Turner v. Cox

196 Cal. App. 2d 596, 16 Cal. Rptr. 644, 1961 Cal. App. LEXIS 1618
CourtCalifornia Court of Appeal
DecidedNovember 1, 1961
DocketCiv. 25576
StatusPublished
Cited by13 cases

This text of 196 Cal. App. 2d 596 (Turner v. Cox) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Turner v. Cox, 196 Cal. App. 2d 596, 16 Cal. Rptr. 644, 1961 Cal. App. LEXIS 1618 (Cal. Ct. App. 1961).

Opinion

LILLIE, J.

Plaintiff Turner, and Cox, a contractor, entered into a written agreement wherein Cox agreed to construct a house for the Turners; it also provided for arbitration of all disputes and grievances arising from the contract. A controversy arose relative to faulty construction; thus, on June 1, three arbitrators were selected—Mr. Drinkward, by the Turners; Mr. Bugay, by Cox, and Mr. Wills, by Bugay and Drinkward. After several inspections of the premises and various meetings at which all arbitrators were present, an award was made in favor of the Turners at a meeting on July 21. Concurrent with a motion to confirm the award, Cox moved the Superior Court for an order vacating the same; considerable testimony was taken; the trial court denied the motion to vacate and confirmed the award giving judgment for the Turners. Cox appeals.

The arbitration portion of the written agreement providing that “if there be three (arbitrators) the decision of any two of shall be binding” (par. 15), is here controlling (Crofoot v. Blair Holdings Corp., 119 Cal.App.2d 156 [260 P.2d 156]); however, under section 1286, Code of Civil Procedure, “all the arbitrators shall sit at the hearing of the ease, unless, by consent in writing, all parties shall agree to pro *599 ceed with the hearing with a less number.” Appellant complains that at the last meeting (July 21) resulting in the award, only two arbitrators were present; moreover, they acted without a report of one Mendez for which the arbitrators agreed to wait.

The arbitrator absent at the July 21 meeting was Mr. Bugay. Inasmuch as he is a practicing attorney and in addition to being Cox’s arbitrator was then also his counsel, we are at a loss to understand his apparent indifference to the last meeting of the arbitrators unless he then believed, what appears to be the fact, that the meeting was not “a hearing of the ease” and was not called for that purpose, a hearing at that time was never intended (the evidence having already been taken and discussed and findings and reports having previously been made by two of the arbitrators), and the meeting was called for the sole purpose of making the award, which Bugay knew would be adverse to his client.

The Turners, disturbed by the delay since June 1, asked their counsel, Mr. Butcher, to have the arbitrators meet and decide the matter “one way or the other”; thus he prepared a notice of meeting for this purpose for July 23; on July 18 each of the three arbitrators, including Bugay was served. Thereafter, Butcher contacted Bugay, told him about the findings and reports of the two other arbitrators and asked him if he would be present on July 23d; Bugay told him he could not be there and requested him to advance the meeting to a date convenient to him (Bugay) ; thus, Butcher said to him, “Well, you name a time,” Bugay mentioned July 21, and he and Butcher entered into a stipulation advancing the date from July 23 to the evening of July 21. This was done solely at the request of, and as an accommodation to, Bugay. Pursuant thereto Butcher prepared a new notice of meeting for July 21; when it was served on Bugay he accepted service in writing and said he would be present. However, around 4 or 4:30 p.m. on July 21, Bugay called Butcher’s office, in the latter’s absence, and without giving any reason therefor simply told Butcher’s secretary he would not be at the meeting that evening, and wanted Butcher to call him “if she could arrange it.” Bugay neither asked for nor mentioned any continuance or postponement, nor did he inquire if the meeting would take place in his absence. Butcher did not return to his office until shortly before the scheduled meeting, and the first he knew of Bugay’s call or that he would not be present, was at 7 :30 p.m., when he read the memo relative to *600 the call his secretary had left on his desk. Drinkward and Wills arrived at the meeting; Bugay did not appear, nor did his client, Cox. Twenty or thirty minutes later, Wills and Drinkward signed the award. During the entire meeting, until 9 :30 or 10 p.m. Bugay was in his own office; however, even knowing where they would be, he then made no attempt to call Butcher, Wills or Drinkward. Bugay made no effort to determine if the meeting would be, or had been, continued and whether the two arbitrators had proceeded without him.

As to what transpired during the meeting of July 21, it is apparent that no “hearing of the case” was held; at that time all that remained was the making of the award and it was for that purpose alone the meeting was called; and that was precisely what was done.

The arbitrators had been appointed on June 1; thereafter they held various meetings, some of which were at the Turner home and constituted an inspection of the premises for the defects; all three arbitrators were present, discussed all points of contention and talked to the parties. Bugay, acting in the dual capacity of Cox’s arbitrator and his counsel, was at all of these meetings. Ten days prior to July 21 he saw a list of the defects prepared by the Turners’ counsel, also that made by Drinkward; and around July 1, saw photographs of defects under the house (Exhibits 12A-H). He made two inspection trips and investigated the premises with the other arbitrators; he knew of the porch beam defects and that the “floor had been jacked up,” and agreed during the meetings to a number of other defects. Cox, his client, was consulted and the arbitrators throughout talked to him however, neither Cox nor Bugay offered evidence except that regarding items of cost which they agreed upon. After all hearings had been concluded Drinkward and Wills each prepared a report of his findings. Wills prepared his report about July 15; thereafter, he saw the report of the building inspector (Mr. Hill) and confirmed his findings as being in line with Hill’s report. No dissenting report was ever prepared by Bugay; Bugay had full knowledge of the reports of Drinkward and Wills prior to July 21, and had received a copy of Wills’ report the day before. Cox talked to Wills regarding the report before July 21, and was familiar with the list of structural defects contained therein.

The record is clear that at the hearings held at various times from June 1 to July 21, all evidence necessary to the award had been taken and discussed by the arbitrators, inspections *601 of the premises and investigations of the defects had been made, data prepared by others had been examined, both parties had been consulted, and all contentions on both sides had been studied; and two of the three arbitrators had made reports of their findings. All that remained on July 21 was the making of the final award, for which purpose the meeting at that time was called; no party or his counsel was present during the meeting. It is apparent that no “hearing of the case” was then held; in fact, appellant concedes that the award was made at the July 21 meeting “without taking evidence.” (A.O.B., p. 4.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tung v. Cal. Mortgage and Realty CA1/4
California Court of Appeal, 2015
Cooper v. Lavely & Singer Professional Corp.
230 Cal. App. 4th 1 (California Court of Appeal, 2014)
Kaufman v. Diskeeper CA2/4
California Court of Appeal, 2014
Harris v. GRANGE INSURANCE ASS'N.
868 P.2d 201 (Court of Appeals of Washington, 1994)
Good v. Kaiser Foundation Hospital
152 Cal. App. 3d 819 (California Court of Appeal, 1984)
Davey Tree Surgery Co. v. International Brotherhood of Electrical Workers
65 Cal. App. 3d 440 (California Court of Appeal, 1976)
Sevey v. AMERICAN FEDERATION OF ST. ETC. EMPLOYEES
48 Cal. App. 3d 64 (California Court of Appeal, 1975)
United Brotherhood of Carpenters & Joiners of America, Local 642 v. DeMello
22 Cal. App. 3d 838 (California Court of Appeal, 1972)
Nickals v. Ohio Farmers Insurance Company
237 F. Supp. 904 (N.D. California, 1965)
McRae v. Superior Court
221 Cal. App. 2d 166 (California Court of Appeal, 1963)
Palm Springs Homes, Inc. v. Western Desert, Inc.
215 Cal. App. 2d 270 (California Court of Appeal, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
196 Cal. App. 2d 596, 16 Cal. Rptr. 644, 1961 Cal. App. LEXIS 1618, Counsel Stack Legal Research, https://law.counselstack.com/opinion/turner-v-cox-calctapp-1961.