Travelers Casualty and Surety Company of America v. Winmark Homes, Inc.

518 F. App'x 899
CourtCourt of Appeals for the Eleventh Circuit
DecidedMay 20, 2013
Docket11-15950
StatusUnpublished
Cited by4 cases

This text of 518 F. App'x 899 (Travelers Casualty and Surety Company of America v. Winmark Homes, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Travelers Casualty and Surety Company of America v. Winmark Homes, Inc., 518 F. App'x 899 (11th Cir. 2013).

Opinion

PER CURIAM:

Travelers initiated this action against several entities and individuals to recover under a general indemnity contract in connection with the execution of surety bonds. Having reviewed the record, and with the benefit of oral argument, we affirm the district court’s grant of summary judgment in favor of Travelers.

I

In 2005, a number of developers 1 started building eight residential subdivisions in Gwinnett and Forsyth Counties in Georgia. Pursuant to various development performance and maintenance agreements, the developers agreed that, as a condition precedent to county approval of the subdivision plats, they would construct and maintain certain improvements (i.e., roads, sidewalks, landscaping, and drainage facilities). In July of 2007, Travelers and the Winmark defendants executed a general contract of indemnity (the “indemnity agreement”); Travelers agreed to issue surety bonds on behalf of the developers *901 and other individuals, 2 all of whom agreed to indemnify Travelers for any loss that it might incur as a result of issuing the bonds. We refer to the developers and the individuals collectively as the Winmark defendants. Travelers subsequently issued 22 subdivision maintenance/performance surety bonds. Following a collapse in the real estate market, all of the subdivisions were ultimately abandoned.

Gwinnett County gave notice to the developers and to Travelers that the bonded obligations on some of the bonds had not been completed and that additional work was needed. When the developers refused to perform the additional maintenance, Travelers demanded that the Winmark defendants provide either the full and complete discharge of Travelers from all outstanding bonds or an irrevocable letter of credit in the amount of $924,348.47 (the alleged amount of undischarged liability under the bonds). The Winmark defendants did neither. A few weeks later, Travelers issued another demand under the indemnity agreement, requiring once again discharge from all outstanding bonds or an irrevocable letter of credit in the amount of $659,348.47. Travelers subsequently revised its position and demanded a letter of credit in the amount of $223,846.00, which reflected the low-end estimate of Robert Colby, a professional engineer and construction consultant, of the cost of completing the bonded work remaining at the subdivisions. 3 The Win-mark defendants failed to meet Travelers’ demands, prompting it to file this action. The Winmark defendants filed counterclaims alleging breach of contract, breach of the covenant of good faith and fair dealing, and breach of fiduciary duty.

Travelers moved for summary judgment on its claim for specific performance and indemnification, and on the counterclaims. The district court granted Travelers’ motions. The Winmark defendants appeal from the district court’s grant of summary judgment. They contend that the district court erred in (1) requiring them to provide an irrevocable letter of credit in the amount of $223,846.00; (2) awarding Travelers attorneys’ fees and expenses in the amount of $107,048.21; and (3) rejecting their counterclaims.

II

We review a grant of summary judgment de novo and apply the same legal standards as the district court. See Citizens for Smart Growth v. Sec’y of the Dep’t of Transp., 669 F.3d 1203, 1210 (11th Cir.2012). “The court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R.Civ.P. 56(a). We view the evidence and all factual inferences in the light most favorable to the party opposing the motion. See Prickett v. DeKalb County, 349 F.3d 1294, 1296 (11th Cir.2003) (citations and quotations omitted). Plenary review applies to the construction of written contracts. See Nat’l Fire Ins. Co. of Hartford v. Fortune Constr. Co., 320 F.3d 1260, 1267 (11th Cir.2003).

A

A federal court in a diversity case is required to apply the choice of law rules of the state in which that court sits. See Klaxon Co. v. Stentor Electric Mfg. Co., 313 U.S. 487, 496, 61 S.Ct. 1020, 85 L.Ed. *902 1477 (1941); O’Neal v. Kennamer, 958 F.2d 1044, 1046 (11th Cir.1992). Here it is undisputed that Georgia contract law applies.

When interpreting indemnity agreements under Georgia law, we apply the ordinary rules of contract construction. See Anderson v. U.S. Fid. & Guar. Co., 267 Ga.App. 624, 600 S.E.2d 712, 715 (2004). No construction is required or even permissible when the language employed by the parties in the contract is plain, unambiguous and capable of only one reasonable interpretation. See id. See also Reliance Ins. Co. v. Romine, 707 F.Supp. 550, 552 (S.D.Ga.1989) (“Under Georgia law, where the language of a contract is definite and unambiguous, a court must give it effect.”), aff'd, 888 F.2d 1844 (11th Cir.1989) (per curiam).

The indemnity agreement requires the Winmark defendants to provide Travelers with an irrevocable letter of credit if they fail to obtain Travelers’ discharge from bond liability. The indemnity agreement states, in ¶ 5, as follows:

(a) Indemnitors shall, within thirty (30) days of receipt of Company’s [Travelers] written demand (“Discharge Demand”), procure the full and complete discharge of the Company from any and all Bond(s) ... If Indemnitors fail to provide the aforementioned discharge In-demnitors shall, within an additional seven (7) days, provide Company with an irrevocable letter of credit in form, content and by a bank acceptable to Company. The letter of credit shall be in an amount equal to the total of all undischarged liability under said Bond(s), which liability shall be determined at the time of the Company’s Discharge Demand.

[D.E. 58-5 at 2, ¶ 5] (emphasis added).

We agree with the district court that the Winmark defendants’ promise to provide an irrevocable letter of credit is enforceable by its terms through an order of specific performance. See Anderson, 600 S.E.2d at 715 (recognizing that the Georgia court of appeals “consistently has upheld the validity and enforceability of indemnification agreements executed in connection with the issuance of surety bonds”); Hanover Ins. Co. v. Holley Constr. Co. & Assocs., Inc., 2012 WL 398135, at *7 (M.D.Ga. Feb.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
518 F. App'x 899, Counsel Stack Legal Research, https://law.counselstack.com/opinion/travelers-casualty-and-surety-company-of-america-v-winmark-homes-inc-ca11-2013.