Gale Industries, Inc. v. Trytek

960 So. 2d 805, 2007 WL 1789266
CourtDistrict Court of Appeal of Florida
DecidedAugust 3, 2007
Docket5D06-1569
StatusPublished
Cited by2 cases

This text of 960 So. 2d 805 (Gale Industries, Inc. v. Trytek) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gale Industries, Inc. v. Trytek, 960 So. 2d 805, 2007 WL 1789266 (Fla. Ct. App. 2007).

Opinion

960 So.2d 805 (2007)

GALE INDUSTRIES, INC., etc., Appellant,
v.
Frank J. TRYTEK and Cathy L. Trytek, Appellee.

No. 5D06-1569.

District Court of Appeal of Florida, Fifth District.

June 22, 2007.
Order Denying Rehearing and Granting Certification August 3, 2007.

Edward M. Baird and Mark T. Snelson, of Wright, Fulford, Moorhead & Brown, P.A., Orlando, for Appellant.

*806 Michael R. D'Lugo, of Wicker, Smith, O'Hara, McCoy, Graham & Ford, P.A., Orlando, for Appellee.

MONACO, J.

The appellant, Gale Industries, Inc., seeks review of a final order determining that the appellees, Frank J. Trytek and Cathy L. Trytek, were the prevailing parties for the purpose of the trial court's award of attorneys' fees pursuant to section 713.29, Florida Statutes (2005). Because we conclude that Gale Industries was the prevailing party in this construction lien foreclosure, we reverse.

Mr. and Mrs. Trytek were building a new residence. As part of that project, they contracted with Gale Industries, an insulation contractor, to provide insulation throughout the structure. While installing the insulation, Gale's employees inadvertently caused some staples to be driven through some previously installed electrical wires. The parties agreed that Try-Cor Electric Company, a corporation owned by Frank Trytek that was involved in electrical contracting, would make the necessary repairs. After Try-Cor finished its work the Tryteks delivered an invoice to Gale Industries for the purported cost of the repairs, which after some adjustments was in the final amount of $18,630. Gale Industries balked and declined to set off that amount from its bill because it thought that the cost was unreasonably high.

Eventually, Gale Industries recorded a construction claim of lien in the amount of $12,725 for the insulation work, and timely brought suit to foreclose the lien. Mr. and Mrs. Trytek counterclaimed for the $18,630 cost of the electrical repairs. Early in the proceedings the parties stipulated that the Gale Industries claim of lien complied procedurally with the construction lien law, Chapter 713, Florida Statutes (2001), and that all notice requirements had been met. In addition, the parties agreed that the lien accurately stated the value of the labor, services and materials provided by Gale, subject only to the Trytek counterclaim. An agreed order was rendered that established that Gale's lien was procedurally sufficient; that no evidence would be necessary at trial on that issue; and that Gale Industries was entitled to recover the amount stated in the lien, less any damages proved by Mr. and Mrs. Trytek; and that the only issue to be resolved at trial was the value of the damages alleged in the counterclaim.

Following a nonjury trial, the trial court entered an order determining that the Tryteks were entitled to repair costs of $11,200. After setting off that figure against the agreed lien amount of $12,725, the net result was a judgment for $1,525 in favor of Gale Industries.

Thereafter, each party concluded that it was the "prevailing party" and filed cross-motions to tax attorneys' fees and costs pursuant to section 713.29, Florida Statutes (2005). After a hearing on the motions the trial court, while expressing some concern over this court's position on the definition of prevailing party in the construction lien context, determined that it was required to apply the "significant issues" test set forth in Prosperi v. Code, Inc., 626 So.2d 1360 (Fla.1993), in order to award fees and costs properly. The court then found that the Tryteks were the prevailing party because the only real issue in the case was how much money should be set off against the Gale Industries lien, and the Tryteks primarily prevailed on their counterclaim. The court then awarded attorneys' fees of $55,982.00 and costs of $4,016.67 in favor of Mr. and Mrs. Trytek. Gale appeals.

*807 Section 713.29, Florida Statutes, which concerns attorneys' fees in construction lien cases, states that:

[I]n any action brought to enforce a lien or to enforce a claim against a bond under this part, the prevailing party is entitled to recover a reasonable fee for the services of her or his attorney for trial and appeal or for arbitration, in an amount to be determined by the court, which fee must be taxed as part of the prevailing party's costs, as allowed in equitable actions.

Historically, a contractor or subcontractor who recovered a judgment pursuant to a construction lien, even if it recovered less than the amount sought, would be entitled to attorney's fees as long as they recovered something. See K & M Elec. Supply, Inc. v. Moduplex Corp., 686 So.2d 717, 718 (Fla. 4th DCA 1997). That is to say, if the contractor obtained any monetary judgment pursuant to a Chapter 713 action, it would ordinarily be considered the prevailing party.

Fifteen years ago, however, the Florida Supreme Court determined in Moritz v. Hoyt Enterprises, 604 So.2d 807 (Fla. 1992), in a breach of contract context that the methodology to be used in deciding which party prevailed and was, therefore, entitled to receive an award of attorneys' fees, was the "significant issues" test. Using that test, the trial court is required to decide "which party has in fact prevailed on the significant issues tried before the court." Id. at 810.

Not long thereafter the high court addressed the effect of Moritz on the prevailing party language of section 713.29. In Prosperi, the case thoroughly considered by the trial court, the supreme court focused on this issue. There, a contractor filed a four-count complaint against the owner seeking damages for: (1) foreclosure of a mechanic's lien; (2) breach of contract; (3) quantum meruit; and (4) accounts stated. The owner counterclaimed for breach of contract based upon the filing by the contractor of untrue affidavits, the failure of the contractor to account, and the contractor's incomplete or negligent performance of the contract. Of critical importance for purposes of our analysis, however, is the fact that the trial court in Prosperi declined to grant relief on the claim for the construction lien because the contractor had submitted false interim affidavits. Instead, the trial court held that the contract was breached originally by the contractor because of its filing of false affidavits and because it inaccurately accounted to the owner. The end result was that the trial court found that $31,898.01 remained unpaid under the contract, but that the owner was entitled to a set-off of $14,588.95 for the cost of completion of the contract, for damages resulting from certain construction defects, and for other expenses incurred by the owner. The other two claims based on quantum meruit and accounts stated were then apparently disposed of without liability. The trial court then denied both the contractor's claim and the owner's claim for attorneys' fees. The owner appealed the denial of attorneys' fees, but the district court of appeal affirmed. The question of whether either party was entitled to attorneys' fees, however, was certified to the Florida Supreme Court.

Our Supreme Court began its analysis by discussing the "net judgment" rule. It indicated that:

[T]he net judgment rule comes into play when the claimant fails to foreclose a mechanic's lien but obtains a judgment for the underlying claim which exceeds any claim of the owner. As applied, the rule automatically precludes the owner from recovering attorney's fees under section 713.29. It has no relevance to an *808

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trytek v. Gale Industries, Inc.
3 So. 3d 1194 (Supreme Court of Florida, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
960 So. 2d 805, 2007 WL 1789266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gale-industries-inc-v-trytek-fladistctapp-2007.