TTCP Energy Finance Fund II, LLC v. Ralls Corp.

255 F. Supp. 3d 1285, 2017 U.S. Dist. LEXIS 83659
CourtDistrict Court, N.D. Georgia
DecidedJune 1, 2017
DocketCIVIL ACTION FILE NO. 1:16-cv-3287-TCB
StatusPublished
Cited by3 cases

This text of 255 F. Supp. 3d 1285 (TTCP Energy Finance Fund II, LLC v. Ralls Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TTCP Energy Finance Fund II, LLC v. Ralls Corp., 255 F. Supp. 3d 1285, 2017 U.S. Dist. LEXIS 83659 (N.D. Ga. 2017).

Opinion

ORDER

Timothy C. Batten, Sr., United States District Judge

This case comes before the Court on the joint motion to dismiss filed by Defendants Ralls Corporation and Sany America, Inc. [24].1

I. Factual Background2

This lawsuit arises from Plaintiff TTCP Energy Finance Fund II, LLC’s purchase of a wind-power generation project located in Huei'fano County, Colorado. The project was conceptualized and initially owned and managed by Christine, Daniel, and Darren Schaefer, who jointly owned New Centennial Power, LLC. On March 22, 2013, U.S. Innovative Renewable Energy (“USIRE”) purchased New Centennial Power from the Schaefer family. On that same date, New Centennial entered into a loan agree.ment with Defendant Ralls pursuant to which Ralls provided the capital to construct the project and was engaged to serve as the primary builder and general contractor of the project. The project became operational in October 2013.

In late 2013 and early-to-mid-2014, it became clear to Ralls that New Centennial — which had been renamed Huerfano River Wind, LLC (“HRW”) — had defaulted or would default on the loan agreement, so Ralls began to seek additional debt financing for the project. Ralls advertised the project to various potential investors, including Plaintiff TTCP, a renewable-energy investment fund. In so doing, Ralls used marketing materials that were -developed by Defendants Sany America, Sany Electric, Sany Group, and Sany Heavy Energy Machinery (collectively, • the “Sany Defendants”) for the specific purpose of attracting investors.

The Sany Defendants’ marketing.materials specifically touted the project’s production capacity. In mid-2014, however, TTCP learned that the project’s actual production capacity was lower than represented. When TTCP questioned Ralls about this discrepancy, Ralls sought to reassure TTCP that the actual capacity was* even greater than represented in the Sany marketing materials but that the 2014 production capacity had been intentionally curtailed due to USIRE’s/HRW’s default under the loan agreement. In September 2014, based' on Ralls’s representations and reassurances, TTCP purchased the project by acquiring USIRE’s interest in HRW.

TTCP quickly came- to suspect that Defendants had exaggerated the project’s production capacity to induce TTCP’s acquisition of the project. By the end of 2014, the project’s- actual production numbers were significantly below those contained in the Sany marketing materials- and in Ralls’s reassurances in mid-2014. In early 2015, TTCP repeatedly asked Ralls for an updated analysis or explanation of the project’s performance. Ralls ignored TTCP’s requests for extended time periods, and when it finally did respond,-it changed its story regarding production shortfalls.

[1288]*1288Prior to TTCP’s investment in the project, Ralls had indicated that the poor performance resulted from an intentional effort to curb production because of USIRE’s/HRW’s breach of the loan agreement and a lack of incentive to attend to problems in a timely manner. After TTCP purchased the project and pressed Ralls for an explanation for the continuing poor performance, Ralls admitted that the problem was a lack of wind at the project site. In April 2016, Defendants produced a Sany-branded analysis that revised production capabilities to less than what was contained in the initial-marketing materials, but still more than the actual production numbers that had been achieved in 2015. Frustrated by Defendants’ inconsistent reports, TTCP commissioned its own independent analysis that confirmed that the project’s production capacity was between as much as thirty-two percent less than Defendants had forecasted.

In addition to being party to the misx-ep-resentations that led TTCP to invest in the project, Ralls is also alleged to have failed in its obligations to maintain and operate the project as it promised it would, both before and after TTCP’s acquisition, as detailed in the amended complaint. See [19] at ¶¶ 35-52. In July 2016, moreover, Ralls curtailed the project for three weeks, contrary to TTCP’s instructions, causing the project to be further devalued. TTCP .avers that as a result of Defendants’ conduct, the project is significantly less valuable than it would be if its production capacity were as advertised and if it had .been properly maintained and operated.

Based on these averments, TTCP brings claims against Ralls and the Sany Defendants for fraudulent inducement and negligent misrepresentation. It also asserts claims' against Ralls alone for breach of contract and breach of warranty (as to both the project’s production capabilities and Ralls’s maintenance obligations). TTCP seeks compensatory and punitive damages as well as an award of attorneys’ fees pursuant to O.C.G.A. § 13-6-11. Ralls and Sany America have moved to dismiss TTCP’s amended complaint for failure to state a claim.

II. Legal Standard

Rule 8(a)(2) of the Federal Rules of Civil Procedure requires that a complaint provide “a short and plain statement of the claim showing that the pleader is entitled to relief.” Chaparro v. Carnival Corp., 693 F.3d 1333, 1337 (11th Cir. 2012). This pleading standard does not require “detailed factual allegations,” but it does demand “more than an unadorned, the-defendant-unlawfully-harmed-me accusation.” Id. Under Rule 12(b)(6), a claim will be dismissed for failure to state a claim upon which relief can be granted if it does not plead “enough facts to state a claim to relief that is plausible on its face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 547, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007). The Supreme Court has explained this standard as follows:

A claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged. The plausibility standard is not akin to a “probability reiquirement,” but it asks for more than a sheer possibility that a defendant has acted unlawfully.

Ashcroft v. Iqbal, 556 U.S. 662, 678, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009) (internal citation omitted). Thus, a claim will survive a motion to dismiss only if the factual allegations in the pleading are “enough to raise a right to relief above the speculative level.” Twombly, 550 U.S. at 555, 127 S.Ct. 1955.

In addition to these generally applicable pleading standards, Rule 9(b) re[1289]*1289quires that a party alleging fraud or mistake “must state with particularity the circumstances constituting fraud or mistake.” This rule serves the dual purpose of ensuring that a complaint “alert[s] defendants to the precise misconduct with which they are charged and protecting defendants against spurious charges of immoral and fraudulent behavior.” Ziemba v. Cascade Int'l Inc., 256 F.3d 1194, 1202 (11th Cir. 2001) (internal punctuation omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
255 F. Supp. 3d 1285, 2017 U.S. Dist. LEXIS 83659, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ttcp-energy-finance-fund-ii-llc-v-ralls-corp-gand-2017.