Tri-State Consumer Insurance v. Lexisnexis Risk Solutions, Inc.

858 F. Supp. 2d 1359, 2012 WL 1548276, 2012 U.S. Dist. LEXIS 61768
CourtDistrict Court, N.D. Georgia
DecidedMay 3, 2012
DocketCivil Action No. 1:11-cv-1313-TCB
StatusPublished
Cited by3 cases

This text of 858 F. Supp. 2d 1359 (Tri-State Consumer Insurance v. Lexisnexis Risk Solutions, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri-State Consumer Insurance v. Lexisnexis Risk Solutions, Inc., 858 F. Supp. 2d 1359, 2012 WL 1548276, 2012 U.S. Dist. LEXIS 61768 (N.D. Ga. 2012).

Opinion

ORDER

TIMOTHY C. BATTEN, SR., District Judge.

This matter is before the Court on Plaintiff Tri-State Consumer Insurance Company’s motion to dismiss Defendant LexisNexis Risk Solutions, Inc.’s counterclaim [34].

I. Background

A. Procedural Background

On January 21, 2011, Tri-State filed this action in the Superior Court of Fulton County. On February 21, 2011, Lexis filed its answer, which included a counterclaim against Tri-State. That same day, Lexis also filed a motion to dismiss Tri-State’s claims. In response to Lexis’s motion to dismiss, Tri-State filed an amended complaint, which included the addition of two claims under federal law. Based on TriState’s adding the federal-law claims, Lexis removed the action to this Court on federal-question grounds.1

On April 22, Lexis filed another motion to dismiss, and that same day, Tri-State filed yet another amended complaint.2 On April 29, Lexis filed a third motion to dismiss. Following oral argument on the motion, on November 10, the Court issued an order granting Lexis’s motion in part by dismissing all of Tri-State’s claims except its claims for breach of contract, breach of the warranty of repair, and breach of the implied covenant of good faith and fair dealing.

On November 30, 2011, Lexis again filed its answer to Tri-State’s second amended complaint and a counterclaim against TriState for (1) anticipatory repudiation, (2) breach of contract, (3) breach of the implied covenant of good faith and fair dealing, (4) improper retention of Lexis’s property, and (5) bad faith litigation and stubborn litigiousness.3 Tri-State moves to dismiss all of Lexis’s claims except its claim for improper retention of its property.

B. Facts Alleged by Lexis in Its Counterclaim

On March 31, 2008, Lexis and Tri-State executed two contracts-a master agreement and software and services schedule-for the development, sale, and provision of software to Tri-State. The agreements created a framework by which the parties would work cooperatively to create customized software for Tri-State’s use in its insurance business.

The agreements did not require Lexis to complete the software by a specific date, but instead required both parties’ cooperation in performing certain tasks necessary for the development and implementation of the software. Tri-State knew that without its cooperation, Lexis could not design and produce software customized to meet TriState’s needs.

For example, section 11.5 of the master agreement specified that Lexis would [1363]*1363“have no liability for delays in the provision of the Project implementation services caused by [Tri-State’s] failure to complete its tasks or provide information, or resources in a timely manner.” And the software and services schedule required Tri-State to, inter alia, (1) “[a]ssign competent project, insuranee/business and technical staff to review and sign-off on the final [project]” (§ 10(a)(ii)); (2) “provide adequate resources to ensure that the [client requirements book] process is completed within” seventy-five days of the software and services schedule’s execution (§ 10(a)(iii)); and (3) participate in executive governance committee meetings as required by master agreement § 7.1 (§ 10(a)(xi)). Additionally, sections 3, 5, 6 and 7 of the master agreement required ongoing cooperation from Tri-State in the form of, among other things, testing after delivery of the software and designating coordinators to identify problems.

According to the software and services schedule § 8(a), Tri-State was required to make several payments to Lexis for a base-software license fee. Those payments were “due as follows: $250,000 upon execution of the Master Agreement [and] $125,000 Billable monthly beginning May 1, 2008 and ending on December 1, 2008.” The parties further agreed, pursuant to the software and services schedule § 8(a), that Lexis would create certain customized add-ons for a flat-fee of $245,000 and a number of other customizations to be paid on a time and materials basis.

Lexis developed for and delivered to Tri-State a number of software components and certain software customizations, as well as the policy-decisions batch of software. However, Lexis’s ability to complete the development and implementation of the overall project was delayed by TriState’s various change requests. TriState further hindered the project’s progress by failing to timely provide key information to Lexis and not devoting sufficient resources to the project.

In April 2009, the parties “re-baselined” the project, meaning they generated new target dates for the project’s completion. Starting that month, Lexis generated weekly status reports so as to keep TriState apprised of the progress of the software development.

In May 2009, Peter Kardas, Tri-State’s project manager, sent Lexis an email acknowledging that the software project would be delayed. But in July 2009, TriState informed Lexis that its president Penny Hart had decided to put the software project on indefinite hold, had reassigned Tri-State’s internal resources away from the project, had terminated TriState’s project manager, and had left the country on vacation. That same month, in response to Hart’s email, Lexis notified Tri-State that without Tri-State’s involvement Lexis could not complete the project. And in an effort to restart the project, in August 2009 Lexis’s vice president of its software division, Marvin Karlow, sent Hart a go-forward proposal. Tri-State rejected Karlow’s offer.

Despite the fact that Tri-State had suspended all work on the project and knew that Lexis could not complete the project without Tri-State’s cooperation, on January 22, 2010, Tri-State sent Lexis a letter alleging that pursuant to § 10.3 of the master agreement, Lexis had materially breached the agreements by failing to deliver the software on time. Section 10.3 of the master agreement provides that TriState can terminate the agreements if Lexis “breaches any material term of this Agreement and fails to initiate a remedy for such breach within (30) calendar days after receiving notice thereof from [TriState].”

Three days later, Lexis responded to the letter by proposing that members of the [1364]*1364project’s executive team meet to (1) identify the project’s problems, (2) understand the specific allegations which Tri-State believed gave rise to the allegation of breach, (3) outline the respective interests of the parties, (4) identify areas of alignment and disagreement, and (5) determine a mutually acceptable arrangement to address each party’s concerns.

On February 5, 2010, Tri-State communicated to Lexis that its executive team was not presently available but nonetheless demanded that Lexis deliver the completed project within thirty days. At that point, Tri-State suspended all work on the project, even though it knew that Lexis could not possibly deliver the completed project without Tri-State’s participation and cooperation.

On February 16, Lexis sent Tri-State a letter informing it that Tri-State’s cooperation was a material condition of performance and that it was still willing to reengage with Tri-State on the project. On February 24, 2010, Tri-State informed Lexis that it was terminating the agreements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New York Life Insurance v. Grant
57 F. Supp. 3d 1401 (M.D. Georgia, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
858 F. Supp. 2d 1359, 2012 WL 1548276, 2012 U.S. Dist. LEXIS 61768, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-state-consumer-insurance-v-lexisnexis-risk-solutions-inc-gand-2012.