materialmen. The distinction, however, is in the fact that this bond was executed subsequent to the Act of March 28, 1929, P. L. 106, which further amended the earlier Acts of May 6, 1925, P. L. 546, and May 10,1917, P. L. 158, so as to require townships, among other municipalities, to take out an additional bond for the payment of all labor and material entering into the construction of “roads” as well as into public buildings, etc. Therefore, when this bond was executed laborers and materialmen had legislative authority to sue thereon, although that right was not specifically given in the bond. Defendant does not seriously challenge the general right of action; the statement in its brief that the Act of 1929 required such a bond only “under all contracts subsequently let” is not sound, since no such language appears in that statute or in those to which it is an amendment. As stated above, the serious defense is that the defendant surety company should not be held liable for materials furnished for the job prior to the execution of its bond.

We are not convinced that the court below was justified, under all the averments in the statement and the reasonable inferences arising therefrom, in finally disposing of this case upon the rebuttable presumption *213 that bonds are intended to secure losses sustained after, and not before, their execution.

In the first place, we think the lower court should not have ignored the averment as to the credit terms of the use-plaintiff. The statement of claim alleges that under these terms the contractor had thirty days in which to pay for the cement, which would make the obligation mature on November 17, 1929 — five days after the execution of the bond. If, in fact, these credit terms were a part of the contract between the use-plaintiff and the contractor, the latter was not in default until November 17,1929. It would seem reasonable that the definitive point of responsibility should be the time when the obligation was due and payable, and not when the materials were furnished. Nor is it a valid objection, as urged by defendant, that the materials could not have been furnished in reliance upon the bond; they may have been furnished in reliance upon a promise of a bond to be executed in the future; but even if such were not the case, the matter is immaterial, as no consideration need move from the material-men. The sole issue is whether a bond was in fact given under which materialmen have a right of action. Nor are we impressed by the case of U. S. Fidelity and Guaranty Co. v. Fultz, 76 Ark. 410, which involved a bond required of fire insurance companies, conditioned for the payment of all claims arising under any policy, It is true it was held that the liability of the surety was fixed when the loss by fire occurred, and not from the date when the amount due under the policy became payable. As the opinion indicates, however, this construction was required by the terms of the statute and was for the ■ protection of the insured — not of the surety.

Again, we are not convinced that the bond was intended to have only a prospective effect. In support of its decision the court cites Tarentum Realty Co. v. *214 McClure et al., 230 Pa. 266, in which it was said (at page 270): “The general rule is that bonds are presumptively intended to secure losses sustained after and not before their execution. This, however, is only a presumption which may be overcome if the facts show that past as well as future defaults were intended to be covered by the bond.”

This is undoubtedly the general rule of construction, but, as- the presumption is rebuttable, a court should consider any facts which might tend to establish a contrary effect. The true intent of the bond is to be determined not only from its language, but from all the surrounding circumstances: Commonwealth to Use v. Fidelity & Deposit Company of Maryland, 224 Pa. 95. In the latter case the court said (at page 100), referring to the presumption: “It is one of those general rules to which there are so many exceptions under the facts of particular cases as to require the greatest care in its application in order that injustice may not be done or the legal rights of parties be defeated.”

The court there held a surety company upon the additional bond of a trustee liable for a loss resulting from the misconduct of the trustee previous to the date of the bond. In reaching this determination it took into account not only the language of the bond itself, but the application made by the trustee for the bond and all the surrounding circumstances, including the character of the trust, its indefinite duration, the purpose for which the bond was given, and the investigation made by the surety company prior to its execution. We think these and similar matters should be investigated and considered in this case before it is finally disposed of.

It is to be noted that the bond is general in its terms, referring to the execution of the contract and requiring that the contractor pay all money which may be due for labor performed or materials supplied and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Insurance Exchange v. Transamerica Insurance
507 A.2d 389 (Supreme Court of Pennsylvania, 1986)
Police Protective Ass'n of Casper v. City of Casper
575 P.2d 1146 (Wyoming Supreme Court, 1978)
Fugh Coal Co. v. City of Pittsburgh
70 Pa. D. & C. 299 (Alleghany County Court of Common Pleas, 1949)
Commonwealth v. Ramsey
171 A. 575 (Supreme Court of Pennsylvania, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
161 A. 632, 106 Pa. Super. 209, 1932 Pa. Super. LEXIS 225, Counsel Stack Legal Research, https://law.counselstack.com/opinion/twp-of-mt-lebanon-v-metropolitan-casualty-ins-co-of-new-york-pasuperct-1932.