Trout Unlimited v. DNRC

2025 MT 1
CourtMontana Supreme Court
DecidedJanuary 2, 2025
DocketDA 23-0268
StatusPublished
Cited by1 cases

This text of 2025 MT 1 (Trout Unlimited v. DNRC) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trout Unlimited v. DNRC, 2025 MT 1 (Mo. 2025).

Opinion

01/02/2025

DA 23-0268 Case Number: DA 23-0268

IN THE SUPREME COURT OF THE STATE OF MONTANA 2025 MT 1

MONTANA TROUT UNLIMITED, TROUT UNLIMITED, MONTANA ENVIRONMENTAL INFORMATION CENTER, EARTHWORKS, and AMERICAN RIVERS,

Petitioners and Appellants,

v.

MONTANA DEPARTMENT OF NATURAL RESOURCES AND CONSERVATION and TINTINA MONTANA, INC.,

Respondents and Appellees.

APPEAL FROM: District Court of the Fourteenth Judicial District, In and For the County of Meagher, Cause No. DV-2022-09 Honorable Michael B. Hayworth, Presiding Judge

COUNSEL OF RECORD:

For Appellants:

Sean M. Helle (argued), Jenny K. Harbine, Benjamin J. Scrimshaw, Earthjustice, Bozeman, Montana

Patrick A. Byorth, Megan K. Casey, Trout Unlimited, Inc., Project, Bozeman, Montana

For Appellee Montana Department of Natural Resources and Conservation:

Brian C. Bramblett (argued), Molly Kelly, Montana Department of Natural Resources and Conservation, Helena, Montana

For Appellee Tintina Montana, Inc.:

W. John Tietz (argued), Hallee C. Frandsen, Browning, Kaleczyc, Berry & Hoven, P.C., Helena, Montana For Amici Curiae Association of Gallatin Agricultural Irrigators, Montana Chamber of Commerce, Montana Farm Bureau Federation, Montana League of Cities and Towns, Inc., Montana Stockgrowers Association, and Montana Water Resources Association:

Ryan McLane, Franz & Driscoll, PLLP, Helena, Montana

Argued: March 29, 2024 Submitted on Briefs: April 16, 2024 Decided: January 2, 2025

Filed:

ir,-6t----if __________________________________________ Clerk

2 Justice Jim Rice delivered the Opinion of the Court.

¶1 Montana Trout Unlimited, Trout Unlimited, Montana Environmental Information

Center, Earthworks, and American Rivers (collectively “MTU” or “Appellants”) appeal the

order of the Fourteenth Judicial District Court, Meagher County, denying their petition for

judicial review and affirming the Final Order issued by the Department of Natural Resource

(DNRC) determining the scope of, and granting, a water use permit to Tintina Montana,

Inc. (Tintina), for use in its mining operation. We consider the following issues:

1. Whether MTU has standing to object to DNRC’s determination.

2. Whether DNRC correctly categorized Tintina’s removal of water from its mine and subsequent discharge of the water as neither a beneficial use nor a waste, which therefore fell outside the permitting process of the Montana Water Use Act.

3. Whether DNRC interpreted the Montana Water Use Act in contravention of Article IX of the Montana Constitution.

¶2 We affirm.

FACTUAL AND PROCEDURAL BACKGROUND

¶3 Tintina, a mining company, seeks to operate a large underground copper mine,

known as the Black Butte Copper Project (the Mine), located north of White Sulphur

Springs in Meagher County. The entirety of the project is located within the watershed of

Sheep Creek, which in turn, is a tributary of the Smith River. The Mine is also located

within a subbasin of the Upper Missouri River, which is open to new surface water

appropriations but provisionally closed to new groundwater appropriations and therefore

necessitates that any new groundwater permit be accompanied by a mitigation plan in

3 accordance with § 85-2-360, MCA. Under this statute, the DNRC may issue a permit for a

new groundwater use in a provisionally closed subbasin if it finds, inter alia, that the

applicant has prepared a hydrogeologic report assessing the effects of the proposed

groundwater appropriation on hydrologically connected surface sources, and, if that report

shows there will be a net depletion of surface water, that the applicant has prepared a

mitigation plan capable of offsetting the effects of net depletion of the new appropriation

on existing surface water users. See §§ 85-2-360, -362, MCA.

¶4 Because the Mine will be underground, substantial quantities of groundwater will

infiltrate the Mine, interfering with mining activity. To address this problem, Tintina

anticipates needing to remove about 807 acre-feet of water from the Mine annually. Of that

water, Tintina intends to utilize approximately 350 acre-feet in its mining operation. The

remaining 457 acre-feet (Remainder Water) will not serve any purpose in Tintina’s mining

operation. Tintina proposed to treat the Remainder Water and return it to the underground

aquifer. The Remainder Water would be treated at an on-premises water facility and then

placed in an underground infiltration gallery constructed by Tintina. The infiltration gallery

would be located to return the Remainder Water to the aquifer underlying the Sheep Creek

alluvium. During the treatment process, to comply with seasonal surface-water standards,

the Remainder Water would be held in treatment ponds from July to September.

¶5 In September 2018, Tintina submitted a package of permit and change applications

to the DNRC pursuant to the Montana Water Use Act (MWUA or the Act). One of the

4 applications sought approval of what became Permit No. 41J-30116562 (Application).1 The

Application proposed, as described above, the use of 350 acre-feet of groundwater for

Tintina’s mining operation, and the removal of the remaining 457 acre-feet of groundwater

from the mine, called “mine dewatering,” and return of that water to the ground aquifer.

The Application included a mitigation plan to offset the impact upon senior water right

holders of Tintina’s proposed use within its mining operation of the 350 acre-feet of

extracted water, as required by MWUA, given the Mine’s location within the closed Upper

Missouri River basin. Under the mitigation plan, Tintina is required to obtain and provide

sufficient water to offset any loss to senior rights holders on Coon and Sheep Creeks

year-round, and Black Butte Creek seasonally. Tintina proposed to obtain that water from

a combination of consumptive use reductions in several irrigation rights and Tintina’s

permitted appropriation of high spring flows, which water would be stored in a 292 acre-foot

reservoir that would allow for timely release to offset any of Tintina’s depletions to surface

water.

¶6 Following its review of the Application, DNRC issued a Preliminary Determination

to Grant Tintina’s application for a beneficial use permit to use 350 acre-feet of the removed

water, including extensive findings of fact and conclusions of law in categories addressing

1 Tintina also applied for a water appropriation that ultimately became Permit No. 41J-30116563, which is related to the Permit in this appeal, but not at issue here. Tintina proposed therein to capture high spring flows from Sheep Creek at a flow rate of 7.5 CFS to store up to 291.9 AFY in an off-stream reservoir, and to use the water for wetland maintenance and mitigation purposes. The conditions for this permit were adjusted pursuant to the parties’ stipulated settlement, discussed herein.

5 Concurrent Proceedings, Proposed Appropriation, Basin Closure, and Beneficial Water Use

Permit Criteria, which encompassed physical availability, legal availability, adverse effect,

adequate diversion, possessory interest, and beneficial use. Upon these findings and

conclusions, the Preliminary Determination concluded that Tintina had satisfied all criteria

under the MWUA for issuance of a permit. MTU filed objections to the Preliminary

Determination, challenging the determinations regarding legal availability and adverse

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trout Unlimited v. DNRC
2025 MT 1 (Montana Supreme Court, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2025 MT 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trout-unlimited-v-dnrc-mont-2025.