TransCanada Pipelines Ltd. v. UsGen New England, Inc.

458 B.R. 195, 2011 U.S. Dist. LEXIS 97255, 2011 WL 3880402
CourtDistrict Court, D. Maryland
DecidedAugust 30, 2011
DocketCivil PJM 10-1464
StatusPublished
Cited by2 cases

This text of 458 B.R. 195 (TransCanada Pipelines Ltd. v. UsGen New England, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TransCanada Pipelines Ltd. v. UsGen New England, Inc., 458 B.R. 195, 2011 U.S. Dist. LEXIS 97255, 2011 WL 3880402 (D. Md. 2011).

Opinion

OPINION

PETER J. MESSITTE, District Judge.

TransCanada Pipelines Ltd. (“TransCa-nada”) has appealed a decision of the United States Bankruptcy Court, rendered following a nine-day bench trial, issued in In re USGen New England, Inc. (“USGen”), Reorganized Debtor, Case No. 03-30465 (Bankr. Md.). USGen has cross-appealed. The Court has jurisdiction over the parties’ appeals pursuant to 28 U.S.C. § 158(a). For the following reasons, the Court AFFIRMS the decision of the Bankruptcy Court in its entirety.

I.

The facts of the case are set out in great detail in the Bankruptcy Court’s opinion of April 1, 2010. See In re USGen New England, Inc., Reorganized Debtor, 429 B.R. 437 (Bankr.Md.2010). Rather than engaging in a similarly exhaustive recitation here, the Court will relate only those facts it considers critical to the disposition of this appeal. The Court will begin with a synopsis of the undisputed and disputed facts, summarize the findings of the Bankruptcy Court that have been challenged on appeal, then address the Bankruptcy Court’s ultimate conclusions.

A.

The undisputed facts are these:

TransCanada is a Calgary, Alberta-based company engaged in the natural gas pipeline business. Among other activities, it owns and operates the Canadian Mainline pipeline (the “Mainline”), a 14,898-kilometer natural gas transmission system that extends from the Alberta-Saskatchewan border in the west to the Quebec-Vermont border in the east, where it connects with other natural gas pipelines in Canada and the United States. The Mainline transports natural gas from west to east using a series of compressors installed at various points along its path. TransCa-nada contracts with customers, known as “shippers,” who provide natural gas for TransCanada to transport at specified receipt points; TransCanada then delivers the gas in the amounts provided at delivery points designated by contract. Generally speaking, a shipper pays a charge, known as a demand toll, for the right to ship gas up to a maximum amount specified in its contract with TransCanada. *201 The toll is based primarily on the distance between the receipt point and the delivery point, multiplied by a contracted-for quantity of gas measured in gigajoules per day (“GJ/d”). 1 Whenever a shipper actually ships natural gas — i.e., when it “nominates” its contracted-for use — it pays an additional charge based on the quantity of natural gas shipped, which is also measured in GJ/d. 2

TransCanada sells most of its capacity on the Mainline through an auction process known as an “existing capacity open season.” By posting an existing capacity open season notice, TransCanada announces to potential shippers the amount of capacity available along a particular segment of the Mainline and specifies the date by which bids for that capacity must be received. At the close of an existing capacity open season, TransCanada ranks the bids submitted and awards posted capacity in accordance with procedures outlined in its Transportation Ac-eess Procedure (the “TAP”). The bid-ranking procedures are designed to maximize TransCanada’s revenue over the long term and ensure that capacity is awarded to the shippers that desire it the most.

Most of TransCanada’s operations, including operation of the Mainline, are regulated by the National Energy Board of Canada (the “NEB”). Among other things, the NEB: (1) reviews and approves, for each calendar year, the tolls that TransCanada will charge its shippers for the transport of natural gas along the Mainline; 3 (2) imposes upon TransCanada a “duty of prudence” that requires it to make every effort to minimize its tolls and recover unmitigated damages from defaulting shippers; 4 and (3) approves the bid-ranking procedures outlined in the TAP.

Pursuant to this regulatory scheme, TransCanada may not ordinarily sell capacity on the Mainline unless it first posts *202 the capacity for sale during an existing capacity open season. However, if Trans-Canada determines that projected future demand for its pipeline services necessitates an expansion of its long-term capacity on the Mainline, and if it intends to submit to the NEB an application for authorization to construct new facilities or otherwise expand its capacity, it must issue notice of a “new capacity open season.” When TransCanada announces a new capacity open season, it informs potential shippers that additional capacity will be available for sale beginning on some specified future date and announces the time period during which bids for the new capacity will be accepted. Pursuant to NEB-approved procedures, shippers applying for new capacity service must submit certain documentation with their bids showing, among other things, evidence of their need for gas transport services during the timeframes contemplated in their bids.

Although expansion of capacity via the construction of new facilities requires NEB approval, TransCanada may, without regulatory approval, temporarily increase capacity on the Mainline through a mechanical alteration process known as “re-aeroing.” As noted supra, the Mainline transports natural gas from west to east using a series of compressors installed at various points along its path. TransCana-da may “re-aero” — i.e., mechanically alter — any one of these compressors either to: (1) increase pipeline efficiency and operational flexibility, with a resulting reduction in pipeline capacity; or (2) increase pipeline capacity, but with a resulting reduction in pipeline efficiency and operational flexibility. 5 Although the cost and effort incurred in the re-aeroing of a compressor will vary depending upon the circumstances, the process can, under favorable conditions, take as little as three to four days to complete.

USGen was a Bethesda, Maryland-based energy company that owned electricity-generating facilities in New England and bought and sold electricity and energy-related products. Beginning in 1992, US-Gen entered into a contract with TransCa-nada, whereby USGen reserved 53,904 GJ/d of capacity on the Mainline from a receipt point at Empress, Alberta to a delivery point near Waddington, New York (the “Empress to Iroquois path”). The contract, which was to run from early 1992 through October 31, 2006, obligated US-Gen to pay demand tolls reflecting the cost of transporting gas from Empress to Iroquois, as well as a commodity charge whenever it actually shipped gas. The contract is governed by Canadian law.

On July 8, 2003 (the “petition date”), USGen filed a voluntary petition in the Bankruptcy Court of this District, seeking relief under Chapter 11 of the Bankruptcy Code. 6 Shortly thereafter, on August 12, 2003, USGen asked the Bankruptcy Court to reject its contract with TransCanada, pursuant to 11 U.S.C. § 365.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
E.D. Wisconsin, 2026
Wilmington Trust Co. v. AMR Corp. (In re AMR Corp.)
490 B.R. 470 (S.D. New York, 2013)
Securities & Exchange Commission v. Razmilovic
822 F. Supp. 2d 234 (E.D. New York, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
458 B.R. 195, 2011 U.S. Dist. LEXIS 97255, 2011 WL 3880402, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcanada-pipelines-ltd-v-usgen-new-england-inc-mdd-2011.