Pike Co. v. Tri-Krete Ltd.
This text of 349 F. Supp. 3d 265 (Pike Co. v. Tri-Krete Ltd.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
ELIZABETH A. WOLFORD, United States District Judge *268INTRODUCTION
Plaintiff The Pike Company ("Pike") commenced this action on April 20, 2018, against Defendant Tri-Krete Limited ("Tri-Krete") for breach of contract. (Dkt. 1). On June 25, 2018, Tri-Krete filed an Answer, denying all material allegations in the Complaint and setting forth various affirmative defenses. (Dkt. 5). Tri-Krete also asserted several counterclaims against Pike, which included common law causes of action for breach of contract and unjust enrichment, and violations of the New York Prompt Payment Act, N. Y. Gen. Bus. Law §§ 756 - 758 ("PPA"). (Id. at 4-7).
Contemporaneously with the filing of its Answer, Tri-Krete filed a motion to stay this action and to compel arbitration based upon the alleged PPA violations. (Dkt. 7). Within the days thereafter, Pike responded with a motion to stay arbitration. (Dkt. 9). Pike subsequently filed a motion for a preliminary injunction, seeking to enjoin the arbitration proceedings. (Dkt. 22). For the following reasons, Tri-Krete's motion to stay this action and compel arbitration (Dkt. 7) is granted, Pike's motion to stay arbitration (Dkt. 9) is denied, and Pike's motion for a preliminary injunction (Dkt. 22) is denied.
BACKGROUND
Pike served as the construction manager contractor with Marist College on a campus housing project located in Poughkeepsie, New York (the "Marist Project"). (Dkt. 9-2 at ¶¶ 1, 3). Pike awarded Tri-Krete a subcontract to complete architectural precast work for the Marist Project. (Id. at ¶ 4; see Dkt. 29-1 at ¶¶ 2-3). The parties executed a Master Subcontract Agreement and a Work Order, dated October 2, 2015, and June 14, 2016, respectively (collectively, the "Subcontract"), which governed their relationship as it related to the Marist Project. (Dkt. 9-2 at ¶ 4; see Dkt. 11).
The Subcontract "required payment applications to be submitted by uploading the application to an online invoicing system called Textura." (Dkt. 29-1 at ¶ 9; see Dkt. 9-2 at ¶ 9; see also Dkt. 11 at 30 ("Unless otherwise directed or authorized, in writing, by Contractor, all Applications for Payment and supporting documents for Subcontractor and its sub-subcontractors and suppliers, shall be in electronic format and shall be submitted to Contractor using the Textura Payment Management System....") ). Pike needed to make the Textura system accessible every month so that Tri-Krete could submit the required payment application by the 25th day of that month. (See Dkt. 29-1 at ¶ 9; see Dkt. 9-2 at ¶ 9). According to Pike, "[s]ubcontractors submit 'pencil copies' of their payment applications via Textura," which then generate electronic reports. (Dkt. 9-2 at ¶ 9). Once submitted, "[t]he pencil copy is reviewed by Pike," and "[i]f appropriate, the pencil copy is approved in the system." (Id. ). Pike would also notify Tri-Krete if the "invoice require[d] any modification." (Dkt. 11 at 30; see Dkt. 29-1 at ¶ 9).
According to Tri-Krete's Vice President, Adam Bombini ("Bombini"), the company submitted Payment Application 12 ("App 12") and Payment Application 13 ("App 13") to the Textura system on June 24, 2017, and July 22, 2017, respectively. (See Dkt. 29-1 at ¶¶ 11, 25). Bombini states that Pike never asked for additional information nor did it expressly reject App 12 or App 13. (Id. at ¶¶ 11-12, 26-27).
*269Pike's Project Director, Daniel L. DeCarlo ("DeCarlo"), and Pike's Senior Project Manager, Gloria Ciminelli ("Ciminelli"), dispute the veracity of these submission dates, and instead they contend that App 12 and App 13 were both submitted on July 19, 2017. (Dkt. 9-2 at ¶ 10; Dkt. 34-1 at ¶ 15). Furthermore, DeCarlo also states that on July 24, 2017, Pike informed Tri-Krete that it was in default of certain obligations under the Subcontract, and that Pike was incurring "significant expenses and damages that exceeded Tri-Krete's pending payment application." (Dkt. 9-2 at ¶ 11; see Dkt. 10-5).1 In addition, DeCarlo refers to email communications, taking place between August 3, 2017, and August 4, 2017, in which he demanded that Bombini "immediately deliver a detailed accounts receivable/payable report for all Tri-Krete sub-subcontractors, vendors and suppliers, including documentation showing any unpaid cost liabilities related to Tri-Krete's performance." (Dkt. 9-2 at ¶ 12). DeCarlo insists that due to "the pending notices of default" and his unsatisfied demand for certain documentation, Tri-Krete "was clearly on notice that its payment application No. 12 was not approved and was disputed." (Id. at ¶ 13).
After July 2017, the parties apparently abandoned the Textura invoicing system. According to Bombini, Pike "locked Tri-Krete out of Textura so Tri-Krete could not submit [invoices 8880, 8893, 8894, 8915, and 8916] via Textura." (Dkt. 29-1 at ¶ 102). According to Ciminelli, Tri-Krete "was not issued an invitation through Textura to submit further payment applications" due to Tri-Krete's "continued defaults, its failure to provide requested information, the unapproved status [of App 12 and App 13], and Pike's resulting damages." (Dkt. 34-1 at ¶ 16). DeCarlo also avers that "Pike has no record of ever having received" invoices 8880, 8893, 8894, 8915, or 8916 in 2017, and that, in any event, "these invoices were not the form of payment application used on the Project, do not include all of the necessary documentation to establish Tri-Krete's entitlement to payment, and do not constitute proper payment applications under the terms of the Subcontract." (Dkt. 9-2 at ¶ 17).
Between May 9, 2017, and September 12, 2017, Tri-Krete submitted approximately 20 requests for contract revisions to Pike, asking for Pike to issue a "change order" modifying the Subcontract due to additional work completed by Tri-Krete. (See Dkt. 29-1 at 8-20). During this period, Tri-Krete received a letter from Pike, dated August 25, 2017, which denied contract revision numbers 005, 006, 007, 008, 010, and 018 (as it pertained to "Credit for UCP/Slaw Panels"). (Dkt. 32-17; see Dkt. 29-1 at ¶ 48). According to Bombini, Tri-Krete received no other correspondence rejecting any of the requests for contract revisions. (See Dkt. 29-1 at ¶ 101). It also appears that Tri-Krete memorialized its request for these contract revisions in a single invoiced submission, dated December 7, 2017, and identified as invoice number 8946. (Dkt. 32-34; see Dkt. 29-1 at ¶ 98). On behalf of Pike, DeCarlo contends that these contract revisions "are unapproved change order requests and claims that have been denied by Pike as untimely, unsupported and barred by the terms of *270the Subcontract," and these claims "do not constitute proper and approved payment applications under Tri-Krete's Subcontract." (Dkt. 9-2 at ¶¶ 19-20; see also Dkt. 34-1 at (Cimminelli averring that by December 7, 2017, "Tri-Krete was well aware ... that [Pike] had rejected, expressly or by the terms of the [S]ubcontract, each of the requests for change order listed" in invoice number 8946) ).
PROCEDURAL HISTORY
On April 20, 2018, Pike commenced this action alleging breach of the parties' Subcontract. (Dkt. 1).
Free access — add to your briefcase to read the full text and ask questions with AI
ELIZABETH A. WOLFORD, United States District Judge *268INTRODUCTION
Plaintiff The Pike Company ("Pike") commenced this action on April 20, 2018, against Defendant Tri-Krete Limited ("Tri-Krete") for breach of contract. (Dkt. 1). On June 25, 2018, Tri-Krete filed an Answer, denying all material allegations in the Complaint and setting forth various affirmative defenses. (Dkt. 5). Tri-Krete also asserted several counterclaims against Pike, which included common law causes of action for breach of contract and unjust enrichment, and violations of the New York Prompt Payment Act, N. Y. Gen. Bus. Law §§ 756 - 758 ("PPA"). (Id. at 4-7).
Contemporaneously with the filing of its Answer, Tri-Krete filed a motion to stay this action and to compel arbitration based upon the alleged PPA violations. (Dkt. 7). Within the days thereafter, Pike responded with a motion to stay arbitration. (Dkt. 9). Pike subsequently filed a motion for a preliminary injunction, seeking to enjoin the arbitration proceedings. (Dkt. 22). For the following reasons, Tri-Krete's motion to stay this action and compel arbitration (Dkt. 7) is granted, Pike's motion to stay arbitration (Dkt. 9) is denied, and Pike's motion for a preliminary injunction (Dkt. 22) is denied.
BACKGROUND
Pike served as the construction manager contractor with Marist College on a campus housing project located in Poughkeepsie, New York (the "Marist Project"). (Dkt. 9-2 at ¶¶ 1, 3). Pike awarded Tri-Krete a subcontract to complete architectural precast work for the Marist Project. (Id. at ¶ 4; see Dkt. 29-1 at ¶¶ 2-3). The parties executed a Master Subcontract Agreement and a Work Order, dated October 2, 2015, and June 14, 2016, respectively (collectively, the "Subcontract"), which governed their relationship as it related to the Marist Project. (Dkt. 9-2 at ¶ 4; see Dkt. 11).
The Subcontract "required payment applications to be submitted by uploading the application to an online invoicing system called Textura." (Dkt. 29-1 at ¶ 9; see Dkt. 9-2 at ¶ 9; see also Dkt. 11 at 30 ("Unless otherwise directed or authorized, in writing, by Contractor, all Applications for Payment and supporting documents for Subcontractor and its sub-subcontractors and suppliers, shall be in electronic format and shall be submitted to Contractor using the Textura Payment Management System....") ). Pike needed to make the Textura system accessible every month so that Tri-Krete could submit the required payment application by the 25th day of that month. (See Dkt. 29-1 at ¶ 9; see Dkt. 9-2 at ¶ 9). According to Pike, "[s]ubcontractors submit 'pencil copies' of their payment applications via Textura," which then generate electronic reports. (Dkt. 9-2 at ¶ 9). Once submitted, "[t]he pencil copy is reviewed by Pike," and "[i]f appropriate, the pencil copy is approved in the system." (Id. ). Pike would also notify Tri-Krete if the "invoice require[d] any modification." (Dkt. 11 at 30; see Dkt. 29-1 at ¶ 9).
According to Tri-Krete's Vice President, Adam Bombini ("Bombini"), the company submitted Payment Application 12 ("App 12") and Payment Application 13 ("App 13") to the Textura system on June 24, 2017, and July 22, 2017, respectively. (See Dkt. 29-1 at ¶¶ 11, 25). Bombini states that Pike never asked for additional information nor did it expressly reject App 12 or App 13. (Id. at ¶¶ 11-12, 26-27).
*269Pike's Project Director, Daniel L. DeCarlo ("DeCarlo"), and Pike's Senior Project Manager, Gloria Ciminelli ("Ciminelli"), dispute the veracity of these submission dates, and instead they contend that App 12 and App 13 were both submitted on July 19, 2017. (Dkt. 9-2 at ¶ 10; Dkt. 34-1 at ¶ 15). Furthermore, DeCarlo also states that on July 24, 2017, Pike informed Tri-Krete that it was in default of certain obligations under the Subcontract, and that Pike was incurring "significant expenses and damages that exceeded Tri-Krete's pending payment application." (Dkt. 9-2 at ¶ 11; see Dkt. 10-5).1 In addition, DeCarlo refers to email communications, taking place between August 3, 2017, and August 4, 2017, in which he demanded that Bombini "immediately deliver a detailed accounts receivable/payable report for all Tri-Krete sub-subcontractors, vendors and suppliers, including documentation showing any unpaid cost liabilities related to Tri-Krete's performance." (Dkt. 9-2 at ¶ 12). DeCarlo insists that due to "the pending notices of default" and his unsatisfied demand for certain documentation, Tri-Krete "was clearly on notice that its payment application No. 12 was not approved and was disputed." (Id. at ¶ 13).
After July 2017, the parties apparently abandoned the Textura invoicing system. According to Bombini, Pike "locked Tri-Krete out of Textura so Tri-Krete could not submit [invoices 8880, 8893, 8894, 8915, and 8916] via Textura." (Dkt. 29-1 at ¶ 102). According to Ciminelli, Tri-Krete "was not issued an invitation through Textura to submit further payment applications" due to Tri-Krete's "continued defaults, its failure to provide requested information, the unapproved status [of App 12 and App 13], and Pike's resulting damages." (Dkt. 34-1 at ¶ 16). DeCarlo also avers that "Pike has no record of ever having received" invoices 8880, 8893, 8894, 8915, or 8916 in 2017, and that, in any event, "these invoices were not the form of payment application used on the Project, do not include all of the necessary documentation to establish Tri-Krete's entitlement to payment, and do not constitute proper payment applications under the terms of the Subcontract." (Dkt. 9-2 at ¶ 17).
Between May 9, 2017, and September 12, 2017, Tri-Krete submitted approximately 20 requests for contract revisions to Pike, asking for Pike to issue a "change order" modifying the Subcontract due to additional work completed by Tri-Krete. (See Dkt. 29-1 at 8-20). During this period, Tri-Krete received a letter from Pike, dated August 25, 2017, which denied contract revision numbers 005, 006, 007, 008, 010, and 018 (as it pertained to "Credit for UCP/Slaw Panels"). (Dkt. 32-17; see Dkt. 29-1 at ¶ 48). According to Bombini, Tri-Krete received no other correspondence rejecting any of the requests for contract revisions. (See Dkt. 29-1 at ¶ 101). It also appears that Tri-Krete memorialized its request for these contract revisions in a single invoiced submission, dated December 7, 2017, and identified as invoice number 8946. (Dkt. 32-34; see Dkt. 29-1 at ¶ 98). On behalf of Pike, DeCarlo contends that these contract revisions "are unapproved change order requests and claims that have been denied by Pike as untimely, unsupported and barred by the terms of *270the Subcontract," and these claims "do not constitute proper and approved payment applications under Tri-Krete's Subcontract." (Dkt. 9-2 at ¶¶ 19-20; see also Dkt. 34-1 at (Cimminelli averring that by December 7, 2017, "Tri-Krete was well aware ... that [Pike] had rejected, expressly or by the terms of the [S]ubcontract, each of the requests for change order listed" in invoice number 8946) ).
PROCEDURAL HISTORY
On April 20, 2018, Pike commenced this action alleging breach of the parties' Subcontract. (Dkt. 1). By letter dated May 8, 2018, Tri-Krete notified Pike of various alleged violations of the PPA. (Dkt. 7-5). Tri-Krete asserted, among other things, that Pike had "unreasonably withheld approval" of App 12, App 13, invoice numbers 8880, 8893, 8894, 8915, and 8916, and all requested contract revisions, and that Pike had "failed to give Tri-Krete a written notice of withholding specifying conditions for withholding payment and identifying the amount to be withheld." (Id. at 1). Tri-Krete also expressed its intention to refer the matter to the American Arbitration Association ("AAA") for expedited arbitration if the parties could not resolve the purported violations within 15 days of Pike's receipt of the letter. (Id. at 1-2). Tri-Krete filed a Demand for Arbitration with the AAA on June 11, 2018, and notified Pike the next day. (Dkt. 7-6).
On June 25, 2018, Tri-Krete filed its Answer in this action, denying all material allegations in the Complaint, setting forth various affirmative defenses, and asserting several counterclaims against Pike, which included causes of action for breach of contract, unjust enrichment, and violation of the PPA. (Dkt. 5). On the same day, Tri-Krete filed the pending motion to stay this action and to compel arbitration of its PPA claims. (Dkt. 7). On July 7, 2018, Pike filed the pending motion to stay arbitration (Dkt. 9), arguing that the PPA's arbitration provision did not apply to Tri-Krete's claims (Dkt. 9-1). On August 29, 2018, Pike filed a motion for a preliminary injunction, requesting that the Court enjoin any further arbitration proceedings. (Dkt. 22). Each party opposed the other's respective motions. (See Dkt. 14; Dkt. 15; Dkt. 25).
On September 19, 2018, the Court heard oral argument. (Dkt. 27; Dkt. 28). The Court requested further submissions; Tri-Krete filed an affidavit with additional exhibit submissions on October 2, 2018 (Dkt. 29; Dkt. 32; Dkt. 33), and Pike filed two responsive affidavits and associated exhibits on October 15, 2018 (Dkt. 34). A telephone status conference was held on October 17, 2018 (Dkt. 37), and on October 25, 2018, Pike filed a further affidavit and letter (Dkt. 38).
DISCUSSION
I. Pike's Motion for a Preliminary Injunction
A. Legal Standard
In order to obtain a preliminary injunction, the moving party must establish the following: (1) a likelihood of irreparable harm absent preliminary relief; (2) a likelihood of success on the merits; (3) the balance of equities tipping in favor of the moving party; and (4) the public interest is served by an injunction. See Winter v. Nat. Res. Def. Council, Inc. ,
*271Citigroup Glob.Mkts., Inc. v. VCG Special Opportunities Master Fund Ltd. ,
B. Irreparable Harm
The most important prerequisite to issuing a preliminary injunction is irreparable harm. Faiveley Transp. Malmo AB v. Wabtec Corp. ,
C. Likelihood of Success on the Merits
"The typical preliminary injunction is prohibitory and generally seeks only to maintain the status quo pending a trial on the merits. A mandatory injunction, in contrast, is said to alter the status quo by commanding some positive act." Tom Doherty Assocs., Inc. v. Saban Entm't, Inc. ,
D. Pike's Motion for a Preliminary Injunction Hinges Upon the Arbitrability of Tri-Krete's Claims
Pike argues that "[c]ourts often find irreparable harm where the moving party is seeking to stay an imminent arbitration where the arbitrability of the dispute is in question." (Dkt. 22-3 at 3). Pike finds support for this proposition in Md. Casualty Co. v. Realty Advisory Bd. On Labor Relations ,
In opposition, Tri-Krete relies upon Emery Air Freight Corp. v. Local Union 295 ,
In both Emery Air and Maryland Casualty , the Second Circuit first analyzed whether the relevant claims were arbitrable. In Maryland Casualty , the court determined that the claims were not arbitrable.
By comparison, the Emery Air court first determined that the issues were arbitrable.
Consistent with Emery Air and Maryland Casualty , the Court will determine whether the parties' disputes are arbitrable before deciding whether irreparable harm exists. See Int'l Bhd. of Elec. Workers ,
Thus, the issue of arbitrability is central to the Court's disposition of each pending motion. Although Pike may not have formally agreed to arbitrate the alleged PPA violations, that fact is irrelevant where the parties are subject to a compulsory arbitration provision set forth in a state statute. However, the scope of the PPA's arbitration provision will influence the arbitrability of Tri-Krete's claims. Accordingly, the Court must first address the PPA's arbitration provision and the arbitrability of Tri-Krete's PPA claims before ruling upon Pike's motion for a preliminary injunction.
E. The Arbitrability of Tri-Krete's PPA Claims
1. The PPA's Requirements and Arbitration Remedy
The Court's research has revealed only a limited number of state and federal opinions interpreting the PPA, and virtually no case law describing the scope of the PPA's arbitration provision in any depth. As such, the Court begins its analysis with the statutory text.
The purpose of the PPA is "to expedite payment of all monies owed to those who perform contracting services pursuant to construction contracts."
The contractor['s] ... payment of subcontractor or material supplier's interim or final invoice shall be made on the basis of a duly approved invoice of the work performed and materials supplied during the billing cycle.
Upon receipt of written notice of a complaint... that a contractor has violated the provisions of this article ... [or] where a subcontractor alleges a contractor has violated the provisions of this article[,] ... the parties shall attempt to *274resolve the matter giving rise to such complaint.
If the parties cannot reach a mutually agreeable resolution, "the aggrieved party may refer the matter, not less than fifteen days of the receipt of third party verification of delivery of the complaint, to the American Arbitration Association for an expedited arbitration pursuant to the Rules of the American Arbitration Association."
2. The Subcontract's Dispute Resolution Clause
A preliminary issue that the Court must address is whether the Subcontract provides Pike with the option of avoiding the PPA's arbitration requirements. Pike argues that the dispute resolution process set forth in the parties' Subcontract provides Pike with "the right to reject arbitration and to commence litigation if it chose to do so." (Dkt. 26 at 11). The Subcontract expressly provides Pike with the option of accepting or rejecting any demand for arbitration for "[a]ll claims, disputes and other matters in question between [Tri-Krete] and [Pike] arising out of or related to the Subcontract...." (Dkt. 11 at 60-61; see
In support of its position, Pike relies upon Turner Constr. Co. v. J & A Concrete Corp. ,
The Turner court's reasoning is fundamentally flawed because it failed to address § 757 of the PPA. Section 757 voids any "provision, covenant, clause or understanding in, collateral to or affecting a construction contract stating that expedited arbitration as expressly provided for and in the manner established by section seven hundred fifty-six-b of this article is unavailable to one or both parties."
By contrast, the Third Department's subsequent decision in the case of In re Arbitration between Capital Siding & Constr., LLC ,
Here, the dispute resolution procedure set forth in Section 11.9 of the Subcontract empowers Pike with the sole authority to elect whether to proceed with arbitration or litigation. (See Dkt. 11 at 60-61). Pike argues that Capital Siding is distinguishable because the provision at issue in that case mandated that any dispute related to the parties' agreement be resolved through litigation in all circumstances, whereas the instant provision permits Tri-Krete to demand arbitration and only vests Pike with the authority to elect or decline to proceed to arbitration. (See Dkt. 26 at 11 (arguing that the Subcontract merely provides "for the progression of disputes through mediation and then arbitration if Pike decides to proceed with arbitration," and it grants Pike "the right to reject arbitration and to commence litigation if it chose to do so") ). According to Pike, "there is nothing in the controlling Subcontract or Prime Contract that states that expedited arbitration under the Prompt Payment Act is unavailable to either party, or that would prevent Tri-Krete from demanding arbitration under the Prompt Payment Act had it satisfied the threshold requirements to demand expedited arbitration." (Id. ).
However, § 757 prohibits any contractual provision that causes the PPA's expedited arbitration remedy to become "unavailable to one or both parties."
As a result, insofar as Pike argues that the arbitration remedy is unavailable to Tri-Krete because of the Subcontract's dispute resolution clause, that clause is rendered void and unenforceable pursuant to § 757(3) of the PPA. Accordingly, the arbitration remedy set forth in § 756-b(3) of the PPA remains available to Tri-Krete for any alleged violation of the PPA.
3. The Scope of the PPA's Arbitration Provision
Having determined that Tri-Krete may invoke the PPA's arbitration procedures, the next issue becomes the scope of any such arbitration. The plain language of the PPA reveals its arbitration provision was broadly drafted in favor of arbitrability. Subsection three of § 756-b sets forth the PPA's arbitration remedy, see
Section 756-b(3) clearly outlines the necessary prerequisites that must be satisfied before seeking the benefit of the PPA's arbitration remedy. While there is little caselaw specifically interpreting this arbitration provision, the available decisional law supports the conclusion that a claim alleging a violation of the PPA is subject to arbitration so long as the prerequisites of § 756-b(3) have been satisfied.
In Capital Sidings , the court determined that the PPA's arbitration remedy may be raised when "a contractor is accused of violating any of the PPA's provisions."
Federal and state courts agree that "a defendant that did not respond to an invoice within the allotted twelve days" is not precluded from raising affirmative defenses or "present[ing] evidence that the invoiced amount was 'subject to various deductions for, inter alia, back charges, incorrect invoicing, and improper performance of the work.' " Layout, Inc. v. Heavy Metal Corp. , No. 16-CV-2531,
In other words, Pike's arguments against the applicability of the PPA raise various potential defenses to the alleged PPA violations and are thus, entwined with the merits of Tri-Krete's PPA claims. See generally Nat'l Union Fire Ins. Co. of Pittsburgh, Pa. v. Belco Petroleum Corp. ,
Indeed, if every time a demand for arbitration is made-in full satisfaction of the prerequisites for arbitration under § 756-b(3) -the resisting party may invoke substantive questions challenging the merits of the alleged violation before any arbitration may proceed, the laudatory objectives of the PPA, including "speedier resolutions" and reduced "time and funds wasted in litigation," would be undermined. See N.Y. Bill Jacket, 2009 A.B. 6493, Ch. 417. Furthermore, an extensive analysis by a court of whether the PPA has been violated, *278and any related affirmative defenses, would leave very little for an arbitration panel to resolve. It is doubtful that the state legislature contemplated that the AAA would play so minimal a role in resolving alleged PPA violations when the aggrieved party demands expedited arbitration.
In sum, the material question before this Court is whether the prerequisites of § 756b(3) have been satisfied. Pike does not dispute receipt of Tri-Krete's May 8, 2018, letter (Dkt. 9-2 at ¶ 7), which outlines various alleged PPA violations, including that Pike "unreasonably withheld approval" of App 12, App 13, invoices 8880, 8893, 8894, 8915, and 8916, and the requested contract revisions numbered one through twenty (Dkt. 7-5); see also
Therefore, Tri-Krete complied with the prerequisites of § 756-b(3) and any PPA violation alleged in the May 8, 2018, letter is properly before the AAA and should proceed to conclusion in the pending arbitration. Accordingly, Pike's motion for a preliminary injunction (Dkt. 22) is denied on the ground that the alleged PPA violations are arbitrable before the AAA panel, and thus, Pike has not demonstrated that irreparable harm will result from compelling continued arbitration proceedings. Furthermore, to the extent Tri-Krete's motion to compel arbitration seeks to arbitrate the alleged PPA violations now pending before the AAA (Dkt. 7), its motion is granted, and Pike's competing motion to stay that arbitration (Dkt. 9) is denied. Importantly, the Court's conclusion should not be interpreted as endorsing Tri-Krete's position that it is entitled to payment of any of the amounts asserted as due from Pike. As discussed in further detail below, the merits of Tri-Krete's claims and Pike's defenses to those claims must be evaluated, at least in the first instance, through arbitration.
4. Issues Not Subject to Arbitration
The Court pauses to emphasize that the only arbitrable claims-and the only claims referred to arbitration-are the alleged PPA violations set forth in the May 8, 2018, letter and encompassed by Tri-Krete's fourth counterclaim. (See Dkt. 5 at 6-7; Dkt. 7-5). To be sure, Tri-Krete's counterclaims for breach of contract, unjust enrichment, and unpaid labor and materials seek similar, if not identical, monetary relief as that which is sought by its fourth counterclaim. (See Dkt. 5 at 4-8). However, Tri-Krete's first, second, and third counterclaims are not subject to resolution in arbitration, as the AAA's authority to issue an arbitral award is limited to the "alleged violation" of the PPA. See
Pike's breach of contract cause of action is also not arbitrable. While Pike may argue to the AAA panel that Tri-Krete's purported breaches of the Subcontract represent defenses to its obligations under the PPA, the arbitral opinion and award should be based upon Pike's compliance or non-compliance with the PPA. In other words, the AAA panel is without jurisdiction to determine whether Pike has asserted a meritorious common law cause of action for breach of contract. This is so even if the AAA panel finds it necessary to determine whether Tri-Krete materially breached the Subcontract in order to resolve the alleged PPA violations.3
II. This Action Will be Staved Pending Arbitration
Having determined that some, but not all, of the claims before this Court are subject to arbitration, the Court must now decide whether to stay the balance of this matter pending the resolution of the arbitration. See JLM Indus., Inc. v. Stolt-Nielsen SA ,
Accordingly, "[t]he party seeking a stay must first demonstrate that 'there are issues common to the arbitration and the court proceeding,' and then show that 'those issues will be finally determined by arbitration.' " In re A2P SMS Antitrust Litig ,
"A discretionary stay is particularly appropriate where there is significant factual overlap between the remaining claims and the arbitrated claims." Winter Inv'rs, LLC v. Panzer , No. 14 Civ. 6852 (KPF),
Aside from arguing, in general, that a stay of this action would be in the interests of judicial economy (see Dkt. 7-2 at 7-8), Tri-Krete offers little reason for this Court to find a stay to be justified. Nonetheless, in the exercise of its discretion, the Court will stay this action for the following reasons. See Cosmotek Mumessillik Ve Ticaret Ltd. Sirkketi v. Cosmotek USA, Inc. ,
Pike's Complaint alleges a breach of contract cause of action arising from Tri-Krete's alleged default and breach of the Subcontract. (Dkt. 1). Whether Tri-Krete has breached the Subcontract raises an issue that is "common to the arbitration and the court proceeding" because Pike has raised this issue as a defense to its obligations under the PPA. (See, e.g. , Dkt. 9-1 at 7). Indeed, while the arbitration will not reach the merits of Pike's breach of contract claim, it may "finally determine" the factual issue of whether a breach of the Subcontract occurred in deciding whether Pike has a viable defense to the alleged PPA violations.
Tri-Krete has also asserted several counterclaims arising from Pike's alleged breaches of the Subcontract and alleged unjust enrichment derived from the labor and materials supplied by Tri-Krete. (Dkt. 5 at 4-6). The resolution of the alleged PPA violations may provide the Court with insight as to whether Pike failed to make payments owed to Tri-Krete pursuant to the billing cycle established under the Subcontract, and as such, could have significant bearing on at least some of Tri-Krete's non-arbitrable allegations. See Hikers Indus., Inc. v. William Stuart Indus. (Far E.) Ltd. ,
Accordingly, in light of the significant overlap among the issues to be decided in this action and those likely to be decided during arbitration, the Court concludes that a stay is appropriate. See Catlin Syndicate 2003 v. Traditional Air Conditioning, Inc. , No. 17-CV-2406 (JFB) (AYS),
In sum, the Court recognizes that the merits of the claims pending before it in this action have issues in common with the alleged PPA violations that must be resolved in arbitration. The significant overlap of these factual and legal issues warrants the issuance of a discretionary stay of this action.
CONCLUSION
For the foregoing reasons, Tri-Krete's motion to stay this action and compel arbitration (Dkt. 7) is granted, Pike's motion to stay arbitration (Dkt. 9) is denied, and Pike's motion for a preliminary injunction (Dkt. 22) is denied. The parties shall notify the Court within 15 days of a final arbitration decision. The Clerk of Court is directed to stay this matter until further order of the Court.
SO ORDERED.
Related
Cite This Page — Counsel Stack
349 F. Supp. 3d 265, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pike-co-v-tri-krete-ltd-nywd-2018.