Trytek v. Gale Industries, Inc.

997 So. 2d 365, 33 Fla. L. Weekly Supp. 945, 2008 Fla. LEXIS 2379, 2008 WL 5170586
CourtSupreme Court of Florida
DecidedDecember 11, 2008
DocketSC07-1641
StatusPublished

This text of 997 So. 2d 365 (Trytek v. Gale Industries, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trytek v. Gale Industries, Inc., 997 So. 2d 365, 33 Fla. L. Weekly Supp. 945, 2008 Fla. LEXIS 2379, 2008 WL 5170586 (Fla. 2008).

Opinion

997 So.2d 365 (2008)

Frank J. TRYTEK, et al., Petitioners,
v.
GALE INDUSTRIES, INC., etc., Respondent.

No. SC07-1641.

Supreme Court of Florida.

December 11, 2008.

*366 Michael R. D'Lugo of Wicker, Smith, O'Hara, McCoy, and Ford, P.A., Orlando, FL, for Petitioner.

Edward M. Baird and Mark T. Snelson of Wright, Fulford, Moorhead, and Brown, P.A., Orlando, FL, for Respondent.

Barry Kalmanson, Maitland, FL, on behalf of Southeastern Association of Credit Management and Florida Independent Concrete and Associated Products, Inc., for Amicus Curiae.

PARIENTE, J.

In Gale Industries, Inc. v. Trytek, 960 So.2d 805 (Fla. 5th DCA 2007), the Fifth District Court of Appeal ruled on statutory attorneys' fees in construction lien actions and certified a question of great public importance. We therefore have jurisdiction. See art. V, § 3(b)(4), Fla. Const. We rephrase the certified question as follows:

Where a lienor obtains a judgment against a property owner in an action to enforce a construction lien brought pursuant to section 713.29, Florida Statutes (2005), are trial courts required to apply the "significant issues" test articulated in Prosperi v. Code, Inc., 626 So.2d 1360 (Fla.1993), in determining which party, if any, is the "prevailing party" for the purpose of awarding attorneys' fees?

We answer the rephrased certified question in the affirmative and hold that trial courts are required to apply the "significant issues" test of Prosperi to evaluate entitlement to prevailing party attorneys' fees under section 713.29, even when the lienor obtains a judgment on the lien.[1] We *367 conclude that this Court has consistently approached the award of attorneys' fees in lien actions as being "tempered by equitable principles." Prosperi, 626 So.2d at 1363. In that regard, when applying Prosperi to the facts of a case, there is no mandatory requirement that the trial court determine that one party is the "prevailing party." We therefore quash the Fifth District's decision that held that the trial court is required to award the lienor "prevailing party" attorneys' fees if the lienor recovers a judgment in any amount on the lien claim that exceeds any setoff or damages claimed by the homeowner on his or her counterclaim.

FACTS AND PROCEDURAL HISTORY

In this case, the petitioners, Frank J. Trytek and his wife, Cathy L. Trytek, (hereinafter referred to as either "Trytek" or "homeowner"), were building a new residence. As part of the project, they contracted with Gale Industries, an insulation contractor, to install insulation throughout the structure (hereinafter referred to as either "Gale," "contractor," or "lienor"). It is undisputed that "[w]hile installing the insulation, Gale's employees inadvertently caused some staples to be driven through some previously installed electrical wires. The parties agreed that Try-Cor Electric Company, a corporation owned by Frank Trytek that was involved in electrical contracting, would make the necessary repairs." Gale Indus., 960 So.2d at 806. According to the invoice in the record, Trytek's cost incurred for the electrical repair work was $11,770, including a $250 building inspection fee. Trytek delivered a check to Gale for $736, which Trytek determined was the amount due on the contract work after setting off the inspection fee and repair work done by his company. Gale refused to accept Trytek's check and recorded a construction lien in the amount of $12,725, which did not include any offset for the damages it caused.

This case eventually proceeded to trial. As set forth in the Fifth District's opinion:

Early in the proceedings the parties stipulated that the Gale Industries claim of lien complied procedurally with the construction lien law, Chapter 713, Florida Statutes (2001), and that all notice requirements had been met. In addition, the parties agreed that the lien accurately stated the value of the labor, services and materials provided by Gale, subject only to the Trytek counterclaim. An agreed order was rendered that established that Gale's lien was procedurally sufficient; that no evidence would be necessary at trial on that issue; and that Gale Industries was entitled to recover the amount stated in the lien, less any damages proved by Mr. and Mrs. Trytek; and that the only issue to be resolved at trial was the value of the damages alleged in the counterclaim.
Following a nonjury trial, the trial court entered an order determining that the Tryteks were entitled to repair costs of $11,200. After setting off that figure against the agreed lien amount of $12,725, the net result was a judgment for $1,525 in favor of Gale Industries.
Thereafter, each party concluded that it was the "prevailing party" and filed cross-motions to tax attorneys' fees and costs pursuant to section 713.29, Florida Statutes (2005). After a hearing on the motions the trial court, while expressing some concern over this court's position on the definition of prevailing party in *368 the construction lien context, determined that it was required to apply the "significant issues" test set forth in Prosperi v. Code, Inc., 626 So.2d 1360 (Fla.1993), in order to award fees and costs properly. The court then found that the Tryteks were the prevailing party because the only real issue in the case was how much money should be set off against the Gale Industries lien, and the Tryteks primarily prevailed on their counterclaim.

Id.

In determining that Trytek was the prevailing party, the trial court reasoned:

There was never an issue about Gale performing the insulation work at the Tryteks residence nor was there ever an issue about whether Gale was entitled to payment for its work. Early in the case, there was an agreed order on Plaintiff's Motion for Partial Summary Judgment which recognized the validity and amount of Gales' [sic] lien. The real issue in the case was how much money should be setoff from the lien amount as compensation to the Tryteks for repairing the damage done by Gale during its installation of the insulation. The Tryteks prevailed on their counterclaim to the extent of almost extinguishing the Gale lien. It was this aspect of the case that required expert testimony, document production, document analysis and trial time. The Tryteks recovered $11,200 on their counterclaim. Gale only offered a discount of from $320 to $3200. Therefore, this Court finds that the Tryteks prevailed on the "significant issue" of this case and are the prevailing parties entitled to recover attorneys' fees and costs pursuant to § 713.29, F.S.

Gale Indus., Inc. v. Trytek, No. 48-2004-CA-7549, order at 4 (Fla. Orange County Cir. Ct. Dec. 13, 2005).

The parties stipulated to the amount of attorneys' fees and costs and thus the trial court entered an order awarding attorneys' fees of $55,982.00 and costs of $4,016.67 in favor of the homeowner, Trytek.[2] On appeal, the Fifth District recognized that this Court's decisions in Moritz v. Hoyt Enterprises, 604 So.2d 807 (Fla. 1992), and Prosperi v. Code, Inc., 626 So.2d 1360 (Fla.1993), modified the "prevailing party" rule by applying the "significant issues" test. However, it concluded that the "significant issues" test of Prosperi applies only where the contractor is unsuccessful in its lien foreclosure action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hensley v. Eckerhart
461 U.S. 424 (Supreme Court, 1983)
Willis Shaw Express, Inc. v. Hilyer Sod, Inc.
849 So. 2d 276 (Supreme Court of Florida, 2003)
KENMARK CONST., INC. v. Cronin
765 So. 2d 129 (District Court of Appeal of Florida, 2000)
Crane Co. v. Fine
221 So. 2d 145 (Supreme Court of Florida, 1969)
Grant v. Wester
679 So. 2d 1301 (District Court of Appeal of Florida, 1996)
United States v. Griffin-Moore Lumber Co.
62 So. 2d 589 (Supreme Court of Florida, 1953)
State Farm Fire & Cas. Co. v. Palma
629 So. 2d 830 (Supreme Court of Florida, 1993)
Pennington & Associates, Inc. v. Evans
932 So. 2d 1253 (District Court of Appeal of Florida, 2006)
Prosperi v. Code, Inc.
626 So. 2d 1360 (Supreme Court of Florida, 1993)
Moritz v. Hoyt Enterprises, Inc.
604 So. 2d 807 (Supreme Court of Florida, 1992)
Peter Marich & Associates, Inc. v. Powell
365 So. 2d 754 (District Court of Appeal of Florida, 1978)
KCIN, INC. v. Canpro Investments, Ltd.
675 So. 2d 222 (District Court of Appeal of Florida, 1996)
Brevard County Fair Ass'n, Inc. v. Cocoa Expo, Inc.
832 So. 2d 147 (District Court of Appeal of Florida, 2002)
Hollub Const. Co. v. Narula
704 So. 2d 689 (District Court of Appeal of Florida, 1997)
Poranski v. Millings
82 So. 2d 675 (Supreme Court of Florida, 1955)
Hutchinson v. Hutchinson
687 So. 2d 912 (District Court of Appeal of Florida, 1997)
Emery v. International Glass & Mfg., Inc.
249 So. 2d 496 (District Court of Appeal of Florida, 1971)
Gale Industries, Inc. v. Trytek
960 So. 2d 805 (District Court of Appeal of Florida, 2007)
Orix Capital Markets v. Park Avenue Assoc.
881 So. 2d 646 (District Court of Appeal of Florida, 2004)
Sanfilippo v. Larry Giacin Tile Co., Inc.
390 So. 2d 413 (District Court of Appeal of Florida, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
997 So. 2d 365, 33 Fla. L. Weekly Supp. 945, 2008 Fla. LEXIS 2379, 2008 WL 5170586, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trytek-v-gale-industries-inc-fla-2008.