Tracy v. C. M. McClung Company

285 S.W. 956, 215 Ky. 632, 1926 Ky. LEXIS 751
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedJune 8, 1926
StatusPublished
Cited by1 cases

This text of 285 S.W. 956 (Tracy v. C. M. McClung Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tracy v. C. M. McClung Company, 285 S.W. 956, 215 Ky. 632, 1926 Ky. LEXIS 751 (Ky. 1926).

Opinion

Opinion op the Court by

Judge MoCandless—

Affirming.

J. C. Tracy, a resident of Corbin, Ky., during the year 1922, erected a large apartment building in tbe city of Corbin, and in the month of August placed an order with C. M. McClung & Company, a wholesale dealer of Knoxville, Tenn., to furnish the heating and plumbing’ materials to be used in its construction. It appears that the company estimated and fixed the price on the heating material and drew plans for its installation from the blue prints of the building and that Tracy’s plumber made a list of plumbing material, Tracy signing and giving to -the salesman a blank order for the material which was to be shipped as specifically ordered. The first specific order was dated the 19th of September. Various other orders were made from time to time during the intervening months running through December into January, and a *634 large amount of correspondence ensued in which he was requesting that shipments he expedited, the building being occupied about the first of May. Trouble arose over the adjustment of accounts and in April,-1924, McClung & Company sued at law for the balance due it. Later it filed an amended petition.setting out a material lien which it had properly recorded and on motion the case was transferred to equity. Tracy filed an answer and counterclaim in three paragraphs, a demurrer being sustained to the first and third paragraphs, whereupon he filed an amendment to each paragraph. Demurrers were sustained to paragraphs one and three as amended and the third was dismissed, though the first was apparently treated as if the demurrer had been overruled. Evidence was taken on all questions during preparation of the pleadings, plaintiff having concluded and the defendant having taken the principal part of his evidence before the demurrer was sustained to- paragraphs one and three of the answer as amended. Before submission, but after the completion of the evidence, defendant moved to transfer the action to the ordinary docket for a trial of the question of damages, and this was overruled. On final hearing the court rendered judgment in favor of the platintiff for $2,909.09, the amount of its claim, including interest after maturity of bills; and allowed defendant $213.89 on his counterclaim, to be credited on the principal judgment. It also adjudged the enforcement of the material lien on the house and lot. The defendant excepted to 'all .adverse rulings and appeals.

(1) Plaintiff pleaded that the goods it furnished amomited to $4,683.52, upon which defendant had paid $1,939.85, leaving a balance of $2,743.73, and that the accrued interest to May 20, 1923, amounted to $29.80, making a total of $2,773.49, for which it prayed judgment, with interest from May 20,1923. In its amended petition the interest was computed to April 4, 1924, aggregating $179.00, and leaving a total balance of $2,909.08, for which it asked judgment from April 4, 1924. Defendant admited the accuracy of the charges and credits, but in effect denies the interest charge and the allowance of this is assigned as error. The evidence shows that plaintiff’s regular terms are sixty days “with interest charged after maturity,” and indicates that demand was made for payment prior to May 20, 1923, and it can hardly be said the judgment is not sustained by the pleadings, hence this point is not well taken. Henderson Cotton *635 Mfg. Co. v. Lowell Machine Shops, 86 Ky. 668; Magruder v. Ericson, 146 Ky. 89; Supreme Lodge of K. & H. v. Lapp, 25 Rep. 74; McKinney Dep. Bank v. Scott, 207 Ky. 340; Miller v. Winter, 206 Ky. 377; Royster v. Waller, 186 Ky. 476.

(2) In the second paragraph of the answer as amended the defendant alleged that at the time he gave plaintiff the contract, two-thirds of the construction work had been done on the building; that he informed the plaintiff’s agent that it was to be completed by the first of December; that the apartments were to be occupied by tenants and that he was desirous of contracting with a firm that could furnish the material as he needed it, so as to assure its completion at the date mentioned; that the agent represented to him that the plaintiff had all of the material necessary in stock at its plant in Knoxville, which.was sufficiently near for it to 'be furnished at once as ordered and that this was the moving consideration in the contract. Further allegations of that paragraph related to defective material and inconvenience caused workmen by delay in shipment of material, to which reference will later be made. In the third paragraph damages were sought for loss of rents between December 1st and May 1st, it being alleged that defendant could have completed the building on that date and have rented it continuously afterward at the rate of $550.00 per month, but for the delay in the delivery of this material.

The alleged contract was not set out in this paragraph, but the second paragraph was made a part of it by reference in these words; “The defendant here reiterates-all the allegations of this statement to the second paragraph of this answer, set-off and counterclaim, and adopts same as an amendment to the third paragraph of the said answer, set-off and counterclaim as fully as if rewritten herein.” A demurrer was sustained to this paragraph and defendant refusing to plead further it was dismissed, and this is relied upon as error.

There is some confusion in our practice as to whether a paragraph of a pleading may be incorporated in and made a part o'f another paragraph by reference; and our decisions on this question are not entirely harmonious. -Sec. 113, subsection 3 of the Civil Code provides :

“If there be more than one cause of action or defense, each.must be distinctly stated in a separate *636 numbered paragraph; and either, which is intended to respond to part only of an adverse pleading must show to what part it is responsible. ... ”

This section is thus construed ’by Mr. Newman:

“Moreover, each paragraph or separate defense must be complete in itself without reference to others. It is true that defendant need not repeat in each paragraph the same allegations where the same facts are alike applicable to several causes of action or defenses, but having averred them in one paragraph or by way of introduction to all he may refer to them in such distinct and intelligible language as to include or incorporate them into each of the paragraphs or defenses. Each of the separate paragraphs must be a sufficient defense to the cause of action which it purports to answer and the • averments of one paragraph or defense cannot, it would seem, on demurrer be brought in aid of the allegations in another without appropriate reference to such other averments.” Newman on Pleading & Prac tice, sec. 426d.

No authority is cited in support of the text, but it is in line with Day v. Clark, 1 A. K. Marshall 521, though this was written before the code. This case is also cited as the basis of the text in 31 C. J., page 47, in which the rule is thus laid down:

“Facts which are alleged in other pleadings in the same cause may be made a part of the pleadings by expressly adopting them. Thus one defendant may adopt the answer of another defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Princeton v. Baker
35 S.W.2d 524 (Court of Appeals of Kentucky (pre-1976), 1931)

Cite This Page — Counsel Stack

Bluebook (online)
285 S.W. 956, 215 Ky. 632, 1926 Ky. LEXIS 751, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tracy-v-c-m-mcclung-company-kyctapphigh-1926.