Trans-Care, Inc. v. BD. OF COM'RS OF CTY. OF VERMILLION

831 N.E.2d 1255, 2005 Ind. App. LEXIS 1440, 2005 WL 1877337
CourtIndiana Court of Appeals
DecidedAugust 10, 2005
Docket83A01-0501-CV-41
StatusPublished
Cited by13 cases

This text of 831 N.E.2d 1255 (Trans-Care, Inc. v. BD. OF COM'RS OF CTY. OF VERMILLION) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trans-Care, Inc. v. BD. OF COM'RS OF CTY. OF VERMILLION, 831 N.E.2d 1255, 2005 Ind. App. LEXIS 1440, 2005 WL 1877337 (Ind. Ct. App. 2005).

Opinion

OPINION

BARNES, Judge.

Case Summary

Trans-Care, Inc. appeals the trial court's grant of summary judgment in favor of the Board of Commissioners of Vermillion County ("the Commissioners" or "the County") and Paul Lee, d/b/a Vermillion County EMS. We affirm.

Issue

The dispositive issue is whether Trans-Care had standing to challenge the County's award of a contract to Lee for the provision of emergency ambulance services.

Facts

In December 1999, the County awarded Trans-Care a contract to provide emer-geney ambulance or medical services ("EAS" or "EMS") for the years 2000, 2001, and 2002. Trans-Care is located in Terre Haute, Vigo County. In mid-2002, the County published notice of its intent to accept sealed bids for the provision of EAS for the years 2008, 2004, and 2005. Trans-Care, Lee, and Providence Medical Group ("Providence") submitted bids to provide EAS as requested. At the time the bids were submitted, only Trans-Care was certified by the State Emergency Management Agency ("SEMA") as an EAS/EMS provider, pursuant to state statutes and regulations. Neither Lee nor Providence had any EAS experience, equipment, or employees at the time.

On June 25, 2002, the Commissioners opened the EAS bids. Providence, the low bidder, was awarded the contract. On September 17, 2002, Trans-Care filed a declaratory judgment action against the County and Providence seeking to void Providence's contract. At a December 3, 2002 executive meeting of the Commissioners, Providence asked to be released from its contract. The Commissioners did so, and also rejected the first bids of Trans-Care and Lee.

On December 11, 2002, Trans-Care and Lee submitted new proposals for providing EAS in the County to the Commissioners. These proposals did not come in the form of sealed bids. At the conclusion of this meeting, Lee was awarded the contract. (On December 830, 2002, SEMA approved Lee, d/b/a Vermillion County EMS, as a certified EAS/EMS provider in accordance with state law. Lee began providing EAS service in the County in January 20083.

Also in January 2003, Providence was dismissed as a defendant in Trans-Care's still pending declaratory judgment action. Trans-Care later sought and was granted permission to file a first, then second amended complaint that specifically attacked the contract awarded to Lee and sought to invalidate that contract. The trial court also required Trans-Care to name Lee as an additional defendant. On August 11, 2004, Trans-Care moved for summary judgment. The County and Lee responded with cross-motions for summary judgment. On January 10, 2005, the trial court denied Trans-Care's summary judgment motion and granted the County's and Lee's cross-motions for summary judgment, disposing of all of Trans-Care's claims. Trans-Care now appeals.

*1258 Analysis

"Summary judgment is appropriate only where there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law." Save The Valley, Inc. v. Indiana-Kentucky Elec. Corp., 820 N.E.2d 677, 679 (Ind.Ct.App.2005), aff'd on rehearing, 824 N.E.2d 776 (Ind.Ct.App.2005), trans. pending. All facts and reasonable inferences drawn from those facts are construed in favor of the nonmoving party. JSV, Inc. v. Hene Meat Co., Inc., 794 N.E.2d 555, 560 (Ind.Ct.App.2003). Further, although they may assist our review, we do not owe deference to the findings and conclusions entered by the trial court here in its summary judgment order. See Save the Valley, 820 N.E.2d at 679. Instead, we may affirm on any ground or theory supported by the designated evidence. Malone v. Price, 755 N.E.2d 213, 216 (Ind.Ct.App.2001). The question of standing presents an issue of law. See Embry v. O'Bannon, 798 N.E.2d 157, 159 (Ind.2008).

Indiana Code Section 34-14-1-2, part of the Declaratory Judgment Act, provides:

Any person interested under a deed, will, written contract, or other writings constituting a contract, or whose rights, status, or other legal relations are affected by a statute, municipal ordinance, contract, or franchise, may have determined any question of construction or validity arising under the instrument, statute, ordinance, contract, or franchise and obtain a declaration of rights, status, or other legal relations thereunder.

The basis of jurisdiction under the Declaratory Judgment Act is the existence of a justiciable controversy or question, which is clearly defined and affects the legal right, the legal status, or the legal relationship of parties having adverse interests. Little Beverage Co., Inc. v. DePrez, 777 N.E.2d 74, 83 (Ind.Ct.App.2002), trans. denied. A primary requirement of the Act is that a plaintiff demonstrate that it has standing for the relief requested. Id. The relief Trans-Care sought was invalidation of the EMS contract between the County and Lee.

The primary cases concerning standing in lawsuits such as Trans-Care's, where a bidder has not been awarded a local government contract, have addressed construction bidding governed by the Indiana Public Purchasing laws now found in Article 5-22 of the Indiana Code. See Brownsburg Cmty. Sch. Corp. v. Natare Corp., 824 N.E.2d 336, 338-39 (Ind.2005); All-Star Constr. & Excavating, Inc. v. Bd. of Pub. Works, 640 N.E.2d 369, 370 (Ind. 1994), Shook Heavy & Einutl Constr. Group v. City of Kokomo, 682 N.E.2d 355, 358 (Ind.1994). These cases all clearly hold that only a citizen or taxpayer of the locality may challenge the award of a contract under these laws and the Public Lawsuit Statute, now located at Indiana Code Chapter 34-13-5. 1 The losing bidder does not have standing to do so, unless it is also a citizen or taxpayer of the locality. See Natare, 824 N.E2d at 8388-39. Trans-Care is not a citizen or taxpayer of Vermillion County, but apparently of Vigo County.

Additionally, the parties agree that a contract for the provision of EMS is one *1259 for personal services. The award of such a contract is not governed by the strict bidding procedures outlined by the Public Purchasing laws. Instead, "The purchasing agency of a governmental body may purchase services using any procedure the governmental body or the purchasing agency of the governmental body considers appropriate." Ind.Code $ 5-22-6-1. As our supreme court has observed, "procurement of personal services ... are not included within the seope of the Public Purchasing Statute and, therefore, not subject to it." Shook, 682 N.E.2d at 357.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
831 N.E.2d 1255, 2005 Ind. App. LEXIS 1440, 2005 WL 1877337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trans-care-inc-v-bd-of-comrs-of-cty-of-vermillion-indctapp-2005.