Turner Construction Co. v. J & A Concrete Corp.

44 Misc. 3d 217, 984 N.Y.S.2d 579
CourtNew York Supreme Court
DecidedApril 1, 2014
StatusPublished
Cited by2 cases

This text of 44 Misc. 3d 217 (Turner Construction Co. v. J & A Concrete Corp.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Turner Construction Co. v. J & A Concrete Corp., 44 Misc. 3d 217, 984 N.Y.S.2d 579 (N.Y. Super. Ct. 2014).

Opinion

OPINION OF THE COURT

Eileen Bransten, J.

This matter comes before the court on petitioner Turner Construction Company’s verified petition (the petition) to permanently stay the arbitration initiated by respondent J & A Concrete Corporation. Respondent opposes. For the reasons that follow, the petition is granted.

Background

Petitioner was retained by the Government of the Republic of Singapore (the owner) to act as general contractor on a construction project known as the New Chancery of the Permanent Mission of Singapore to the United Nations (the project).

Petitioner and respondent entered into a subcontract dated November 16, 2011 (the subcontract), pursuant to which respondent would be paid $2.9 million to perform work related to “superstructure concrete” for the project. (Petition ¶ 5.)

As set forth in greater detail below, the subcontract sets forth the procedure by which respondent is required to request payment from petitioner. The underlying dispute stems in part from respondent’s requisition for payment submitted on July 19, 2013. On August 2, 2013, petitioner returned a marked-up [220]*220copy of the requisition to respondent, stating that certain of the invoiced amounts were not approved. Specifically at issue are 10 invoices, pursuant to which respondent seeks payment totaling $57,561 (the invoices).

Separately, the subcontract provides that a certain percentage of the contract price is retained by the owner until completion of the project. Respondent’s request that the amount of such retainage be reduced from 10% to 5% was denied, although the retainage was reduced to $250,000 by petitioner’s letter dated June 13, 2013. Respondent nevertheless argues that the amount of such retainage is unreasonable.

On October 4, 2013, respondent filed a demand for arbitration with the American Arbitration Association (AAA), seeking recovery of $360,000 for “ ‘contract work, change orders and retainage.’ ” (Petition ¶ 6.) The arbitration demand was assigned claim No. 002-ROF-59N. (Petitioner’s exhibit B.) The parties thereafter agreed to extend the deadlines imposed by the AAA until November 14, 2013 (Rosen affirmation, exhibit A), and petitioner commenced this action on November 22, 2013.

Analysis

A petition to permanently stay arbitration is brought pursuant to section 7503 of the New York Civil Practice Law and Rules, which provides in pertinent part that “a party who has not participated in the arbitration and who has not made or been served with an application to compel arbitration, may apply to stay arbitration on the ground that a valid agreement was not made or has not been complied with.” (CPLR 7503 [b].)

In the context of such a petition, “the courts play the ‘gate-keeping’ role of deciding certain ‘threshold’ issues before compelling or staying arbitration.” (Merrill Lynch, Pierce, Fenner & Smith v Benjamin, 1 AD3d 39, 43 [1st Dept 2003].) Notably, “the threshold issue of whether the parties have agreed to arbitrate or otherwise are bound to arbitrate, is a matter for the courts to decide.” (Southgate Owners Corp. v KNS Bldg. Restoration Inc., 2013 NY Slip Op 32683[U], *2 [Sup Ct, NY County, July 24, 2013].) According to the First Department, “[t]he party seeking a stay of arbitration has the burden of showing sufficient facts to establish justification for the stay.” (Matter of AIU Ins. Co. v Cabreja, 301 AD2d 448, 449 [1st Dept 2003].)

Respondent initiated the arbitration in question pursuant to article 35-E of the New York General Business Law, which is also known as the New York Prompt Payment Act (PPA). Gen[221]*221eral Business Law § 756-b (3) (c) provides that under certain circumstances, an “aggrieved party may refer the matter ... to the American Arbitration Association for an expedited arbitration pursuant to the Rules of the American Arbitration Association.” (General Business Law § 756-b [3] [c].) General Business Law § 756-b (3) (a) sets forth the circumstances under which such a referral may take place, including “where a subcontractor alleges a contractor has violated the provisions of this article.” (General Business Law § 756-b [3] [a] [iv].)

I. Whether the Invoices Provide a Basis for Referral to Arbitration

The parties disagree whether the invoices provide a basis for referring the underlying dispute to arbitration. First, there is a question as to whether the invoices were timely disputed by petitioner. If they were not, as respondent contends, then petitioner would have committed a PPA violation which could trigger respondent’s right to initiate arbitration. Second, the work detailed in the invoices appears to have been authorized by petitioner’s representatives through the issuance of “Additional Work Order[s],” making them effectively undisputed. Arguably, petitioner’s subsequent failure to pay likewise constitutes a PPA violation warranting referral to arbitration.

A. The Timeliness of the Invoices

General Business Law § 756-a (2) (a) (ii) provides that “[u]pon delivery of an invoice and all contractually required documentation, a contractor or subcontractor shall approve or disapprove all or a portion of such invoice within twelve business days.” (General Business Law § 756-a [2] [a] [ii].)

Respondent characterizes the invoices as “undisputed, unprocessed, overdue and unpaid,” and states that “the invoices, although received many months before the commencement of the arbitration, are undisputed.” (Respondent’s affirmation in opp ¶¶ 1, 10.)

The dates of the invoices range from May 9, 2012 to April 26, 2013. (Respondent’s affirmation in opp ¶ 3.) However, despite their age, the invoices were submitted together on July 19, 2013. (Petition ¶ 9.) By response submitted on August 2, 2013, within the 12-business-day period mandated by General Business Law § 756-a (2) (a) (ii), petitioner disputed the invoices. (Petition ¶ 9.) The other requisition referenced in the parties’ papers is dated June 20, 2013, did not include the invoices, and was paid in the full amount of $148,858.20 by check dated July 16, 2013. (Petitioner’s reply affirmation ¶ 4; petitioner’s reply, exhibit A.) [222]*222Respondent has not identified any other requisition in which the invoices were submitted.

Accordingly, petitioner’s response to the July 19, 2013 requisition was timely under the PPA and does not provide basis under General Business Law § 756-b for referral to arbitration.

B. The Additional Work Orders

Respondent contends that the invoices were authorized and confirmed by petitioner’s representative by the issuance of multiple additional work orders, and that the invoices therefore represent work that respondent “completed, outside its contract work, at Turner’s direction.” (Respondent’s affirmation in opp ¶¶ 3-5.) In effect, respondent appears to be arguing that petitioner’s issuance of the additional work orders authorizing the work set forth in the invoices precluded petitioner from later disputing the invoices when they were submitted with the July 19, 2013 requisition.

Respondent’s characterization of the work as “outside its contract work” notwithstanding, the invoices along with multiple additional work orders memorialize exactly the type of deviation from “the Work” contemplated by article IX of the subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maple Drake Austell Owner, LLC v. D.F. Pray, Inc.
385 F. Supp. 3d 373 (S.D. Illinois, 2019)
Pike Co. v. Tri-Krete Ltd.
349 F. Supp. 3d 265 (W.D. New York, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
44 Misc. 3d 217, 984 N.Y.S.2d 579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/turner-construction-co-v-j-a-concrete-corp-nysupct-2014.