TWB Architects, Inc. v. The Braxton, LLC

Procedural entryThis page is a short order in TWB Architects, Inc. v. The Braxton, LLC. Read the opinion of the Court — 578 S.W.3d 879
Tennessee Supreme Court·Decided July 22, 2019·No. M2017-00423-SC-R11-CV·Published

Opinion

07/22/2019 IN THE SUPREME COURT OF TENNESSEE AT NASHVILLE February 6, 2019 Session

TWB ARCHITECTS, INC. v. THE BRAXTON, LLC ET AL.

Appeal by Permission from the Court of Appeals Chancery Court for Cheatham County No. 14181 David D. Wolfe, Judge ___________________________________

No. M2017-00423-SC-R11-CV ___________________________________

We granted review to determine whether summary judgment was properly granted to an architect firm seeking to recover its design fees from a development company. The architect firm designed a condominium project for the development company. The development company ran short of funds and was not able to pay the architect firm under their design contract. As a result, the architect firm’s president agreed to accept a condominium in the project instead of the fee. But the development company did not fulfill that agreement because the development company had pledged the condominium as collateral for a construction loan. The architect firm filed a mechanic’s lien for its unpaid fee under the parties’ design contract, and then filed this suit to enforce the lien. The trial court granted summary judgment to the architect firm, holding that the firm was entitled to its fee under the design contract, and there was insufficient evidence that the parties intended a novation by substituting the agreement to convey a condominium for the design contract. The Court of Appeals affirmed. We find that disputed questions of material fact exist about whether the architect firm and the development company intended a novation when they entered into the agreement for the condominium. Thus, the trial court should not have granted summary judgment to the architect firm. We reverse and remand to the trial court.

Tenn. R. App. P. 11 Appeal by Permission; Judgment of the Court of Appeals Reversed; Judgment of the Trial Court Reversed; Remanded to the Trial Court

SHARON G. LEE, J., delivered the opinion of the Court, in which JEFFREY S. BIVINS, C.J., CORNELIA A. CLARK, HOLLY KIRBY, and ROGER A. PAGE, JJ., joined.

William R. O’Bryan, Jr., and Kevin C. Baltz, Nashville, Tennessee, for the appellants, The Braxton, LLC, and Fidelity and Deposit Company of Maryland.

Donald N. Capparella, Nashville, Tennessee, for the appellee, TWB Architects, Inc. OPINION

Background

In February 2005, TWB Architects, Inc., through its president and sole owner, Timothy W. Burrow, signed an agreement (“Architect Agreement”) with Progress Capital Partners, LLC, through its sole member and chief manager, John Rankin. Under the Architect Agreement, TWB Architects agreed to provide design services for the construction of a condominium complex, known as “The Braxton,” in Ashland City. Progress Capital Partners agreed to pay TWB Architects a fee for its design services based on two percent of the construction costs for the project, with progress payments based on an hourly rate billed monthly before construction.1

Progress Capital Partners failed to obtain sufficient financing for the project. In early May 2005, Mr. Rankin advised Mr. Burrow that the construction budget could not cover TWB Architects’ fee. Mr. Rankin proposed that Mr. Burrow accept a condominium in the project as payment for the architect firm’s fee. Mr. Burrow, with the consent of TWB Architects, agreed.

Later, Progress Capital Partners deeded the property on which the project was located to The Braxton, LLC (“Braxton”), a company formed by Mr. Rankin.2 On February 16, 2006, Braxton and Mr. Burrow agreed in writing (“Condominium Agreement”) for Mr. Burrow to buy Penthouse P6 for “$0 in consideration of design fees owed in contract for architecture design” between Progress Capital Partners and TWB Architects dated February 17, 2005. Mr. Burrow, with TWB Architects’ consent, signed as purchaser and Mr. Rankin signed as seller for Braxton.3 Attached and incorporated

1 Section 11.2.4 of the Architect Agreement details TWB Architects’ fee arrangement:

Progress payments will be made based on $150 per hour, plus expenses, but with a maximum of two (2) percent of construction costs. At the end of the Architect’s Basic Services, if the amount paid is less than two (2) percent of the construction costs, payment will be made for the difference at the time the Owner begins construction. If the project is not constructed, there will be no obligation to pay more than $150 per hour, plus expenses. 2 In January 2007, Charles Elcan became a member of Braxton. Mr. Elcan became the sole member when Mr. Rankin surrendered his membership interest in September 2008. 3 The Condominium Agreement was not the first time TWB Architects had consented to Mr. Burrow being given consideration for TWB Architects’ fees. Mr. Rankin had also signed the Architect Agreement as managing general partner of the Ashland Company. The Architect Agreement provided that one-third of TWB Architects’ design fee could be applied as credit against any mortgage balances owed

-2- into the Condominium Agreement was a copy of the Architect Agreement, showing that TWB Architects’ fee supported the zero dollar purchase price. Under the Condominium Agreement, the closing of the sale would be on or before August 4, 2008, with an option for Braxton to extend that date for up to ninety days.

After June 2005, TWB Architects stopped sending Braxton monthly invoices for progress payments. By May 2006, TWB Architects had substantially completed its design work. During construction of the project, Mr. Rankin routinely submitted Loan Advance Requisition forms and Sworn Owner’s Statements to the bank financing the project. Mr. Rankin signed the Sworn Owner’s Statements, verifying that there were no unpaid architect fees because he understood there were no fees owed to TWB Architects based on the Condominium Agreement.

During construction of the project, Mr. Burrow spent nearly $40,000 for upgrades to Penthouse P6, which he referred to as “my penthouse.” He corresponded with the general contractor and with Mr. Rankin about specific upgrades to customize Penthouse P6, which included cabinets, granite, tile, lighting, mantles, hearths, doors, wiring, and a unique floorplan.

On November 3, 2008, the day before the extended closing deadline under the Condominium Agreement, Mr. Burrow wrote to Mr. Rankin demanding to close the next day. In addition, Mr. Burrow stated that if Braxton failed to meet the closing deadline, then Mr. Burrow would treat the Condominium Agreement “as continuing in full force and effect, and require specific performance of [Braxton] to deliver a deed.” He mentioned neither the Architect Agreement nor the design fee.

A week later, Mr. Burrow wrote to Mr. Rankin to clarify “instead of TWB Architects, Inc. receiving cash for the design fee of 2 percent of construction cost as set forth in the . . . [Architect Agreement], I will be given Penthouse P6 and the boat slip.” He asked Mr. Rankin to sign at the bottom of the letter to confirm the terms stated in the letter, but Mr. Rankin did not do so.

On November 11, 2008, Mr. Burrow emailed Mr. Rankin, asking whether he had told the bank that the proceeds from the condominium sale to Mr. Burrow would be zero dollars. Mr. Rankin replied that he had told the bank that Mr. Burrow would need to be paid two percent or receive his condominium unit, and that Mr. Burrow had invested tens of thousands of dollars in the condominium. Mr. Rankin later admitted in a 2010

by Mr. Burrow to Mr. Rankin or the Ashland Company if Mr. Burrow exercised his option under a lease/purchase agreement to purchase condominium units that he was leasing from the Ashland Company.

-3- deposition that he told the bank something different—that Mr. Burrow was “our design architect, and he’s getting this unit for his fees.”

On November 25, 2008, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

TWB Architects, Inc. v. The Braxton, LLC, (Tenn. 2019).

TWB Architects, Inc. v. The Braxton, LLC (TWB Architects, Inc. v. The Braxton, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sartor v. Arkansas Natural Gas Corp.
321 U.S. 620 (Supreme Court, 1944)
In Re Estate of Ina Ruth Brown
402 S.W.3d 193 (Tennessee Supreme Court, 2013)
Tina Marie Hodge v. Chadwick Craig
382 S.W.3d 325 (Tennessee Supreme Court, 2012)
84 Lumber Co. v. Smith
356 S.W.3d 380 (Tennessee Supreme Court, 2011)
HCA, Inc. v. American Protection Insurance Co.
174 S.W.3d 184 (Court of Appeals of Tennessee, 2005)
Abshure v. Methodist Healthcare-Memphis Hospitals
325 S.W.3d 98 (Tennessee Supreme Court, 2010)
B & B Enterprises of Wilson County, LLC v. City of Lebanon
318 S.W.3d 839 (Tennessee Supreme Court, 2010)
Tennie Martin, et.al. v. Southern Railway Company, et.al.
271 S.W.3d 76 (Tennessee Supreme Court, 2008)
Hannan v. Alltel Publishing Co.
270 S.W.3d 1 (Tennessee Supreme Court, 2008)
Staples v. CBL & Associates, Inc.
15 S.W.3d 83 (Tennessee Supreme Court, 2000)
McCarley v. West Quality Food Service
960 S.W.2d 585 (Tennessee Supreme Court, 1998)
Anderson v. Mason
141 S.W.3d 634 (Court of Appeals of Tennessee, 2003)
Church v. Perales
39 S.W.3d 149 (Court of Appeals of Tennessee, 2000)
Jennings v. Case
10 S.W.3d 625 (Court of Appeals of Tennessee, 1999)
State v. Matthews
888 S.W.2d 446 (Court of Criminal Appeals of Tennessee, 1993)