Trapani Construction Company, Inc. v. The Elliot Group, Inc.

2016 IL App (1st) 143734, 64 N.E.3d 132
CourtAppellate Court of Illinois
DecidedSeptember 23, 2016
Docket1-14-3734
StatusUnpublished
Cited by12 cases

This text of 2016 IL App (1st) 143734 (Trapani Construction Company, Inc. v. The Elliot Group, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trapani Construction Company, Inc. v. The Elliot Group, Inc., 2016 IL App (1st) 143734, 64 N.E.3d 132 (Ill. Ct. App. 2016).

Opinion

2016 IL App (1st) 143734

FIFTH DIVISION September 23, 2016

No. 1-14-3734

TRAPANI CONSTRUCTION COMPANY, INC., an ) Appeal from the Illinois Corporation, ) Circuit Court of ) Cook County Plaintiff-Appellee, ) ) v. ) ) No. 09 CH 51534 THE ELLIOT GROUP, INC., an Illinois Corporation; ) ARLINGTON MARKET, LLC, an Illinois Limited ) Liability Company; and PARKWAY BANK AND ) TRUST, INC., ) ) Defendants ) Honorable ) Franklin U. Valderrama, (The Elliot Group, Inc., an Illinois Corporation, Defendant- ) Judge Presiding. Appellant).

JUSTICE REYES delivered the judgment of the court, with opinion. Justices Lampkin and Burke concurred in the judgment and opinion.

OPINION

¶1 Defendant The Elliot Group, Inc. (defendant), 1 a real estate developer, appeals on order

of the circuit court of Cook County entering judgment in favor of and awarding $257,764.70 to

plaintiff Trapani Construction Co., Inc. (plaintiff), a general contractor. On appeal, defendant

asserts the trial court erred in finding a contract implied in fact existed between the parties

because (1) defendant never accepted plaintiff’s offer to provide construction services, (2) an

1 Defendant is referred to as “The Elliott Group, Inc.,” in the parties’ briefs and the record on appeal. 1-14-3734

unsigned draft contract dated July 5, 2007, required defendant’s acceptance by signature, and (3)

defendant sufficiently disclosed to plaintiff it was acting as an agent of Arlington Market, LLC

(Arlington Market), the owner of the property. For the following reasons, we affirm.

¶2 I. BACKGROUND

¶3 In early July 2007, plaintiff sent a draft contract to defendant indicating plaintiff would

provide construction services to defendant on the property located at Kensington Road and

Dryden Road in Arlington Heights, Illinois (the property), for a project known as the “Arlington

Market Site Work” (the project). Defendant was listed as the project owner but did not sign the

contract. Nevertheless, plaintiff commenced and completed the work pursuant to the terms of the

contract. During the course of plaintiff’s performance, payments totaling $2,042,846.50 were

approved and made to plaintiff based on its payment requests to defendant. Plaintiff, however,

was not paid in full and requested defendant pay the remaining $257,764.70 for its work

performed on the project. Defendant refused.

¶4 On December 22, 2009, plaintiff filed a three-count complaint against defendant,

Arlington Market, and Parkway Bank & Trust Company (Parkway Bank), 2 alleging foreclosure

of mechanic’s lien (count I), breach of contract (count II), and unjust enrichment, in the

alternative (count III). Count I was dismissed by the trial court, and as a result Parkway Bank

was dismissed from the case. On April 22, 2014, a bench trial commenced on counts II and III.

On April 23, 2014, plaintiff dismissed its claim against Arlington Market and proceeded against

defendant alone. At the conclusion of plaintiff’s case-in-chief, defendant moved for a directed

verdict. The trial court denied defendant’s motion on count II. Plaintiff voluntarily dismissed

count III with prejudice. Thereafter, on May 7, 2014, plaintiff filed a one-count amended

2 Arlington Market and Parkway Bank are not parties to this appeal.

2 1-14-3734

complaint alleging that defendant’s refusal to pay the remaining $257,764.70 constituted a

breach of contract implied in fact.

¶5 No transcript of the bench trial appears in the record on appeal. The parties, however,

stipulated to a bystander’s report that summarized the trial proceedings pursuant to Illinois

Supreme Court Rule 323(c) (eff. Dec. 13, 2005), which was certified by the trial court. The

following facts were adduced at trial.

¶6 A. Plaintiff’s Evidence

¶7 Plaintiff presented the following evidence. Plaintiff had performed work for defendant as

a general contractor on other construction projects prior to this project. On these occasions,

plaintiff had performed under an unsigned contract and was paid in excess of $18 million by

defendant for its work. Similarly, plaintiff performed under an unsigned contract and was paid in

full by defendant for its work on a separate building, which was another part of this project.

¶8 On March 1, 2007, plaintiff submitted a proposal to defendant to provide construction

services for this project. The proposal indicated plaintiff had “[e]specially prepared” the proposal

for “Mr. Lou Elliott, The Elliott Group.” Thereafter, plaintiff sent five draft contracts to

defendant indicating plaintiff would provide construction services to defendant for the work at

issue. 3 Defendant was listed as a contracting party in all five draft contracts. None of the draft

contracts were ever executed.

¶9 The last draft contract forwarded to defendant by plaintiff was dated July 5, 2007.

Plaintiff’s witnesses testified defendant had provided plaintiff with landscape drawings and civil

drawings for the work at issue and that the drawings were attached to and made part of the draft

contract dated July 5, 2007. Plaintiff’s proposal was also attached to the draft contract as a

3 Plaintiff presented evidence that a “series of draft *** contracts” were sent to defendant. The record indicates plaintiff sent five draft contracts.

3 1-14-3734

“contract document.”

¶ 10 Plaintiff’s witnesses testified that, in early July 2007, plaintiff commenced performing on

the work at issue. 4 Plaintiff’s witnesses further testified the project specifications were provided

by defendant and prepared by third parties hired by defendant. The project specifications

indicated they were prepared at the request of defendant or the Elliott Home Builders. Plaintiff’s

witnesses asserted plaintiff performed pursuant to the terms and specifications of the draft

contract dated July 5, 2007, and the attached documents.

¶ 11 Plaintiff’s witnesses also testified plaintiff followed the procedures set out in the draft

contract dated July 5, 2007, to obtain payment. The payments were made periodically. For each

payment request plaintiff sent to defendant during the course of plaintiff’s performance, plaintiff

submitted to defendant a contract activity report, a certificate for payment, an application and

certification for payment, an application and certificate for payment, and lien waivers. All

documents listed defendant and plaintiff as the contracting parties and defendant as the project

owner. Payments totaling $2,042,846.50 were approved and tendered to plaintiff based on the

payment requests addressed to defendant. The contract amount on the draft contract dated July 5,

2007, matched the amounts on the payment requests and lien waivers plaintiff submitted to

defendant.

¶ 12 Maria Weisbruch (Weisbruch), plaintiff’s employee, testified she prepared the documents

for the payment requests. She stated that Mark Elliott, the president of defendant, would review

the payment requests and other related documents with her. Weisbruch further testified

defendant would “meticulously review” the payment requests and would often require changes in

them before plaintiff was paid. David Cartwright (Cartwright), plaintiff’s senior vice president,

4 The record does not indicate which witnesses provided this testimony.

4 1-14-3734

testified defendant discussed the payment requests with plaintiff. 5 Defendant did not deny

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McDunn v. McDunn
Appellate Court of Illinois, 2026
Hill v. Shaffer
S.D. Illinois, 2022
Lynnardio Dean v. REM Staffing
Seventh Circuit, 2021
People ex rel. Department of Human Rights v. Oakridge Nursing & Rehab Center
2019 IL App (1st) 170806 (Appellate Court of Illinois, 2019)
Marque Medicos Archer, LLC v. Liberty Mutual Insurance Company
2018 IL App (1st) 163351 (Appellate Court of Illinois, 2018)
BMO Harris Bank, N.A. v. Porter
2018 IL App (1st) 171308 (Appellate Court of Illinois, 2018)
Rishell v. Alvion Properties, Inc.
569 B.R. 322 (S.D. Illinois, 2017)
Trapani Construction Co.3-2573, Inc. v. Elliot Group, Inc.
2016 IL App (1st) 143734 (Appellate Court of Illinois, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2016 IL App (1st) 143734, 64 N.E.3d 132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trapani-construction-company-inc-v-the-elliot-group-inc-illappct-2016.