Twin Oaks at Southwood v. Summit Constrs.
This text of 941 So. 2d 1263 (Twin Oaks at Southwood v. Summit Constrs.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
TWIN OAKS AT SOUTHWOOD, LLC, Appellant,
v.
SUMMIT CONSTRUCTORS, INC., a Florida Corporation, Appellee.
District Court of Appeal of Florida, First District.
*1264 M. Stephen Turner, P.A., and J. Nels Bjorkquist, of Broad and Cassel, Tallahassee, for Appellant.
Hugh M. Davenport, Jacksonville, for Appellee.
BARFIELD, J.
The defendant in a lawsuit arising out of a construction contract appeals a non-final order which granted the plaintiff's motion to dismiss the defendant's counterclaims and determined that the plaintiff was entitled to arbitration of the counterclaims. We find that the trial court erred in finding that the plaintiff did not waive its right to demand arbitration when it instituted the litigation.
In 2002, appellant/owner and appellee/contractor entered into a "cost plus" contract for construction of a housing complex under the supervision of the federal Department of Housing and Urban Development (HUD), to be completed in February 2004 (hereinafter designated "the Contract"). The Contract provided that the agreement between the parties was set forth in the "Contract Documents," which included, inter alia, the AIA "General Conditions of the Contract for Construction." The AIA general conditions defined "Contract Documents" as including, inter alia, "Modifications issued after execution of the Contract," and defined "modification" in this context as "(1) a written amendment of the Contract signed by both parties, (2) a Change Order, (3) a Construction Change Directive or (4) a written order for a minor change in the Work issued by the Architect." The AIA general conditions also included an arbitration clause: "Any Claim arising out of or related to the Contract, except Claims relating to aesthetic effect and except those waived as provided for in Sections 4.3.10, 9.10.4 and 9.10.5, shall, after decision by the Architect or 30 days after submission of the Claim to the Architect, be subject to arbitration."
In May 2004, three months after the completion date contemplated in the Contract, the parties entered into a "Project Completion Agreement" (PCA), which referenced the Contract. The PCA stated that the parties had agreed to two change orders which had been "fully funded," and that a third change order had been approved for an extension of the contract completion date. It noted that problems attributable to the architect had caused substantial delays in the progress of the work, that additional upgrades had been made and additional fee obligations had been incurred, and that the parties wished "to conclude construction expeditiously and [to] resolve all issues known or which could have been known and to establish with finality amounts that will be due [the contractor] upon final completion of the project." The owner agreed that $340,012.00 would be due the contractor "in addition to *1265 Contract initial amount and the previously funded Change Orders No. 1 and No. 2 to cover all issues known or which could have been known through project completion." The owner also agreed to pay the water connection fees, to waive any liquidated damages under the contract "up to September 1, 2004," and to request that the 10% retainage be reduced to 5% when the project was certified 90% complete by HUD. Paragraph six provided: "This Agreement constitutes the entire agreement between the Parties with respect to the subject matter hereof and may not be amended except in a writing signed by the Parties." Paragraph eight provided: "Except as provided herein, the terms and conditions of the Contract shall remain in full force and effect."
In May 2005, one year after the PCA was signed, nearly nine months after the completion date referenced in the PCA, and four months after the substantial completion date in January 2005, the parties entered into a "Project Disbursement Agreement" (PDA), which referenced the Contract and incorporated the PCA. It stated that the "total unpaid balance in the HUD Contract for Construction plus approved change orders" was just under $2.5 million and that the parties and the lender "wish to facilitate the final endorsement of the Project by providing for an agreed upon assessment of liquidated damages" to allow the owner, lender, and HUD "to balance the loan and disburse the balance of the funds designed for construction to [the contractor]." The contractor agreed to provide the documents required to remove all liens filed by it or its subcontractors and to keep the property free of any future liens. In return, the lender agreed to disburse to the contractor $1.5 million, which represented the amount due at that point, less $471,413.00 in liquidated damages (the actual liquidated damages would have exceeded $800,000). The parties agreed that at final endorsement, the lender would disburse to the contractor the remainder of the unpaid balance. Paragraph eight provided: "Except as provided herein, the terms and conditions of the Contract shall remain in full force and effect." Paragraph nine provided: "This written Agreement and all of its provisions shall be considered to be the complete Agreement between the Parties relating to the matters set forth herein, notwithstanding any oral representations or other writings to the contrary and may not be amended except in a writing signed by all Parties to this Agreement."
In December 2005, the contractor filed a complaint against the owner which referenced the Contract, the PCA, and the PDA, and which sought payment of $340,012.00 "as required by the Project Completion Agreement," together with prejudgment interest and costs. The owner's answer asserted that the PCA became part of the subsequent PDA, "which finally resolved the amounts to be paid to Plaintiff after construction was fully completed," that the PDA "is an accord and satisfaction of any amount owed for project construction," and that the actual liquidated damages chargeable to the contractor for failure to complete the work by the extended completion date "far exceeded the amount due under the Project Completion Agreement, and were foregone under the Project Disbursement Agreement to satisfy all obligations." As affirmative defenses, the owner asserted that the PDA fulfilled all of the owner's obligations to pay the contractor "by accord and satisfaction," and that the owner was entitled to set-offs for utility charges it had paid on behalf of the contractor and for loss of utility refunds for which the contractor was responsible.
The owner was allowed to file a four-count counterclaim which referenced the three agreements between the parties. *1266 The first count stated that between the extended completion date and the substantial completion date, potential liquidated damages had accrued in the amount of $814,574.88, but that only $417,413.00 in liquidated damages were assessed under the PDA, leaving remaining liquidated damages of $397,161.88, which exceeded the amount the contractor was seeking to recover from the owner. The second count stated that defective work by the contractor had required the owner to incur $8,000 in repair costs and roughly $50,000 in estimated repair costs. The third count stated that the contractor had not installed backflow preventers as required by the building codes, that the cost of installing the backflow preventers was $100,000.00, and that the contractor had not agreed to pay for it after demand had been made.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
941 So. 2d 1263, 2006 WL 3371495, Counsel Stack Legal Research, https://law.counselstack.com/opinion/twin-oaks-at-southwood-v-summit-constrs-fladistctapp-2006.