Turkiye Ihracat Kredi Bankasi, A.S. v. Nature's Bakery, LLC

District Court, D. Nevada·Decided October 11, 2022·No. 3:20-cv-00330·Unknown

Opinion

3 UNITED STATES DISTRICT COURT

4 DISTRICT OF NEVADA

5 * * *

6 NATURE’S BAKERY, LLC, Case No. 3:20-cv-00330-MMD-EJY

7 Third Party Plaintiff and Counter Defendant, ORDER 8

9 v.

10 INTRANSIA, LLC,

11 Third Party Defendant and Counterclaimant. 12 13 I. SUMMARY 14 This is a commercial dispute about the fig paste that goes into Third-Party Plaintiff 15 and Counter Defendant Nature’s Bakery, LLC’s fig bars.1 The parties to this case have 16 mostly settled their claims against each other (ECF Nos. 129, 141), and the Court 17 granted Nature’s Bakery summary judgment on its sole claim for breach of contract 18 against Third Party Defendant and Counterclaimant Intransia, LLC (ECF No. 124 (“MSJ 19 Order”) at 14), but the Court has not yet entered judgment in Nature’s Bakery’s favor or 20 adjudicated Intransia’s counterclaims against Nature’s Bakery. Before the Court are two 21 motions: (1) Nature’s Bakery’s motion for entry of judgment under Federal Rule of Civil 22 Procedure 54(b) on its claim against Intransia (ECF No. 134 (“Nature’s Bakery’s 23 Motion”));2 and Intransia’s motion for leave to amend the scheduling order (ECF No. 143 24 (“Intransia’s Motion”)).3 Because the Court finds it would be more just and efficient to 25

1See, e.g., Nature’s Bakery, Whole Wheat Fig Bars (Last Visited Sept. 27, 2022), 26 https://www.naturesbakery.com/shop-snacks/whole-wheat-fig-bars.

27 2Intransia filed a response (ECF No. 135), and Nature’s Bakery filed a reply (ECF No. 136). 28 1 finally resolve all of Nature’s Bakery and Intransia’s overlapping claims against each 2 other at trial instead of proceeding in a piecemeal manner, and Intransia does not even 3 argue it has shown good cause to amend the scheduling order in its Motion—and as 4 further explained below—the Court will deny both motions and direct the parties to file 5 the joint pretrial order (“JPO”) they were supposed to file back in July (see ECF No. 125) 6 within 30 days. 7 II. BACKGROUND 8 The Court incorporates by reference the undisputed background facts it recited in 9 the MSJ Order. (ECF No. 124 at 2-7.) In the MSJ Order, the Court found that an 10 indemnification agreement between Nature’s Bakery and Intransia was valid, 11 enforceable, and Intransia had breached it. (Id. at 9-14.) The Court resolved the parties’ 12 competing motions for summary judgment accordingly. (Id. at 14.) The Court also 13 otherwise denied Intransia’s motion for summary judgment and informed Intransia that it 14 would have to file a motion seeking leave to amend the scheduling order if it wanted to 15 file another motion for summary judgment because the dispositive motions deadline 16 expired June 15, 2021. (Id. at 14-16 & n.14.) 17 Just after it entered the MSJ Order, the Court entered a minute order referring the 18 case for a settlement conference and ordering that the JPO was due 30 days after that 19 settlement conference. (ECF No. 125.) A couple of weeks later, but before any 20 settlement conference was held, Türkiye Ihracat Kredi Bankasi A.Ş. and Nature’s Bakery 21 settled their claims against each other. (ECF Nos. 128 (joint stipulation of dismissal), 129 22 (order granting that stipulation).) 23 Nature’s Bakery also filed its pending Motion before United States Magistrate 24 Judge Elayna J. Youchah held the settlement conference, but the Court did not rule on it 25 before Judge Youchah held that conference. Turkiye Ihracat Kredi Bankasi, A.S. and 26 Intransia settled their claims against each other at the settlement conference on June 9,

3Nature’s Bakery filed a response. (ECF No. 144.) 28 1 2022. (ECF No. 137; see also ECF No. 141 (order granting stipulation to dismiss filed 2 pursuant to the settlement agreement).) Following the settlement conference, Nature’s 3 Bakery and Intransia thus became the only parties with claims remaining against each 4 other. However, as the settlement conference was held on June 9 (ECF No. 137), that 5 also meant that the JPO was due within 30 days of June 9, 2022 (ECF No. 125). As of 6 the date of entry of this order, Nature’s Bakery and Intransia have not filed the JPO. 7 They accordingly violated the Court’s order. (Id.) Intransia also waited from the beginning 8 of February, when the Court issued the MSJ Order (ECF No. 124), until September to 9 file its Motion (ECF No. 143). 10 IV. DISCUSSION 11 Nature’s Bakery asks the Court to enter judgment in line with the MSJ Order, and 12 Intransia seeks leave to file another motion for summary judgment and stay the JPO 13 deadline until 30 days after the Court issues an order on that motion for summary 14 judgment. Neither party explicitly acknowledges that they missed the existing JPO 15 deadline. The Court first addresses Nature’s Bakery’s Motion, and then Intransia’s 16 Motion. 17 A. Nature’s Bakery’s Motion 18 Nature’s Bakery requests the Court enter judgment under Rule 54(b) because the 19 Court’s grant of summary judgment to it and against Intransia for breach of the 20 indemnification agreement constitutes a final judgment, and both the equities and judicial 21 administrative interests favor entering judgment now. (ECF No. 134.) Intransia counters 22 that granting Nature’s Bakery’s Motion could lead to overlapping, piecemeal appeals, the 23 judgment Nature’s Bakery seeks overlaps with Intransia’s counterclaims that have not 24 yet been resolved, and Nature’s Bakery does not argue that delaying entry of judgment 25 would result in any significant financial loss based on, for example, a difference in 26 interest rates. (ECF No. 135.) The Court agrees with Intransia in pertinent part. 27 “When an action presents more than one claim for relief ... the court may direct 28 entry of final judgment as to one or more, but fewer than all, claims or parties only if the 1 court expressly determines that there is no just reason for delay.” Fed. R. Civ. P. 54(b). 2 To enter judgment against a single claim, “the district court first must render ‘an ultimate 3 disposition of an individual claim.’” Pakootas v. Teck Cominco Metals, Ltd., 905 F.3d 4 565, 574 (9th Cir. 2018) (quoting Curtiss-Wright Corp. v. Gen. Elec. Co., 446 U.S. 1, 7 5 (1980)). Second, the district court must find there is “no just reason for delay.” Id. When 6 deciding what constitutes an individual claim, the Ninth Circuit takes “a pragmatic 7 approach” which focuses on whether the ostensibly multiple claims are separately 8 justiciable. Id. at 574-75. Under this approach, “[c]laims with partially ‘overlapping facts’ 9 are not ‘foreclosed from being separate for purposes of Rule 54(b).’” Id. at 575 (quoting 10 Wood v. GCC Bend, LLC, 422 F.3d 873, 881 (9th Cir. 2005)). District courts must use 11 their discretion to determine whether “judicial administrative interests” and “the equities 12 involved” are best served by severing the finally decided claims from those still pending. 13 Id. at 576 (quoting Curtiss-Wright, 466 U.S. at 8). However, when “an important and 14 controlling legal issue ... cuts across” or “curtails” both final and non-adjudicated claims, 15 the Ninth Circuit has found certification to appeal appropriate. Wood, 422 F.3d at 881. 16 To start, the Court makes three initial observations. First, neither party disputes 17 that the Court’s MSJ Order is a final order as to Nature’s Bakery’s sole claim against 18 Intransia. And the Court agrees it is. Indeed, the Court found in the MSJ Order that the 19 pertinent indemnification agreement is valid, enforceable, and Intransia breached it. 20 (ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Turkiye Ihracat Kredi Bankasi, A.S. v. Nature's Bakery, LLC, (D. Nev. 2022).

Turkiye Ihracat Kredi Bankasi, A.S. v. Nature's Bakery, LLC (Turkiye Ihracat Kredi Bankasi, A.S. v. Nature's Bakery, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Curtiss-Wright Corp. v. General Electric Co.
446 U.S. 1 (Supreme Court, 1980)
Learjet, Inc. v. Oneok, Inc.
715 F.3d 716 (Ninth Circuit, 2013)
Oneok, Inc. v. Learjet, Inc.
575 U.S. 373 (Supreme Court, 2015)