Tri-State Painting Co., Inc. v. Oak Ridge Foam & Coating Systems, Inc.

Indiana Court of Appeals·Decided September 4, 2026·No. 25A-PL-02410·Published·Judge Kenworthy

Opinion

FILED

Sep 04 2026, 8:28 am

CLERK

Indiana Supreme Court

Court of Appeals

and Tax Court

IN THE

Court of Appeals of Indiana Tri-State Painting Co. Inc., Appellant-Plaintiff

v.

Oak Ridge Foam & Coating Systems, Inc., Evansville Vanderburgh School Building Corporation, ARC Construction Co., and River Town Construction, LLC, Appellees-Defendants

September 4, 2026

Court of Appeals Case No.

25A-PL-2410

Appeal from the Vanderburgh Superior Court The Honorable Jillian N. Kratochvil, Judge Trial Court Cause No.

82D06-2402-PL-856

Opinion by Judge Kenworthy

Court of Appeals of Indiana | Opinion 25A-PL-2410 | September 4, 2026 Page 1 of 16

Judges Weissmann and DeBoer concur.

Kenworthy, Judge.

Case Summary [1] Evansville Vanderburgh School Corporation (the “School”) undertook stadium

bleacher refinishing projects at two of its high schools. The School hired River Town Construction, LLC (“River Town”) as the contractor for one project and ARC Construction Co., Inc. (“ARC”) as the contractor for the other. River Town and ARC each subcontracted with Tri-State Painting Co., Inc. (“Tri- State”) for Tri-State to provide labor and materials to coat concrete steps, walkways, and seating in the stadiums. Tri-State obtained the coating product from Oak Ridge Foam & Coating Systems, Inc. (“Oak Ridge”) and applied it at both stadiums. The coating failed to perform as expected.

[2] Tri-State filed a complaint against the School, River Town, ARC, and Oak Ridge (collectively, the “Defendants”). The Defendants asserted an array of cross-claims and counterclaims. Relevant to this appeal, River Town and ARC (collectively, the “Contractors”) each asserted counterclaims against Tri-State alleging (1) Tri-State breached the subcontracts, and (2) they were entitled to indemnification and a defense from Tri-State for cross-claims asserted against them by the School.

[3] The Contractors then moved for judgment on the pleadings, seeking judgment in their favor on their counterclaims. After a hearing, the trial court granted the Contractors’ motions—awarding judgment for the Contractors against Tri-State for breach of contract in an amount to be determined later and ordering Tri- State to indemnify and defend the Contractors against all claims.

[4] Tri-State sought and the trial court granted certification of these orders for interlocutory appeal, and this Court accepted jurisdiction. On appeal, Tri-State raises several issues, of which we find the following consolidated issue dispositive: Did the trial court err in granting judgment on the pleadings on the Contractors’ counterclaims? We reverse and remand.

Facts and Procedural History 1 [5] In 2020, the School contracted with River Town to complete a stadium

refinishing project at Reitz High School and with ARC to do the same at Bosse High School (collectively, the “Projects”). In turn, the Contractors subcontracted with Tri-State to provide labor and materials for coating the concrete steps, walkways, and seating at the stadiums. The subcontracts are not identical but contain many similar provisions, including for indemnity and defense.

1 We held oral argument on July 14, 2026, in our courtroom at the Indiana Statehouse. We thank counsel for their skillful written and oral advocacy.

Court of Appeals of Indiana | Opinion 25A-PL-2410 | September 4, 2026 Page 3 of 16

[6] According to Tri-State’s pleadings, the School’s architect did not originally specify an Oak Ridge product. But the originally specified product was not acceptable to the School, and Tri-State contacted Oak Ridge to inquire “if it manufactured a product that would be better suited” to the Projects. Appellant’s App. Vol. 2 at 26. After receiving “all relevant details” about the Projects, Oak Ridge recommended its product, OR 42D. Id. The architect accepted the recommendation and issued change orders specifying the use of “OR42D 100% Polyurethane” as the coating. Id. at 81.

[7] Tri-State placed orders for OR 42D. Some OR 42D was delivered, but “most of the product delivered was OR 42[.]” Id. at 26. Tri-State notified Oak Ridge of the discrepancy. Oak Ridge responded that OR 42 was “the same or better than OR 42D” and was “specially and expressly formulated” for the Projects. Id. at 27, 31. Tri-State applied both products “with requisite care, skill, workmanship, and in total conformity with all application instructions and guidelines.” Id. at 31. 2 But the products failed “for the purpose for which [they were] intended and recommended”: they cracked, bubbled, and developed pinholes; and the color bled onto clothes and bleached when exposed to the sun and heat. Appellant’s App. Vol. 2 at 27–28. Tri-State attributed the failure to the “defective quality” of the products. Id. at 28.

2 At the hearing on the motions for judgment on the pleadings, counsel for Tri-State clarified that both OR 42D and OR 42 were applied at the Reitz stadium, but only OR 42 was applied at the Bosse stadium. See Tr. Vol. 2 at 41.

Court of Appeals of Indiana | Opinion 25A-PL-2410 | September 4, 2026 Page 4 of 16

[8] Attempts at remediation were made, but in 2024, Tri-State filed a complaint against the Defendants. 3 Count 3 of Tri-State’s complaint sought declaratory judgment and Count 4 sought interpleader against the Contractors.

[9] The Contractors answered 4 and asserted counterclaims for breach of contract and indemnity against Tri-State. ARC alleged Tri-State breached the warranty provision of its subcontract agreement by failing to provide materials that conformed to the requirements of the subcontract and were free from defects. ARC also invoked the provision of the subcontract obligating Tri-State to defend, pay all costs incurred, and hold ARC harmless for its failure to adhere to the subcontract and sought indemnification for “any damages ARC has, or will incur, due to Tri-State’s negligence in performing its scope of work.” Appellee’s App. Vol. 2 at 54. River Town likewise alleged Tri-State breached its subcontract agreement by using a different product than specified and invoked the indemnification and defense clause of its subcontract. Both Contractors alleged they had fully performed under their subcontracts.

[10] Tri-State replied to each counterclaim. It admitted it entered subcontracts with the Contractors to provide labor and materials for the coating of the steps, walkways, and seating for the Projects; admitted change orders were issued for

3 Tri-State’s claims against the School and Oak Ridge are not part of this appeal.

4 The Contractors did not answer Counts 3 and 4 of Tri-State’s complaint because they simultaneously filed partial motions to dismiss those counts for failure to state a claim upon which relief could be granted. Instead, they reserved the right to amend their answers if the motions were denied. As of the date of the hearing on the motions for judgment on the pleadings, the motions to dismiss remained pending.

Court of Appeals of Indiana | Opinion 25A-PL-2410 | September 4, 2026 Page 5 of 16 use of OR 42D; and admitted it applied a coating to the projects. Tri-State denied it breached either subcontract, denied it was negligent in applying the product, denied it warranted the product, and denied it owed indemnity or a defense to the Contractors “under the facts of this case.” Id. at 82 (Answer to River Town’s counterclaims), 92 (Answer to ARC’s counterclaims). As to River Town, Tri-State denied River Town had fully performed under the subcontract because River Town had not paid the balance due to Tri-State. 5 Tri-State also asserted affirmative defenses to the Contractors’ counterclaims, including: the School’s architect specified the product, Tri-State made no warranties and was not a guarantor of the product, and any failure was caused by others.

Free access — add to your briefcase to read the full text and ask questions with AI

Tri-State Painting Co., Inc. v. Oak Ridge Foam & Coating Systems, Inc., (Ind. Ct. App. 2026).

Tri-State Painting Co., Inc. v. Oak Ridge Foam & Coating Systems, Inc. (Tri-State Painting Co., Inc. v. Oak Ridge Foam & Coating Systems, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Murray v. City of Lawrenceburg
925 N.E.2d 728 (Indiana Supreme Court, 2010)
Shepherd v. Truex
823 N.E.2d 320 (Indiana Court of Appeals, 2005)
Fox Development, Inc. v. England
837 N.E.2d 161 (Indiana Court of Appeals, 2005)
Milestone Contractors, L.P. v. Indiana Bell Telephone Co.
739 N.E.2d 174 (Indiana Court of Appeals, 2001)
Collins v. McKinney
871 N.E.2d 363 (Indiana Court of Appeals, 2007)
Eskew v. Cornett
744 N.E.2d 954 (Indiana Court of Appeals, 2001)
Millner v. Mumby
599 N.E.2d 627 (Indiana Court of Appeals, 1992)
Hendricks County, Indiana v. Gwyn L. Green
120 N.E.3d 1118 (Indiana Court of Appeals, 2019)