Reliance Insurance v. Romine

707 F. Supp. 550, 1989 U.S. Dist. LEXIS 1928, 1989 WL 18623
CourtDistrict Court, S.D. Georgia
DecidedFebruary 22, 1989
DocketCiv. A. 488-124
StatusPublished
Cited by8 cases

This text of 707 F. Supp. 550 (Reliance Insurance v. Romine) is published on Counsel Stack Legal Research, covering District Court, S.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reliance Insurance v. Romine, 707 F. Supp. 550, 1989 U.S. Dist. LEXIS 1928, 1989 WL 18623 (S.D. Ga. 1989).

Opinion

ORDER

ALAIMO, Chief Judge.

This is an action for recovery of damages under an indemnification agreement. Before the Court are cross-motions for summary judgment. As the agreement at issue is valid and binding upon the parties, defendant’s motion will be denied but plaintiff’s motion will be granted.

BACKGROUND

In the fall of 1983, Norris, Inc. (“Norris”), a non-party to this action, agreed to enter into a construction contract with Cer-tainTeed, another non-party, for the construction of the Filled Coatings Systems project (“the Project”) for CertainTeed in Savannah, Georgia. CertainTeed informed Norris that, as a condition precedent to being awarded the contract, Norris would be required to obtain labor and material payment and performance bonds (“the bonds”).

Subsequently, Aubrey Norris, president of Norris, approached the insurance agency of Dixon Sheehan Titus, Inc. (“Dixon Shee-han”), an authorized bonding agent for plaintiff. As part of its application for plaintiff’s bonds from Dixon Sheehan, Norris submitted a financial statement. Based upon a review of the financial statement, Dixon Sheehan informed Norris that, because of Norris’ financial condition, plaintiff would not issue bonds to Norris on the Project. However, Norris was informed that plaintiff would be willing to issue bonds for the Project if Norris obtained an additional indemnitor. Thereafter, Aubrey Norris informed Dixon Sheehan that Ted Romine, the defendant in this matter, would sign an indemnification agreement as an additional indemnitor so that plaintiff would issue its bonds to Norris for the Project.

On November 7, 1983, Norris entered into a construction contract with Certain- *551 Teed for the construction of the Project. As required by CertainTeed, Norris also continued to seek the required labor and material payment and performance bonds it needed to construct the Project. Subsequently, on November 16, 1983, Norris executed a “Contractors Bond Application and Indemnification Agreement” with plaintiff. In addition, both Aubrey Norris and Ted Romine individually signed the indemnification agreement given to plaintiff. Following receipt of the executed indemnification agreement, Dixon Sheehan issued plaintiffs labor and material payment and performance bonds for the Project to Norris.

Thereafter, during the winter of 1983 and spring of 1984, Norris undertook construction of the Project for CertainTeed. However, in the spring of 1984, Certain-Teed declared Norris in default of its contract obligations and terminated Norris on the Project.

At the time that Norris was declared in default by CertainTeed, Norris was unable to pay six subcontractors and suppliers who had furnished Norris with labor, materials and equipment for its use at the Project. All six claimants subsequently submitted claims to plaintiff for work done on the Project. Plaintiff requested each claimant to provide it with documentation of all materials, equipment and labor furnished to Norris for use on the Project, and further requested that each claimant execute a claimant’s affidavit stating that the furnished items were used for or on the Project.

Thereafter, based upon the claims affidavits submitted by each claimant, accompanied by supporting documentation and in accordance with its standard investigation practices for claims of this size and nature, plaintiff paid each of the claims. The total amount of claims paid by plaintiff on the Project was $28,211.80. Following payment, plaintiff made demands upon Romine for reimbursement based on the indemnity agreement which defendant had executed. Upon defendant’s refusal to pay, plaintiff filed this action to recover the above sum.

DISCUSSION

1. Validity of the Indemnification Agreement

Defendant attempts to avoid liability to plaintiff by contending that, although he executed the indemnification agreement at issue, it is not valid and enforceable due to a failure of consideration. Specifically, defendant contends plaintiff issued its bond to Norris prior to Romine’s execution of the indemnification agreement and that, consequently, there was no present consideration for his agreement to indemnify plaintiff. Defendant argues that the agreement was therefore nudum pactum; thus, unenforceable.

The facts which defendant has placed before the Court as support for this contention are problematic. The only evidence which defendant has mustered on this issue is in the form of hearsay statements contained in his own deposition, at pages 51-52, and in the second paragraph of his affidavit, in which he asserts that Aubrey Norris told him that Norris was working on the Project and already had been issued the bonds prior to Romine’s signing the indemnification agreement.

Fed.R.Civ.P. 56(e) provides that hearsay statements are not to be considered “facts” for purposes of a motion for summary judgment. 1 Thus, it is well established that hearsay evidence which is inadmissible in a trial of a case on the merits properly cannot be considered on a motion for summary judgment. See Broadway v. City of Montgomery, Ala., 530 F.2d 657 (5th Cir.1976); Horace Slay Auto Sales v. General Motors Corp., 495 F.Supp. 415 (S.D.Miss.1980). The statement attributed to Aubrey Norris in defendant’s affidavit, being offered for its truth, is clearly hearsay. 2 As *552 no hearsay exception exists which will permit the admission of this information for that purpose, it is not a fact which properly may be considered by the Court for purposes of this motion. See Broadway, supra.

In contrast to the inadmissible hearsay statements are the facts offered on this issue by plaintiff as supplied by the affidavit of Thomas Sheehan, a principal of Dixon Sheehan. That affidavit establishes, via Sheehan's personal knowledge, that Dixon Sheehan received the executed indemnification agreement prior to the issuance of plaintiffs bonds to Norris on the Project. Sheehan affidavit, paragraphs 7, 13.

Thus, the only facts properly before the Court clearly support a finding that defendant received present consideration in the form of the issuance of plaintiffs bond to Norris in exchange for his promise to indemnify plaintiff. The Court finds, therefore, that the indemnification agreement is valid and enforceable.

II. Liability for Claimed Amounts

Defendant also contends that the payments made by plaintiff in settlement of the claims of the six subcontractors on the Project were excessive and that he is, therefore, not required to indemnify plaintiff for those payments. Plaintiff shows that it settled the claims of the six contractors after due investigation and that, therefore, it is entitled to full indemnification from defendant. The Court agrees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western Surety Company v. Mooney Construction, Inc.
574 F. App'x 865 (Eleventh Circuit, 2014)
Haysman v. Food Lion, Inc.
893 F. Supp. 1092 (S.D. Georgia, 1995)
Transamerica Insurance v. H.V.A.C. Contractors, Inc.
857 F. Supp. 969 (N.D. Georgia, 1994)
Reliance Insurance Co. v. Ted O. Romine
888 F.2d 1344 (Eleventh Circuit, 1989)
Reliance Insurance v. Romine
888 F.2d 1344 (Eleventh Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
707 F. Supp. 550, 1989 U.S. Dist. LEXIS 1928, 1989 WL 18623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reliance-insurance-v-romine-gasd-1989.