Murphy v. Droessler

525 N.W.2d 117, 188 Wis. 2d 420, 1994 Wisc. App. LEXIS 1291
CourtCourt of Appeals of Wisconsin
DecidedOctober 20, 1994
Docket94-0061
StatusPublished
Cited by4 cases

This text of 525 N.W.2d 117 (Murphy v. Droessler) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murphy v. Droessler, 525 N.W.2d 117, 188 Wis. 2d 420, 1994 Wisc. App. LEXIS 1291 (Wis. Ct. App. 1994).

Opinion

VERGERONT, J.

Mark and Jean Murphy appeal from an order dismissing their action to obtain clear title on their newly constructed residence. The trial court granted the counterclaims of Paul Droessler, d/b/a Stoughton Masonry (Droessler), and Conco Concrete Construction, Inc. (Conco) for foreclosure of their construction liens on the property. The issue is whether Droessler and Conco properly served construction lien notices pursuant to § 779.02(2)(b), Stats. We conclude the notices did not meet the statutory requirements because they were not served on the Murphys by registered or certified mail, return receipt requested, and the construction liens are therefore invalid. Accordingly, we reverse the order of the trial court.

BACKGROUND

Most of the facts concerning the two claims for construction liens are not disputed. Schuchardt Construction Corporation (Schuchardt Construction) was the general contractor for the construction of the Murphys' new home. Droessler entered into a subcontract with Schuchardt Construction for the masonry work. Droessler delivered the first materials to the site on May 17,1991; first began work on June 4,1991; and last worked on the job on August 19, 1991. Droessler submitted three draw requests to Schuchardt Construction: one dated May 20, 1991, for $10,000; one dated June 19,1991, for $15,000; and one dated August 5,1991, for $29,136. On July 1,1991, Schuchardt Con *423 struction paid Droessler $15,000, and Droessler signed a partial waiver of construction lien (partial lien waiver) and a contractor's affidavit. This was the only draw Droessler received.

Conco entered into a subcontract with Schuchardt Construction for the concrete flatwork. The first materials and labor were supplied on May 10,1991, and the initial concrete work was completed on May 14, 1991, Conco was paid in full for this work on June 3,1991, at which time it executed a partial lien waiver and a contractor's affidavit. Conco began work on the second phase of the concrete flatwork on July 10, 1991. Additional work was agreed upon on August 6, 1991. This work was done between August 10 and August 14, 1991.

Upon becoming aware that Schuchardt Construction was not paying subcontractors, Conco obtained a post-office address for Jean Murphy from Schuchardt Construction. Conco sent a construction lien notice to that address by certified mail, return receipt requested, on September 3, 1991, but this was returned unclaimed. Conco again contacted Schuchardt Construction and learned that an address for Jean Murphy at 2842 Cimarron Trail, Madison, had just been obtained. Conco sent the same notice by certified mail, return receipt requested, to this address on September 9, 1991, and Ms. Murphy signed for this mailing on September 10, 1991.

Schuchardt Construction and its principal, Michael Schuchardt, each filed Chapter 7 petitions for bankruptcy. Criminal charges were filed by the state against Michael Schuchardt in connection with his activities on the Murphy residence.

The Murphys' complaint named Droessler as a defendant and alleged that he failed to comply with the *424 notice requirements of § 779.02(2), Stats. 1 They requested an order that Droessler's lien be declared void and that he satisfy the claim for the lien he filed; they also requested an award of actual and punitive damages. Droessler brought Conco in as a third party defendant. Droessler's and Conco's counterclaims against the Murphys each alleged unjust enrichment, a valid lien and sought the amounts due to satisfy the liens.

Michael Schuchardt, on advice of counsel, refused to testify. The trial court granted Droessler's request for a bifurcated trial on the ground that the construction lien claims (as opposed to the unjust enrichment *425 claims) could be resolved without Michael Schuchardt's testimony. The trial on the lien claims was to the court. The court concluded that the partial lien waivers and contractor's affidavits signed by Droessler and Conco constituted substantial compliance with the notice requirements of § 779.02(2)(b), Stats., and if there were any insufficiencies in the form of the notices, the Murphys were not misled. The court granted foreclosure on the liens and also ordered that the Murphys were entitled to the payments Droessler was receiving under an agreement with Michael Schuchardt.

The findings of fact made by the trial court will not be set aside unless clearly erroneous. Section 805.17(2), Stats. However, the construction of a statute and its application to a known set of facts is a question of law that this court reviews de novo, without deference to the trial court's conclusion. Tahtinen v. MSI Ins. Co., 122 Wis. 2d 158, 166, 361 N.W.2d 673, 677 (1985).

Section 779.01(3), Stats., gives persons who supply labor or materials for an improvement to real estate a lien on the land, provided they comply with § 779.02, Stats. With certain exceptions not applicable here, § 779.02 requires that the furnisher of labor or materials give notice within sixty days after furnishing the first labor or materials. The section provides that the notice shall be in "substantially the following language," and sets forth the contents of the notice. The notice must be "in writing, in 2 signed copies, to the owner either by personal service on the owner or authorized agent or by registered mail with return receipt requested to the owner or authorized agent at the last-known post-office address." Section 779.02(2)(b). The statutory requirement of registered *426 mail is met by certified mail if a sender's receipt is obtained from the postal authorities and return receipt is requested. Section 990.001(13), Stats.; 2 Trojan v. Bd. of Regents, 104 Wis. 2d 277, 280-85, 311 N.W.2d 586, 587-90 (1981). There are thus three components to the requirements for the notice: time, contents and manner of service.

DROESSLER'S NOTICE

Mary Cardin, an employee of Schuchardt Construction, testified that she mailed the partial lien waiver and contractor's affidavit signed by Droessler to Jean Murphy on July 15,1991. She knew she mailed it then because the date is handwritten on her copy, and it was her practice to note the date of mailing in that way. July 15 is fifty-nine days from Droessler's first delivery of materials. Ms. Murphy testified that she did not receive these documents until the middle of August.

The trial court considered the conflicting testimony of Ms. Cardin and Ms. Murphy, chose to credit Ms. Cardin's testimony, and found that she mailed the documents on July 15. The Murphys do not challenge this finding. However, they argue that Ms. Cardin did not send the partial lien waiver or the contractor's affi *427 davit to the Murphys by registered or certified mail. Droessler does not claim the documents were mailed by registered or certified mail.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seider v. O'CONNELL
2000 WI 76 (Wisconsin Supreme Court, 2000)
Aluminum Industries Corp. v. Camelot Trails Condominium Corp.
535 N.W.2d 74 (Court of Appeals of Wisconsin, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
525 N.W.2d 117, 188 Wis. 2d 420, 1994 Wisc. App. LEXIS 1291, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murphy-v-droessler-wisctapp-1994.