Troutman v. FMC Corp.

340 N.W.2d 581, 115 Wis. 2d 683, 1983 Wisc. App. LEXIS 3937
CourtCourt of Appeals of Wisconsin
DecidedOctober 26, 1983
Docket83-374
StatusPublished
Cited by4 cases

This text of 340 N.W.2d 581 (Troutman v. FMC Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Troutman v. FMC Corp., 340 N.W.2d 581, 115 Wis. 2d 683, 1983 Wisc. App. LEXIS 3937 (Wis. Ct. App. 1983).

Opinion

BROWN, J.

A roofing subcontractor, Rob Troutman, appeals from several rulings of the trial court which effectively dismissed FMC Corporation, the owner of the building in question, as a party to the action. At the base of this action is an attempt by Troutman to recover the contract price of $37,200 for work done on FMC’s roof by lien foreclosure. Although Troutman’s notice to FMC was defective, no determination was made by the trial court, pursuant to sec. 779.02(2) (e), Stats., as to whether the insufficiency of the notice misled or deceived FMC. Therefore, we reverse the trial court’s decision and remand the case for a hearing on this issue.

During 1981, FMC Corporation decided that its roof was in need of patchwork and repair. Charles Harp, the plant engineer for the manufacturing department, was put in charge of obtaining bids from area contractors for this job. Harp ultimately recommended a general contractor, TRC Co., operated by Richard Kreckel. Kreckel, in turn, hired the Troutman Roofing Company to do the roofing work. Troutman supplied all of the materials and labor for the job.

*685 Apparently, the relationship between Harp and Kreckel was a spurious one. Without FMC’s or Trout-man’s knowledge, Harp and Kreckel had agreed that Harp would recommend Kreckel’s company, and the two of them would split the profits.

Work on the roof was completed on or about November 9, 1981. FMC did pay TRC Co. for the work performed, but TRC Co. never paid Troutman the amount owed of $37,200. On December 1, Troutman met with another FMC employee (Harp was fired in October) to discuss payment. Troutman handed the employee a single copy of a “Notice of Intention to File Claim for Lien.” Another notice was received approximately one week later by registered mail.

Troutman instituted an action against Kreckel, Harp and FMC. Judgment was granted against Kreckel and Harp. With respect to the claims against FMC, 1 the trial court dismissed the mechanic’s lien foreclosure claim holding: (1) the notice Troutman had provided did not. meet the requirements of sec. 779.02 (2) (b), Stats., and (2) Troutman was not exempt from the notice requirement to preserve his lien rights. On charges that FMC was legally responsible for the fraudulent acts of Harp, the court granted summary judgment in favor of FMC. Finally, the court denied the plaintiff’s request to amend his pleadings to include a cause of action for the negligent hiring and retention of an employee by FMC.

The major thrust of Troutman’s appeal centers on the validity of his mechanic’s lien on FMC’s property. Our first inquiry is whether the notice Troutman gave FMC was sufficient under sec. 779.02(2) (b), Stats. We agree with the trial court that it was not.

*686 Section 779.02(2) (b), Stats., states that two signed copies of the notice shall be given within sixty days after first furnishing labor or materials. The notice must contain: (1) the date on which labor or materials were first furnished, and (2) the legal description, street address or other clear description of the real estate. Id. Troutman’s notice failed to give the date on which labor or materials were first furnished and is, therefore, defective.

Troutman is correct in his assertion that the form of the notice does not have to conform with the suggested statutory language. However, his notice failed to comply with a substantive requirement.

FMC argues that this failure to follow the requirements of sec. 779.02(2) (b), Stats., is fatal. This assertion is not entirely correct, however, Section 779.02(2) (e) explains the procedure to be followed where there is a deficiency in the notice. It states: “[i]f the owner . . . complains of any insufficiency of any notice, the burden of proof is upon the owner ... to show that he or she has been misled or deceived by the insufficiency.” It is clear from the record that the trial court did not consider whether the failure to give the date on which the labor or materials were first furnished in any. way deceived or misled FMC. Therefore, we remand the case back to the trial court for a hearing on the effect of the insufficiency of the notice. 2

If FMC does show the defective notice is prejudicial, 3 Troutman strongly asserts that the roofing work per *687 formed constitutes an “improvement” as defined in sec. 779.01(2) (c), Stats., and, therefore, is exempt from the notice requirement under sec. 779.02 (1) (c).

In ascertaining the limits of the scope of the word “improvement,” we must first look to the statutory-definition itself in sec. 779.01 (2) (c), Stats.

“Improve” or “improvement” includes any building, structure, erection, fixture, demolition, alteration, excavation, filling, grading, tiling, planting, clearing or landscaping which is built, erected, made or done on or to land for its permanent benefit. This enumeration is intended as an extension rather than a limitation of the normal meaning and scope of “improve” and “improvement.”

Nowhere in the statute is the word “repair” found.

The ordinary and accepted meaning of a word can be established by reference to a recognized dictionary. Department of Natural Resources v. Wisconsin Power & Light Co., 108 Wis. 2d 403, 408, 321 N.W.2d 286, 289 (1982). Webster’s Third New International Dictionary defines “repair” as “fix” or “to restore by replacing a part or putting together what is torn or broken.” This word is commonly used to describe a replenishing of the status quo.

A close look at the statutory descriptions reveals that an “improvement” is something more than a mere replenishing of the status quo. “Building, structure, erection, fixture, alteration, filling, tiling and planting” all connote an “adding on” or development of an integral part of a structure. “Demolition, grading, clearing and landscaping” describe a “tearing down” and “clearing away” of a structure or land. These words clearly go beyond a replenishing of the status quo.

*688 Troutman places heavy reliance on this court’s opinion of Sullivan Brothers, Inc. v. State Bank of Union Grove, 107 Wis. 2d 641, 321 N.W.2d 545 (Ct. App. 1982), which expressly approved a broad construction of the exemption statute to support his position that his work was an alteration of the roof. However, Troutman’s reliance on the Sullivan case is misplaced. This court in Sullivan held that the remodeling of a bank building was an alteration of the structure and, therefore, exempt as falling within the statutory definition of “improvement.” Id. at 645, 321 N.W.2d at 547. An alteration makes something significantly different without changing it into something else.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kox v. Center for Oral & Maxillofacial Surgery, S.C.
579 N.W.2d 285 (Court of Appeals of Wisconsin, 1998)
Murphy v. Droessler
525 N.W.2d 117 (Court of Appeals of Wisconsin, 1994)
McQuay-Perfex, Inc. v. Wisconsin Telephone Co.
381 N.W.2d 587 (Court of Appeals of Wisconsin, 1985)
Bob Ryan Leasing v. Sampair
371 N.W.2d 405 (Court of Appeals of Wisconsin, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
340 N.W.2d 581, 115 Wis. 2d 683, 1983 Wisc. App. LEXIS 3937, Counsel Stack Legal Research, https://law.counselstack.com/opinion/troutman-v-fmc-corp-wisctapp-1983.