Trireme Energy Holdings, Inc. v. RWE Renewables Americas, LLC

CourtDistrict Court, S.D. New York
DecidedDecember 9, 2022
Docket1:22-cv-07439
StatusUnknown

This text of Trireme Energy Holdings, Inc. v. RWE Renewables Americas, LLC (Trireme Energy Holdings, Inc. v. RWE Renewables Americas, LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trireme Energy Holdings, Inc. v. RWE Renewables Americas, LLC, (S.D.N.Y. 2022).

Opinion

a rrotessional COTpPoravion O N S | N | 1301 Avenue of the Americas 40th Floor New York, New York 10019-6022 0: 212.999.5800 f: 212.999.5899 December 1, 2022 VIA CM/ECF Hon. Jennifer L. Rochon United States District Judge Southern District of New York 500 Pearl Street New York, New York 10007 Re: = Trireme Energy Holdings, Inc. et al. v. Innogy Renewables US LLC et al., No. 1:20-cv-05015-JLR-BCM [rel. 1:22-cv-07439-JLR]: Request for Leave to Move for Summary Judgment Dear Judge Rochon: We write on behalf of the Defendants in the above-captioned matter, pursuant to this Court’s Individual Rule 3.I., to request leave to make a motion for summary judgment as to both substantive claims pending in this action.! While we are cognizant of the Court’s discouragement of summary judgment motions in non-jury cases, for the reasons set forth below, the record in this case is straightforward, largely undisputed and overwhelmingly demonstrates Defendants’ entitlement to judgment as a matter of law. In fact, Judge Caproni (who maintains a similar rule to Your Honor) previously found that summary judgment motion practice is appropriate in this case. See Ex. A at 53:18-21 (“I am going to set a motion for summary judgment . . . I think it is conceivable that this case can be resolved on summary judgment.”). Background: This case concerns the development and construction of a wind farm in upstate New York - the “Cassadaga Project.” Plaintiffs sold the Cassadaga Project (along with several other wind farms) to Defendant Innogy Renewables US LLC (“IRUS”) in late 2017, and IRUS took control of the Project in mid-2018. Beyond the initial payment that IRUS made for Cassadaga, and pursuant to the agreement of sale (the “Merger Agreement”), Plaintiffs would be entitled to an additional payment of $69.7 million (the “Milestone Payment”) if either of two conditions (“Milestones”) was met. First, if IRUS had obtained certain permits necessary to begin construction of Cassadaga on or before October 1, 2019, the Milestone Payment would be due (the “2019 Milestone”). Second, and alternatively, if Cassadaga became commercially operational (7.e., if construction on Cassadaga was complete) by December 31, 2020, that would also trigger the Milestone Payment (the “2020 Milestone”). It is undisputed that IRUS did not meet either Milestone. However, both Milestones are ' We recognize that, in the ordinary course, this Rule requires parties to make this request in the form of a letter-motion to convert the pre-trial conference into a pre-motion conference, and to do so no more than 14 days after the close of fact discovery. However, as this action was transferred to this Court well after the close of fact discovery (and as Judge Caproni advised the parties to hold off on summary judgment until after Daubert motions) we respectfully submit that this letter is timely and that a determination on our request to move for summary judgment should be made in advance of the next appearance before the Court, now scheduled for February 22, 2023. ECF No. 184.

Hon. Jennifer L. Rochon December 1, 2022 Page 2 expressly conditional. Nothing in the Merger Agreement requires IRUS to meet — or even to try to meet Milestone. The only relevant requirement that the Merger Agreement imposes is that IRUS use “commercially reasonable efforts” to “continue to develop” the Cassadaga Project in accordance with standards separately defined in an Annex to the agreement, but that requirement is detached from any obligation to seek to meet a particular Milestone. Plaintiffs have two remaining claims (others were dismissed by Judge Caproni). First, they allege that IRUS breached the Merger Agreement by not exercising commercially reasonable efforts to develop Cassadaga and that, had IRUS exercised commercially reasonable efforts, IRUS would have achieved the 2019 Milestone (although there is no requirement for IRUS to achieve that Milestone or to exercise any particular level of effort to do so) (the “Reasonable Efforts Claim”). Second, they allege that IRUS breached the implied covenant of good faith and fair dealing by failing to complete construction of Cassadaga in 2020, in bad faith, for the purpose of depriving the Plaintiffs of the benefits of the contract (the “Bad Faith Claim”).” Yet, after extensive fact discovery, Plaintiffs have failed to adduce any competent evidence sufficient to prove either claim. Reasonable Efforts Claim: “The standard for satisfying commercial reasonability under New York law is a fairly lenient one,” demanding only “some conscious exertion to accomplish the agreed goal[.]” Shane Campbell Gallery, Inc. v. Frieze Events, Inc., 441 F. Supp. 3d 1, 4 (S.D.N.Y. 2020) (quoting Holland Loader Co. v. FLSmidth A/S, 313 F. Supp. 3d 447, 473 (S.D.N.Y. 2018), aff'd, 769 F. App’x 40 (2d Cir. 2019)). Importantly, a commercially reasonable efforts clause does not require “perfect actions that achieved maximum returns . . . [thus] [a] claim for a material breach of a commercially reasonable efforts provision cannot be established simply by observing, in hindsight, that [defendant] could have done something differently that would have produced a better result.” InspiRx, Inc. v. Lupin Atlantis Holdings SA, 554 F. Supp. 3d 542, 562 (S.D.N.Y. 2021) (granting summary judgment to defendant on a claim for breach of a commercially reasonable efforts clause) (emphasis added; citation omitted). Based on only undisputed facts, IRUS’s summary judgment motion will show that Plaintiffs cannot prevail on the reasonable efforts claim for two reasons. First, where (as here) “the term ‘commercially reasonable efforts’ is not defined by the contract, courts in this district require the party seeking to enforce the efforts provision [here, the Plaintiffs] to establish the objective standard by which the breaching party’s efforts are to be judged, in the context of

? Plaintiffs also seek a declaratory judgment holding that Defendant Innogy SE (IRUS’s former parent) is a guarantor of any judgment against IRUS that may be entered in this action. Defendants do not dispute this. > Tn fact, Plaintiffs’ failures of proof are so significant that, after the close of fact discovery (and in a significant departure from usual practice), the undersigned informed Plaintiffs of our position that while it was not sanctionable for Plaintiffs to assert these claims in hopes discovery would adduce some evidence to support them, now that discovery is closed, it is a plain violation of Federal Rule 11(b) to continue to pursue these claims without evidence. See Ex. B. Although our letter cited to persuasive authority and to the record, Plaintiffs’ response was astoundingly flippant. It stated only that: “[t]he characterizations of the facts and the law in your letter are wrong. Trireme’s claims are meritorious, and we will continue to prosecute them vigorously.” See Ex. C.

Hon. Jennifer L. Rochon December 1, 2022 Page 3 the particular industry.” Holland Loader Co., 313 F. Supp. 3d at 472 (emphasis added). Plaintiffs have not done that, despite submitting opinions from four different experts. That 1s an independent threshold reason why the claim cannot succeed. See Sekisui Am. Corp. v. Hart, 15 F. Supp. 3d 359, 381 (S.D.N.Y. 2014) (“[Plaintiffs] have not proven that [defendant] breached [the reasonable efforts clause] . . . [plaintiffs] presented no evidence establishing the objective standard for ‘commercially reasonable efforts[.]’”); MBIA Ins. Corp. v. Patriarch Partners VII, LLC, 950 F. Supp. 2d 568, 617 (S.D.N.Y.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thompson v. Advanced Armament Corp.
614 F. App'x 523 (Second Circuit, 2015)
Sekisui America Corp. v. Hart
15 F. Supp. 3d 359 (S.D. New York, 2014)
Holland Loader Co. v. Flsmidth A/S
313 F. Supp. 3d 447 (S.D. Illinois, 2018)
MBIA Insurance v. Patriarch Partners VIII, LLC
950 F. Supp. 2d 568 (S.D. New York, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Trireme Energy Holdings, Inc. v. RWE Renewables Americas, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trireme-energy-holdings-inc-v-rwe-renewables-americas-llc-nysd-2022.