TRW, Inc. v. United States

38 Cont. Cas. Fed. 76,508, 28 Fed. Cl. 155, 1993 U.S. Claims LEXIS 27, 1993 WL 135343
CourtUnited States Court of Federal Claims
DecidedApril 23, 1993
DocketNo. 92-198C
StatusPublished
Cited by2 cases

This text of 38 Cont. Cas. Fed. 76,508 (TRW, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TRW, Inc. v. United States, 38 Cont. Cas. Fed. 76,508, 28 Fed. Cl. 155, 1993 U.S. Claims LEXIS 27, 1993 WL 135343 (uscfc 1993).

Opinion

OPINION

ANDEWELT, Judge.

I.

In this government contract action, plaintiff, TRW, Inc., seeks to recover approximately $2.9 million in bid and proposal (B & P) costs that it incurred in preparing a bid proposal in response to the United States Internal Revenue Service’s (IRS) Request for Proposal No. IRS-89-038 (RFP), issued on September 29, 1989. The RFP covered an automated method of processing checks and forms designated as the Check Handling Enhancements and Expert Systems (CHEXS). Plaintiff submitted a proposal in response to the RFP but, after a series of negotiations with plaintiff, the IRS ultimately determined not to award a contract under the RFP requirements. Plaintiff contends that it is entitled to recover all of the B & P costs it incurred in preparing its CHEXS proposal because the IRS breached its contractual obligation to consider plain[157]*157tiff’s bid proposal fairly and honestly. This action is presently before the court on defendant’s motion for partial summary judgment. For the reasons set forth below, defendant’s motion is denied.2

II.

The genesis of the type of action involved herein, where an unsuccessful bidder on a federal contract seeks to recover its B & P costs in the United States Court of Federal Claims, is the Court of Claims decision in Heyer Products Co. v. United States, 135 Ct.Cl. 63, 69, 140 F.Supp. 409 (1956); see also Keco Industries, Inc. v. United States, 192 Ct.Cl. 773, 428 F.2d 1233 (1970). In Heyer, the court held that an implied-in-fact contract is created when a contractor submits a bid in response to a government bid solicitation, and that pursuant to this implied contract, the government is obliged to consider that bid fairly and honestly. The measure of damages potentially available for a breach of such an implied-in-fact contract is “the expense to which [the bidder] was put in preparing [its] bid.” 135 Ct.Cl. at 69.

In its motion for partial summary judgment, defendant contends that even assuming the IRS breached its contractual obligation to consider plaintiff’s proposal fairly and honestly, plaintiff nevertheless is precluded from recovering approximately $2.1 million of the approximately $2.9 million in B & P costs sought in its complaint. Defendant bases its motion on advance agreements plaintiff had entered with the United States Department of Defense (DoD). These agreements obliged the government to pay certain B & P costs incurred during the years 1990-92 by plaintiff’s Space and Defense Sector (TRW Space). Defendant contends that pursuant to these advance agreements, defendant already has paid plaintiff $2.1 million of the $2.9 million in CHEXS B & P costs plaintiff seeks in this action. As an alternative argument, defendant contends that even if the $2.1 million in CHEXS B & P costs had not been paid, in view of the advance agreements, plaintiff would receive an improper “windfall” if the government made any additional payments toward reimbursing this $2.1 million in costs. To comprehend defendant’s argument, it is necessary to understand the intricacies of these advance agreements.

III.

During the pertinent time period, the Secretary of Defense was obliged by statute to enter annual agreements with qualifying contractors that describe the manner and extent to which DoD would pay a contractor’s independent research and development (IR & D) and B & P costs for future years.3 The purpose of such agreements was to encourage contractors to engage in research and development activities.

Herein, plaintiff entered two advance agreements with DoD, one covering the year 1990 and the other covering the years 1991 and 1992. These agreements include almost all of TRW Space’s operations and oblige DoD to pay incurred IR & D and B & P costs (hereinafter B & P costs) up to a specified ceiling amount. The parties, in effect, arranged for the government to pay the sums owed plaintiff under these advance agreements through payments based on plaintiff’s General and Administrative (G & A) costs billed through existing government contracts. For each year, the parties adjusted the G & A expense rate used in these existing contracts so that by the end of the year, the total periodic payments to plaintiff for B & P costs would equal the ceiling amount contained in the applicable advance agreement. Since actual G & A [158]*158expenditures and B & P costs for a given year could only be estimated, the G & A rate was established on a provisional basis. The rate was subject to subsequent modification to assure that the total payments resulting from the G & A adjustment did not exceed the lower of (1) plaintiffs actual B & P costs and (2) the ceiling amount established in the applicable advance agreement.

In each of the years 1990-92, plaintiff received payments equal to the ceiling amounts set forth in the advance agreements but its actual B & P costs apparently far exceeded those ceilings. For each of these years, the following chart shows the established ceiling and amount paid pursuant to the applicable advance agreement, the B & P costs plaintiff allegedly incurred subject to the agreement, the amount of such costs incurred in excess of the ceiling (total uncompensated B & P costs), and the total amount of alleged B & P costs incurred by plaintiff on the CHEXS solicitation for that year.

1990 1991 1992

Amount Paid Up To The Ceiling $136,000,000 $177,500,000 $180,250,000

Total B & P Costs Incurred 170,390,000 195,514,000 not yet calculated

Uncompensated B & P Costs Incurred Above The Ceiling 34,390,000 18,014,000 not yet calculated

CHEXS B & P Costs Incurred 845,343 1,229,845 9,910

As the chart demonstrates, for 1990 and 1991, the amounts of uncompensated B & P costs far exceeded the total amounts of plaintiffs CHEXS B & P costs. For 1992, the total B & P costs incurred and the uncompensated B & P costs have not yet been calculated, but plaintiff maintains, and defendant does not now dispute, that the total uncompensated B & P costs for that year similarly exceeded plaintiffs CHEXS B & P costs.

IV.

Defendant has not contended that the B & P costs plaintiff incurred for the CHEXS solicitation had any material effect on the ceilings negotiated by the parties in the advance agreements. Therefore, for purposes of resolving defendant’s partial summary judgment motion, the court will assume that the ceilings contained in the advance agreements would have been the same had plaintiff never bid on CHEXS. In addition, as noted above, plaintiff’s actual B & P costs for each of the applicable years exceeded the ceilings by an amount greater than plaintiff’s B & P costs for CHEXS. Therefore, the court will similarly assume that had plaintiff not responded to the CHEXS RFP, and thereby not incurred any of the alleged CHEXS B & P costs, plaintiff would have received precisely the same total B & P payments under the advance agreements as it actually did for each of the years 1990-92.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,508, 28 Fed. Cl. 155, 1993 U.S. Claims LEXIS 27, 1993 WL 135343, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trw-inc-v-united-states-uscfc-1993.