Tri-State Contractors, Inc. v. Fagnant

393 F. App'x 580
CourtCourt of Appeals for the Tenth Circuit
DecidedSeptember 1, 2010
Docket08-8099
StatusUnpublished
Cited by2 cases

This text of 393 F. App'x 580 (Tri-State Contractors, Inc. v. Fagnant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri-State Contractors, Inc. v. Fagnant, 393 F. App'x 580 (10th Cir. 2010).

Opinion

ORDER AND JUDGMENT *

DAVID M. EBEL, Circuit Judge.

In April 2006, Plaintiff-Appellee TriState Contractors submitted a bid, and an accompanying bid bond, to construct a new city building in Kemmerer, Wyoming. Although the city did not accept Tri-State’s bid, it did not return Tri-State’s bond. Instead, over the- next several months, the city and Tri-State negotiated ways to control costs for the construction project, and the two parties ultimately entered into a contract in July 2006. After signing the contract, Tri-State alleged that numerous undisclosed deficiencies with the building site made construction at the agreed-upon rate impossible. Tri-State thus withdrew from the contract and demanded the return of its bid bond, which the city claimed a right to keep as liquidated damages for Tri-State’s withdrawal.

Tri-State, along with Plaintiffs-Appel-lees Del Bartel and Dale Thurgood (collectively, “Tri-State”), brought suit against Kemmerer and several city officials. The district court granted Tri-State’s motion for summary judgment against the city for return of the bond and denied the individual Defendants’ motion for summary judgment on the ground of qualified immunity. The individual Defendants now appeal that denial. For the reasons that follow, we affirm.

I. Background

The parties agree as to the basic facts at issue in this appeal. In April 2006, the city of Kemmerer, Wyoming, advertised for bids for the construction of a 7800 square-foot building. The building, called the Kemmerer American Family Entertainment Center, was to be an addition to the Victory Theater, located in the city’s downtown area, and was to serve as a recreational facility for Kemmerer residents. The advertisement issued by the city required that “[a]ll bids must be accompanied by either a certified check, cashier’s check drawn on an acceptable bank, or an acceptable bid bond, executed by an approved Surety Company, in an amount no less than five percent (5%) of the total sum of the bid.” (Apt-App. at 82.) Wyoming law also requires that a bid for a public improvement contract be accompanied by a bid bond equal to at least five percent of the total bid amount. Wyo. Stat. Ann. § 15 — 1—113(f). The advertisement further provided that the check or bond “will be retained by [the city of Kem-merer] as liquidated damages if the successful bidder refuses or fails to enter into a contract and bond in accord with his bid when notified of the award.” (Apt.App. at *582 82.) The winning bidder would also be required to provide the city with both a performance bond and a payment bond, “each in the penal sum equal to the total amount of his bid.” (Id.)

On April 18, 2006, three bids were presented, and the bids were opened and read aloud. Tri-State Contractors submitted the lowest bid, at $1,163,845, along with a certified check in the amount of $58,192 serving as the bid bond. Nevertheless, no bids were accepted at that time. Appellant Mike Archibald, Kemmerer City Administrator, spoke to both Tri-State and the city council about Tri-State’s bid, informing all parties that the bids were substantially over the city’s allocated budget. Archibald proposed “value engineering” the project — meaning that the involved parties, owner, contractor, and engineer, all agreed to revisit the project and look for ways to cut costs — and both the city council and Tri-State agreed. The option to value engineer the project was given only to Tri-State as the lowest bidder. Tri-State’s bid bond was not returned.

On July 10, Tri-State submitted another bid form, for $1,079,920. Tri-State did not submit a bid bond with that form, as the city had retained their original $58,192 bid bond. The city accepted this bid, and entered into a contract with Tri-State on July 26, 2006. The city did not advertise for any further bids between the bid-opening on April 18 and the signing of the TriState contract on July 26. On August 7, the city issued Tri-State a “Notice to Proceed,” instructing it to commence construction within one week. On August 25, TriState hand-delivered a letter to Archibald, informing him that, because of numerous deficiencies with the building site that made it impossible to begin construction, Tri-State was withdrawing from the contract. In the letter, Tri-State also demanded return of its bid bond. The city refused to return the bond, insisting on its right to retain the bond as liquidated damages for Tri-State’s alleged breach of the construction contract.

In May 2007, Tri-State brought suit in federal court against the city of Kemmerer, and Appellants Archibald, David Fag-nant (mayor of Kemmerer), and Tony Tomassi (a city councilman). Tri-State alleged that the defendants deprived TriState of its property rights without due process of law, in violation of 42 U.S.C. §§ 1983 & 1988. The defendants moved for summary judgment on all counts, and Tri-State moved for partial summary judgment against the city. On November 17, 2008, the district court denied the defendants’ motion for summary judgment and granted Tri-State’s motion for partial summary judgment as to the procedural due process claim against the city. In addition, the court denied the individual defendants’ motion for summary judgment on the ground of qualified immunity, and entered summary judgment in favor of Plaintiffs against the individual defendants in both their individual and official capacities. 1 On this basis, the court ordered that Tri-State was entitled to the return of its bid bond in the amount of $58,192, plus interest. 2 The court then dismissed all remaining claims. One week later, the district court entered an order amending the November 17 order by clarifying that TriState’s claim for punitive damages was not dismissed.

*583 The individual defendants then filed this appeal, claiming that the district court erred in concluding that they were not entitled to summary judgment in their individual capacities on the ground of qualified immunity.

II. Discussion

A. Jurisdiction

A district court’s order denying summary judgment is generally not an appeal-able order under 28 U.S.C. § 1291. See Bowling v. Rector, 584 F.3d 956, 963 (10th Cir.2009). “Such a denial ‘is subject to appeal, however, when the defendants are public officials asserting a qualified immunity defense and the appealed issue is whether a given set of facts establishes that defendants violated clearly established law.’ ” Id. (quoting Bass v. Richards, 308 F.3d 1081, 1086 (10th Cir.2002)). When reviewing a denial of qualified immunity, this court lacks jurisdiction to review the district court’s factual determinations, see Swanson v. Town of Mountain View, Colo., 577 F.3d 1196, 1199 (10th Cir. 2009), but no material factual disputes exist here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
393 F. App'x 580, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-state-contractors-inc-v-fagnant-ca10-2010.