Trumbull Corp. v. Ohio Dept. of Transp.

2011 Ohio 6863
CourtOhio Court of Claims
DecidedNovember 15, 2011
Docket2011-06943
StatusPublished

This text of 2011 Ohio 6863 (Trumbull Corp. v. Ohio Dept. of Transp.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trumbull Corp. v. Ohio Dept. of Transp., 2011 Ohio 6863 (Ohio Super. Ct. 2011).

Opinion

[Cite as Trumbull Corp. v. Ohio Dept. of Transp., 2011-Ohio-6863.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

TRUMBULL CORPORATION, et al., Case No. 2011-06943

Plaintiffs,

v. Judge Joseph T. Clark

OHIO DEPARTMENT OF TRANSPORTATION,

Defendant. DECISION

{¶1} Trumbull-Great Lakes-Ruhlin, a joint venture (TGR),1 filed a complaint alleging breach of contract and seeking both injunctive and declaratory relief against defendant, Ohio Department of Transportation (ODOT). On May 10, 2011, the court denied TGR’s motion for a temporary restraining order. A trial on the merits was held on July 7-8, 2011, and reconvened on August 10, 2011. {¶2} This case involves a $200 million public improvement project known as the I-71/I-670 Interchange Improvement Project. The award of a contract to design and build the project is subject to the competitive bidding laws of this state. The project is more than twice the size of any previous project completed by ODOT. {¶3} Given the scope of the project, the relatively small number of contractors capable of designing and building such an improvement, and the costs associated with developing and submitting a technical proposal, ODOT accepted proposals from three contractors who had been “short-listed” pursuant to a pre-qualification process which is

1 Plaintiffs shall be referred to collectively as TGR throughout this decision. Case No. 2011-06943 -2- DECISION

not at issue. Those three contractors were TGR, Kokosing Construction Co., Inc. (Kokosing), and Walsh Construction Company, Inc.2 {¶4} The process by which ODOT was to select the design/build team (DBT) is set forth in the numerous contract documents. In a nutshell, once the short-listed DBTs are selected, the next stage of the selection process requires the submission and review of each DBT’s “Technical Proposal.” The Technical Proposals from each of the three DBTs were to be reviewed and then scored by several teams of ODOT employees pursuant to a specialized, multi-faceted scoring system. Thereafter, the price proposals would be unsealed and ODOT would select the DBT whose total proposal represented the “best value” to the state.3 {¶5} A significant provision in the agreement states that any short-listed DBT that survives the rigorous bid process, but does not win a contract, is entitled to a bid stipend from ODOT of up to $500,000 in consideration for its participation.4 {¶6} On the day prior to the opening of the price proposals, TGR was notified by ODOT that its Technical Proposal had been deemed “non-responsive” and that the scoring of the proposal had ceased. As a result, TGR’s Technical Proposal was never

2 Kokosing’s motion to intervene in this case was denied. 3 Selection Criteria (SC) 3.3 states that “[t]he Director has final authority to determine the best interests of the department and may reject any or all Technical/Price Proposals.” 4 The relevant contract language concerning the award of the stipend is found in the Project Scope (PS) and provides as follows: “NEW NOTE - PAYMENT FOR PREPARATION OF RESPONSIVE PRELIMINARY DESIGN CONCEPT “Subject to the conditions listed in this note, the Department will provide a payment of $500,000 or the DBT’s [Design/Build Team] actual costs of preparing the responsive preliminary design concept, whichever is less, to each non-winning short-listed DBT. “* * * “By submitting its Technical Proposal for this Project, the DBT forms a contract and agreement for its technical proposal and conceptual design with the Department, the terms and conditions of which are outlined in the documents referenced in Revised Specification 105.04.” (Emphasis original.) given a cumulative score, its price proposal was never opened, and ODOT withheld TGR’s bid stipend. {¶7} The price proposals of the two surviving contractors were opened and Kokosing’s proposal was determined by ODOT to be the best value. A design/build contract has been executed and work has begun on the project.

BREACH OF CONTRACT {¶8} TGR alleges that ODOT violated the terms of the contract when it deemed TGR’s Technical Proposal non-responsive. According to TGR, its proposal should have been fully scored, its price proposal opened, and its bid considered along with the other two DBTs. TGR further alleges that even if it would not have been selected as the design/build contractor for the project, it was entitled to receive a $500,000 bid stipend. {¶9} The parties agree that the stipend is not payable to a DBT where the DBT’s Technical Proposal is non-responsive to the bid documents in a material respect. The relevant provision regarding “Responsiveness” is found at section 3.2 of ODOT’s Selection Criteria (SC) and it reads as follows: {¶10} “3.2 RESPONSIVENESS {¶11} “A Technical Proposal may be deemed non-responsive at the sole discretion of the Director if any of the following apply: {¶12} “1. The Technical Proposal fails to achieve a total score of at least 70 points; not including bonus points. {¶13} “2. The Technical Proposal receives a score of less than 60 percent of the available points in any one of the Evaluation Criteria (A through I) listed in Section 4.11. {¶14} “3. The Technical Proposal receives a score of less than 70 percent of the available points in three or more of the Evaluation Criteria listed in Section 4.1 (A through I). {¶15} “4. The Project Duration listed in the bidder’s Technical Proposal (see Section 4.13) is in excess of 183 weeks (42 months). {¶16} “5. The Technical Proposal does not respond to the bid documents in a material respect.” (Emphasis added.) Case No. 2011-06943 -4- DECISION

{¶17} TGR argues that the Director violated the parties’ agreement inasmuch as TGR’s Technical Proposal responds to the bid documents in all material respects. {¶18} According to both the contract documents admitted into evidence and the witness testimony, the decision to declare TGR’s Technical Proposal non-responsive was based upon ODOT’s determination that the proposal materially deviated from the Interchange Modification Study (IMS) and the Step 7 Engineering Plans (Step 7 Plans) such that the proposal represented a change to the “basic configuration.” {¶19} The Project Scope (PS) identifies the IMS and the Step 7 Plans as being part of the “basic configuration.” PS section 1.4 provides in relevant part: {¶20} “The Project Scope in its entirety along with elements of the Preliminary Engineering Plans, as indicated in this section, constitute the basic configuration. The design-build proposal shall be consistent with the basic configuration subject only to such changes as may have been approved by the Department in accordance with the Alternative Technical Concepts, as described in the Selection Criteria document. {¶21} “The following elements of the Preliminary Engineering Plans shall be considered as part of the basic configuration: {¶22} “* * * {¶23} “H. Interchange Modification Study documents, which include: {¶24} “1. Interchange Modification Study (revised July 26, 2010) (Appendix RD- 01A) {¶25} “2. Addendum to the Interchange Modification Study (August 13, 2010) (Appendix RD-01B) {¶26} “3. Appendices for the Interchange Modification Study (Appendix RD-02).” {¶27} ODOT’s conception of the basic design of the interchange is memorialized in the Step 7 Plans, and is depicted in the schematic drawing of the proposed interchange in the IMS.5 First and foremost, ODOT believed that the IMS and the Step 7 Plans required an interchange design whereby four lanes of traffic were to enter from the west.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Viviano v. CBS, INC.
597 A.2d 543 (New Jersey Superior Court App Division, 1991)
Samson Sales, Inc. v. Honeywell, Inc.
465 N.E.2d 392 (Ohio Supreme Court, 1984)
Haig v. Ohio State Board of Education
584 N.E.2d 704 (Ohio Supreme Court, 1992)
Lake Ridge Academy v. Carney
613 N.E.2d 183 (Ohio Supreme Court, 1993)
Smith v. Howard Johnson Co.
615 N.E.2d 1037 (Ohio Supreme Court, 1993)
Smith v. Howard Johnson Co., Inc.
1993 Ohio 229 (Ohio Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
2011 Ohio 6863, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trumbull-corp-v-ohio-dept-of-transp-ohioctcl-2011.