Tri-City Community Action Program, Inc. v. City of Malden

680 F. Supp. 2d 306, 2010 U.S. Dist. LEXIS 5291, 2010 WL 271430
CourtDistrict Court, D. Massachusetts
DecidedJanuary 22, 2010
DocketCivil Action 06cv12246-NG
StatusPublished
Cited by6 cases

This text of 680 F. Supp. 2d 306 (Tri-City Community Action Program, Inc. v. City of Malden) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri-City Community Action Program, Inc. v. City of Malden, 680 F. Supp. 2d 306, 2010 U.S. Dist. LEXIS 5291, 2010 WL 271430 (D. Mass. 2010).

Opinion

MEMORANDUM AND ORDER RE: MOTION FOR ATTORNEY FEES & COSTS

GERTNER, District Judge:

I. INTRODUCTION

Plaintiffs are a nonprofit organization, Tri-City Community Action Program, Inc., (“Tri-CAP”), that provides housing to the homeless, and four disabled homeless persons (“Jane Doe and three John Does”) who planned to live in the rooming house that Tri-CAP was to renovate. They sued the City of Malden (“the City”) to compel the issuance of a building permit that would allow Tri-Cap to retrofit the house in compliance with the Americans with Disabilities Act (“ADA”), 42 U.S.C. § 12111 et seq.

There is no question that the plaintiffs were successful, admirably so. Plaintiffs obtained a preliminary injunction which ordered the City to refrain from interfering with the construction of the rooming house. By May of 2008, while the preliminary injunction was in force, Tri-CAP *309 completed the construction, thereby rendering the suit moot. 1

Plaintiffs now move for an award of attorney fees and costs as prevailing parties under the fee-shifting provision of the Fair Housing Act Amendments of 1988 (“FHAA”), 42 U.S.C. § 3613(c)(2). As I describe below, there is no question that plaintiffs deserve to be paid for their efforts, and that the law requires it. The only question is the amount. For the reasons described below, I AWARD $48,994.00 in fees and $1,005.00 in costs.

II. BACKGROUND

Plaintiffs are Tri-CAP, a Malden-based nonprofit that provides housing and services to chronically homeless and disabled adults, and four homeless persons slated to live in a new Tri-CAP facility. On January 11, 2006, Tri-CAP entered into a purchase and sale agreement (“PSA”) to buy a fourteen-room house for $595,000. The house was already a rooming house — one of the last four licensed rooming houses in Malden — but was deteriorating and underutilized. Tri-CAP planned $1.37 million in renovations to bring the building into compliance with the ADA. It had arranged for the funding for the project, much of it from the U.S. Department of Housing and Urban Development (“HUD”).

In February 2006, Malden’s building inspector informed Tri-CAP that he would not issue a building permit. Tri-CAP submitted revised plans in April 2006, which were reviewed but then denied again in August 2006. Tri-CAP then applied to the Malden Planning Board for a special permit to make the renovations. At a public hearing on October 11, 2006, several neighborhood residents raised concerns about the peace and safety of the neighborhood and their children. The meeting was continued until November 15, 2006, at which point the Board denied the permit application, without any statement of reasons.

Plaintiffs filed claims under the FHAA, 42 U.S.C. § 3601 et seq., for defendants’ alleged discriminatory actions; 42 U.S.C. § 1983, for equal protection and due process violations; Mass. Gen. Laws ch. 40A, § 3 for abuse of discretion in connection with the denial of a permit; and various state constitutional and statutory provisions that protect disabled persons against discrimination. Asserting irreparable harm in connection with the delay in obtaining the permit and the risk of losing their HUD grant, plaintiffs sought injunctive relief, as well as damages. 2

III. PROCEDURAL HISTORY

On December 15, 2006, plaintiffs filed a motion for a preliminary injunction. Having had absolutely no response from the defendants to its moving papers and facing a deadline, namely the building seller’s demand for assurances that the permit be obtained by January 31, 2007, plaintiffs moved for a temporary restraining order (“TRO”) on January 18, 2007. The defendants continued to ignore the suit. Plaintiffs filed a motion for default judgment on January 18, 2007, renewing it on January 30, 2007. But while defendants finally responded by opposing the default judgment, they did not oppose the motion for a preliminary injunction.

*310 I granted a preliminary injunction enjoining the City from “interfering with or preventing Tri-City Community Action Program from purchasing, occupying and carrying out modifications” to the property. Electronic Order (January 31, 2007). And, while I denied the renewed motion for default judgment, I chastised the defendants:

The Court will not default the defendants, even though their explanation for the total failure to respond to plaintiffs’ pleadings is barely reasonable. The preliminary injunction which the Court entered yesterday protects the plaintiffs from the immediate consequences of the defendants’ dilatoriness. Under the circumstances, the litigation may proceed; a section 16(b) conference will be scheduled shortly.

Electronic Order (January 31, 2007). The preliminary injunction endorsement found that the plaintiffs were substantially likely to succeed on the merits of their claims as required by the Rule 65, Fed. R. Civ. Pro (all the while underscoring the court’s concern with defendant’s conduct):

There being no opposition, this Court GRANTS in part plaintiffs’ motion for a preliminary injunction (docket # 2). Defendants are hereby ENJOINED from interfering with or preventing TriCity Community Action Program, Inc., from purchasing, occupying and carrying out modifications to the property at 115 Washington St. in Malden set out in plaintiffs permit application submitted on 8/30/06 to the Malden Planning Board. Pl.Ex. G (docket # 3-8), Exhibit H (docket # 3-9). The motion for a preliminary injunction is denied with respect to monetary damages, and attorneys’ fees which are not an appropriate subject for a preliminary injunction. The case was filed on December 15, 2006; a motion for a preliminary injunction accompanied the filing. The complaint was served with answers due on during the first week in January, 2007. The plaintiff — under considerable time pressure as described in its preliminary injunction papers, namely a January 31, 2007 deadline for the purchase of the property which was to be used for transitional housing — moved for a default and indicated to the defendants that it would do so by letter. The defendants did not respond in any way — by letter, by phone call, much less by pleading— until today, the very deadline that was the subject of the preliminary injunction. When the defendants finally responded, their response was only to seek to set aside the default, and not to oppose the preliminary injunction. On its face, the motion for preliminary injunction meets the standards of Rule 65, namely the likelihood of success on the merits, coupled with inseparable harm.

Id. (Italics supplied.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baptista v. Lyons
D. Massachusetts, 2020
Alston v. Town of Brookline
D. Massachusetts, 2019
Rogers v. Cofield
935 F. Supp. 2d 351 (D. Massachusetts, 2013)
CONSERVATION LAW FOUNDATION, INC. v. Patrick
767 F. Supp. 2d 244 (D. Massachusetts, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
680 F. Supp. 2d 306, 2010 U.S. Dist. LEXIS 5291, 2010 WL 271430, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-city-community-action-program-inc-v-city-of-malden-mad-2010.