Transwestern Pipeline Company v. 17.19 Acres of Property

CourtCourt of Appeals for the Ninth Circuit
DecidedDecember 11, 2008
Docket08-15991
StatusPublished

This text of Transwestern Pipeline Company v. 17.19 Acres of Property (Transwestern Pipeline Company v. 17.19 Acres of Property) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transwestern Pipeline Company v. 17.19 Acres of Property, (9th Cir. 2008).

Opinion

FOR PUBLICATION UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT

TRANSWESTERN PIPELINE COMPANY,  LLC, a Delaware limited liability company, Plaintiff-Appellant, v. No. 08-15991 17.19 ACRES OF PROPERTY LOCATED IN MARICOPA COUNTY,  D.C. No. 2:08-cv-00033-JWS more or less; AGUA FRIA INVESTMENTS, LLC, a Delaware OPINION limited liability company; FIRST NATIONAL BANK OF OLATHE, a Kansas corporation; J. LAWRENCE MCCORMLEY, Defendants-Appellees.  Appeal from the United States District Court for the District of Arizona John W. Sedwick, District Judge, Presiding

Submitted December 1, 2008* Pasadena, California

Filed December 11, 2008

Before: Harry Pregerson, Cynthia Holcomb Hall and N. Randy Smith, Circuit Judges.

Opinion by Judge Hall

*This panel unanimously agrees that this case is appropriate for submis- sion without oral argument pursuant to Fed. R. App. P. 34(a)(2).

16281 TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY 16283

COUNSEL

John C. Lemaster, Ryley Carlock & Applewhite, Phoenix, Arizona, and Jeffrey L. Hinds, Bricklemyer Smolker & Bolves, P.A., Tampa, Florida, for the appellant. 16284 TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY Steven A. Hirsch, Bryan Cave LLP, Phoenix, Arizona, for the appellees.

Kenneth B. Bley, Cox, Castle & Nicholson LLP, Los Ange- les, California, for the amici curiae.

OPINION

HALL, Senior Circuit Judge:

Transwestern Pipeline Co. (Transwestern) appeals the dis- trict court’s denial of its preliminary injunction motion seek- ing immediate possession of appellee landowners’ parcels of land. As a holder of a valid Federal Energy Regulatory Com- mission (FERC) certificate, Transwestern claims it is entitled to condemn appellees’ land pursuant to § 717f(h) of the Natu- ral Gas Act (NGA). The district court denied the injunction, holding that, until condemnation proceedings are completed, Transwestern maintains no substantive right of possession and therefore the district court lacked authority to grant prelimi- nary equitable relief. The district court had jurisdiction pursu- ant to 15 U.S.C. § 717f(h) and 28 U.S.C. § 1331. We have jurisdiction pursuant to 28 U.S.C. § 1292(a)(1). We affirm and hold that, until an order of condemnation issues pursuant to the requirements of 15 U.S.C. § 717f(h), Transwestern has no substantive right of possession.

I. Background

Transwestern owns and operates natural gas pipelines serv- ing much of the Southwest. Following the review of its appli- cation and completion of public hearings, the Federal Energy Regulatory Commission (FERC) issued a Certificate of Public Convenience and Necessity (the Certificate) approving Trans- western’s proposed construction and expansion of a natural gas pipeline to meet the demands of a growing Phoenix mar- TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY 16285 ket. The Certificate provided that Transwestern was to com- plete the construction within one year of issuance, or by November 15, 2008.1

Several property owners affected by the Certificate, most prominently the Town of Buckeye, Arizona, opposed the Cer- tificate’s issuance and filed a petition for rehearing of the Cer- tificate with FERC. The petition alleged insufficient process in approving the Certificate and requested that the proposed pipeline route bypass a number of master planned communi- ties. FERC denied the petition for rehearing, see 2008 WL 461054 (F.E.R.C.) and, pursuant to the process outlined by the Natural Gas Act (NGA), several petitioners appealed the denial to the D.C. Circuit. See 15 U.S.C. § 717r. These appeals have since been dismissed during the pendency of this appeal. See Town of Buckeye v. F.E.R.C., No. 08-1126 (D.C. Cir. filed June 27, 2008); El Paso Natural Gas Co. v. F.E.R.C., No. 08-1161 (D.C. Cir. filed Aug. 25, 2008).2

Because neither the rehearing nor the appeal automatically stayed the Certificate’s enforcement, see § 717r(c), Transwes- tern continued to pursue its construction objectives through- out this time. Transwestern was able to reach an agreement on an easement price with most of the 897 affected landowners. With regard to the remaining 129 parcels, Transwestern filed condemnation actions in the district court of Arizona. The NGA authorizes FERC Certificate holders to acquire neces- 1 The ramifications of a possible delay in completion are uncertain, how- ever, as 18 C.F.R. § 157.20(b) (1999), as cited in the Certificate, appears only to require that Transwestern notify FERC within ten days of expira- tion of the Certificate if it is unable to meet the imposed timetable to com- mence service. During the pendency of this appeal, Transwestern was, in fact, able to obtain an extension with FERC to complete the project by a revised deadline of April 15, 2009. 2 On August 25, 2008, the El Paso National Gas Company appeal was placed in abeyance, pending the completion of a proposed sale. 16286 TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY sary land by the exercise of the right of eminent domain, after negotiations with affected landowners fail. § 717f(h).3

After consolidating the actions, Transwestern sought a pre- liminary injunction to obtain immediate possession of the contested parcels. Transwestern claimed entitlement to relief under the court’s equitable powers and, specifically, Rule 65 of the Federal Rules of Civil Procedure. Transwestern argued that the FERC certificate and NGA § 717f(h) guaranteed its success on the merits, and it would suffer irreparable harm if it could not take possession immediately, citing construction delays and resulting expenses, the necessity of complying with the timeline provided by the Certificate, its desire to meet contractual forecasts with suppliers and customers, and the public interest in getting the pipeline in service before fall 2008. The landowners argued the Certificate was improperly granted and also contested the severity and nature of Trans- western’s harm. They argued primarily that any harm incurred by Transwestern was illusory and created by Transwestern’s own choice to prematurely enter contracts, and that Transwes- tern could easily obtain an extension of the FERC deadline. 3 15 U.S.C. § 717f

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Natural Gas Co. v. Land, Cullman County
197 F.3d 1368 (Eleventh Circuit, 1999)
Catlin v. United States
324 U.S. 229 (Supreme Court, 1945)
United States v. 93.970 Acres of Land
360 U.S. 328 (Supreme Court, 1959)
Califano v. Yamasaki
442 U.S. 682 (Supreme Court, 1979)
Kirby Forest Industries, Inc. v. United States
467 U.S. 1 (Supreme Court, 1984)
Northern Border Pipeline Co. v. 127.79 Acres of Land
520 F. Supp. 170 (D. North Dakota, 1981)
City of Oakland v. United States
124 F.2d 959 (Ninth Circuit, 1942)
United States v. Fisk Building
99 F. Supp. 592 (S.D. New York, 1951)
Humphries v. Williams Natural Gas Co.
48 F. Supp. 2d 1276 (D. Kansas, 1999)
Northern Border Pipeline Co. v. 64.111 Acres of Land
125 F. Supp. 2d 299 (N.D. Illinois, 2000)
Guardian Pipeline, L.L.C. v. 950.80 Acres of Land
210 F. Supp. 2d 976 (N.D. Illinois, 2002)
Stanley v. University of Southern California
13 F.3d 1313 (Ninth Circuit, 1994)
East Tennessee Natural Gas Co. v. Sage
361 F.3d 808 (Fourth Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Transwestern Pipeline Company v. 17.19 Acres of Property, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transwestern-pipeline-company-v-1719-acres-of-prop-ca9-2008.