Pike Co. v. Tri-Krete Ltd.

349 F. Supp. 3d 265
CourtDistrict Court, W.D. New York
DecidedNovember 20, 2018
Docket6:18-CV-06311 EAW
StatusPublished
Cited by6 cases

This text of 349 F. Supp. 3d 265 (Pike Co. v. Tri-Krete Ltd.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pike Co. v. Tri-Krete Ltd., 349 F. Supp. 3d 265 (W.D.N.Y. 2018).

Opinion

ELIZABETH A. WOLFORD, United States District Judge *268INTRODUCTION

Plaintiff The Pike Company ("Pike") commenced this action on April 20, 2018, against Defendant Tri-Krete Limited ("Tri-Krete") for breach of contract. (Dkt. 1). On June 25, 2018, Tri-Krete filed an Answer, denying all material allegations in the Complaint and setting forth various affirmative defenses. (Dkt. 5). Tri-Krete also asserted several counterclaims against Pike, which included common law causes of action for breach of contract and unjust enrichment, and violations of the New York Prompt Payment Act, N. Y. Gen. Bus. Law §§ 756 - 758 ("PPA"). (Id. at 4-7).

Contemporaneously with the filing of its Answer, Tri-Krete filed a motion to stay this action and to compel arbitration based upon the alleged PPA violations. (Dkt. 7). Within the days thereafter, Pike responded with a motion to stay arbitration. (Dkt. 9). Pike subsequently filed a motion for a preliminary injunction, seeking to enjoin the arbitration proceedings. (Dkt. 22). For the following reasons, Tri-Krete's motion to stay this action and compel arbitration (Dkt. 7) is granted, Pike's motion to stay arbitration (Dkt. 9) is denied, and Pike's motion for a preliminary injunction (Dkt. 22) is denied.

BACKGROUND

Pike served as the construction manager contractor with Marist College on a campus housing project located in Poughkeepsie, New York (the "Marist Project"). (Dkt. 9-2 at ¶¶ 1, 3). Pike awarded Tri-Krete a subcontract to complete architectural precast work for the Marist Project. (Id. at ¶ 4; see Dkt. 29-1 at ¶¶ 2-3). The parties executed a Master Subcontract Agreement and a Work Order, dated October 2, 2015, and June 14, 2016, respectively (collectively, the "Subcontract"), which governed their relationship as it related to the Marist Project. (Dkt. 9-2 at ¶ 4; see Dkt. 11).

The Subcontract "required payment applications to be submitted by uploading the application to an online invoicing system called Textura." (Dkt. 29-1 at ¶ 9; see Dkt. 9-2 at ¶ 9; see also Dkt. 11 at 30 ("Unless otherwise directed or authorized, in writing, by Contractor, all Applications for Payment and supporting documents for Subcontractor and its sub-subcontractors and suppliers, shall be in electronic format and shall be submitted to Contractor using the Textura Payment Management System....") ). Pike needed to make the Textura system accessible every month so that Tri-Krete could submit the required payment application by the 25th day of that month. (See Dkt. 29-1 at ¶ 9; see Dkt. 9-2 at ¶ 9). According to Pike, "[s]ubcontractors submit 'pencil copies' of their payment applications via Textura," which then generate electronic reports. (Dkt. 9-2 at ¶ 9). Once submitted, "[t]he pencil copy is reviewed by Pike," and "[i]f appropriate, the pencil copy is approved in the system." (Id. ). Pike would also notify Tri-Krete if the "invoice require[d] any modification." (Dkt. 11 at 30; see Dkt. 29-1 at ¶ 9).

According to Tri-Krete's Vice President, Adam Bombini ("Bombini"), the company submitted Payment Application 12 ("App 12") and Payment Application 13 ("App 13") to the Textura system on June 24, 2017, and July 22, 2017, respectively. (See Dkt. 29-1 at ¶¶ 11, 25). Bombini states that Pike never asked for additional information nor did it expressly reject App 12 or App 13. (Id. at ¶¶ 11-12, 26-27).

*269Pike's Project Director, Daniel L. DeCarlo ("DeCarlo"), and Pike's Senior Project Manager, Gloria Ciminelli ("Ciminelli"), dispute the veracity of these submission dates, and instead they contend that App 12 and App 13 were both submitted on July 19, 2017. (Dkt. 9-2 at ¶ 10; Dkt. 34-1 at ¶ 15). Furthermore, DeCarlo also states that on July 24, 2017, Pike informed Tri-Krete that it was in default of certain obligations under the Subcontract, and that Pike was incurring "significant expenses and damages that exceeded Tri-Krete's pending payment application." (Dkt. 9-2 at ¶ 11; see Dkt. 10-5).1 In addition, DeCarlo refers to email communications, taking place between August 3, 2017, and August 4, 2017, in which he demanded that Bombini "immediately deliver a detailed accounts receivable/payable report for all Tri-Krete sub-subcontractors, vendors and suppliers, including documentation showing any unpaid cost liabilities related to Tri-Krete's performance." (Dkt. 9-2 at ¶ 12). DeCarlo insists that due to "the pending notices of default" and his unsatisfied demand for certain documentation, Tri-Krete "was clearly on notice that its payment application No. 12 was not approved and was disputed." (Id. at ¶ 13).

After July 2017, the parties apparently abandoned the Textura invoicing system. According to Bombini, Pike "locked Tri-Krete out of Textura so Tri-Krete could not submit [invoices 8880, 8893, 8894, 8915, and 8916] via Textura." (Dkt. 29-1 at ¶ 102). According to Ciminelli, Tri-Krete "was not issued an invitation through Textura to submit further payment applications" due to Tri-Krete's "continued defaults, its failure to provide requested information, the unapproved status [of App 12 and App 13], and Pike's resulting damages." (Dkt. 34-1 at ¶ 16). DeCarlo also avers that "Pike has no record of ever having received" invoices 8880, 8893, 8894, 8915, or 8916 in 2017, and that, in any event, "these invoices were not the form of payment application used on the Project, do not include all of the necessary documentation to establish Tri-Krete's entitlement to payment, and do not constitute proper payment applications under the terms of the Subcontract." (Dkt. 9-2 at ¶ 17).

Between May 9, 2017, and September 12, 2017, Tri-Krete submitted approximately 20 requests for contract revisions to Pike, asking for Pike to issue a "change order" modifying the Subcontract due to additional work completed by Tri-Krete. (See Dkt. 29-1 at 8-20). During this period, Tri-Krete received a letter from Pike, dated August 25, 2017, which denied contract revision numbers 005, 006, 007, 008, 010, and 018 (as it pertained to "Credit for UCP/Slaw Panels"). (Dkt. 32-17; see Dkt. 29-1 at ¶ 48). According to Bombini, Tri-Krete received no other correspondence rejecting any of the requests for contract revisions. (See Dkt. 29-1 at ¶ 101). It also appears that Tri-Krete memorialized its request for these contract revisions in a single invoiced submission, dated December 7, 2017, and identified as invoice number 8946. (Dkt. 32-34; see Dkt. 29-1 at ¶ 98). On behalf of Pike, DeCarlo contends that these contract revisions "are unapproved change order requests and claims that have been denied by Pike as untimely, unsupported and barred by the terms of *270the Subcontract," and these claims "do not constitute proper and approved payment applications under Tri-Krete's Subcontract." (Dkt. 9-2 at ¶¶ 19-20; see also Dkt. 34-1 at (Cimminelli averring that by December 7, 2017, "Tri-Krete was well aware ... that [Pike] had rejected, expressly or by the terms of the [S]ubcontract, each of the requests for change order listed" in invoice number 8946) ).

PROCEDURAL HISTORY

On April 20, 2018, Pike commenced this action alleging breach of the parties' Subcontract. (Dkt. 1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
349 F. Supp. 3d 265, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pike-co-v-tri-krete-ltd-nywd-2018.